2SUMMER 2004 PROJECTS
1. Roofing a. Crestview Elementary
School b. Hapgood Elementary School c. La Honda
Elementary School d. Los Padres Elementary
School 2. Lompoc High School Parking Lot Paving
3SUMMER 2004 PROJECTS
3. Vandenberg Middle School Technology 4.
Wide Area Network District Wide 5.
District-Wide Phone System 6. Lompoc Valley
Middle School Shade Structure 7. Interim Portable
Classroom Planning
4MODERNIZATION SCHEDULE
Series One Schools Construction First Quarter
2005 Fillmore Elementary School Submitted to
DSA 4/20/04 Clarence Ruth Elementary
School Submitted to DSA 4/20/04 La Canada
Elementary School Submitted to DSA
4/20/04 Lompoc Valley Middle School Submit to
DSA 6/15/04 Lompoc High School Submit to DSA
7/7/04
5MODERNIZATION SCHEDULE
Series Two Schools Crestview Elementary
School Submit to DSA 7/15/04 Buena Vista
Elementary School Submit to DSA 7/15/04 Los
Berros Elementary School Submit to DSA
7/15/04 Hapgood Elementary School Submit to DSA
7/15/04 Vandenberg Middle School Submit to DSA
6/15/04 Cabrillo High School Submit to DSA
7/7/04
6MODERNIZATION SCHEDULE
Series Three Schools Los Padres Elementary
School Submit to DSA 7/15/04 Miguelito
Elementary School Submit to DSA 7/15/04 La
Honda Elementary School Submit to DSA 7/15/04
El Camino Middle School Submit to DSA 6/15/04
Maple High School Submit to DSA 7/7/04
7RECENT ACTIVITY
- Site Reviews - All Phase One Sites
- On site reviews with principals and staff
- Final interim housing review
- Review technology work
- Summer 2004 on-site drawing back-check
8CURRENT FOCUS
- 5/12/04 Cost Estimate Report Budget Review
- Six Elementary Schools
- Los Berros, La Canada, Fillmore, Clarence Ruth,
Buena Vista, and Los Padres. Based on DSA
submittal drawings. - Three High Schools
- Estimates are based on the 50 drawing
submittals. - The detailed estimates are now being reviewed by
each engineering consultant. Back check exercise. - Revising the scope to match the overall budget
and still maintain equity between the sites.
9BUDGET ADJUSTMENT
- 100 infrastructure is currently included
- 10 market factor
- Value engineering
- Bid alternatives
- Bundling
10TEAM GOALS
- It is critical to stay on schedule with all DSA
submittals. - The design team is looking at ways to meet the
budget. - Meeting with general contractors.
- Reviewing each sites greatest need.
11Thank You. Kruger Bensen Ziemer Architects, Inc.
30 West Arrellaga Street, Santa Barbara, CA 93101
Phone 805.963-1726 6477 Telephone Road,
Ventura, CA 93003 Phone 805.650-1033
12RECENT BIDS
Goleta Union School District bid results from
9/16/03
Hollister Elementary School (4) Bids Bid
Date 9/4/01 Average Bid 1,100,000.00 F
inished Cost 1,056,204.00 Kellogg
Elementary School (5) Bids Bid Date
6/5/02 Average Bid 1,140,000.00 Finishe
d Cost 1,060.000.00 La Patera Elementary
School (1) Bid Bid Date 7/8/03 A.J.
Diani 1,785,000.00 (3) Bids ReBid Date
9/16/03 A.J. Diani 1,920,000.00 F.
Schipper 1,866,249.00 Carroll
1,774,577.00
13RECENT BIDS
San Marcos High School Field restroom
renovation Bid Date 1/15/04
159,000 Rebid Date 5/20/04 208,814
30 increase