Perceptions on Bridge Painting Costs: Update on FHWA Study - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Perceptions on Bridge Painting Costs: Update on FHWA Study

Description:

The 36th Annual Mid-Atlantic Quality Assurance Workshop. Charleston, WV. February 12, 2003. Presented by: Bill Shoup Bernard Appleman. Executive Director Vice ... – PowerPoint PPT presentation

Number of Views:52
Avg rating:3.0/5.0
Slides: 22
Provided by: SSPC
Category:

less

Transcript and Presenter's Notes

Title: Perceptions on Bridge Painting Costs: Update on FHWA Study


1
Perceptions on Bridge Painting Costs Update on
FHWA Study
  • The 36th Annual Mid-Atlantic Quality Assurance
    Workshop
  • Charleston, WV
  • February 12, 2003
  • Presented by
  • Bill Shoup Bernard Appleman
  • Executive Director Vice
    President
  • SSPC KTA-Tator, Inc.

2
Outline of Topics
  • Background
  • Perceptions about painting
  • Status of FHWA Cost Study
  • Conclusion

3
Background
  • Steel must compete with concrete
  • 2 options for corrosion protection
  • Painting
  • Unpainted weathering steel

4
Perceptions About Painting
  • Difficult to do correctly by shops
  • Adds considerably to cost of fabrication
  • Adds considerable to time of fabrication
  • Causes environmental headaches
  • Makes steel less competitive

5
Responding to perceptions
  • Perception 1 Difficult to do correctly by shops
  • Response 1 Improve effectiveness of shop
    painting
  • Identify road blocks (e.g., unnecessary
    requirements by specifiers)
  • Identify and disseminate best practice
    (guidelines, information sharing, benchmarking)
  • Training of managers, operators, inspectors

6
Responding to Perceptions
  • Perception 2 Adds considerably to cost of
    fabrication
  • Response 2 Develop valid cost data
  • Discussed later

7
Responding to Perceptions
  • Perception 3 Adds considerably to time of
    fabrication
  • Response 3 Identify fast thru-put coatings
  • Modified polyurea metallic, powder
  • Need to verify performance (e.g., NTPEP testing)

8
Centrifugal Wheel Blast Unit A large beam is
supported by an overhead crane and carried
through a centrifugal wheel blast unit.
9
A painter checks the wet film thickness of the
topcoat on the lower flange of a large beam
(foreground). Two painters apply a zinc-rich
primer to a similar beam (background).
10
Responding to Perceptions
  • Perception 4 Causes environmental headaches
  • Response 4 Develop zero VOC coatings
  • 100 solids powder coatings, thermal spray
    metallic
  • Low VOC and low HAP coatings as possible interim
    step

11
Responding to Perceptions
  • Perception 5 Makes steel less competitive
  • Response 5 Provide valid life cycle cost data
  • Need good data on
  • Fabrication and installation
  • Coating lifetime
  • Maintenance cost
  • Alternatives (unpainted steel, concrete,
    composites)
  • Cost models available (FHWA and others)

12
Status on FHWA Study on Painting Costs
  • Objective
  • Determine the costs for painting of new steel
    bridges

13
Status on Cost Study Expected Output
  • Cost of painting as percent of total fabrication
    (range)
  • Influence on these costs of
  • Type of steel
  • Type of structure
  • Number of coats

14
Detailed Factors Investigated
  • Type of steel
  • A588 (painted and unpainted
  • A572 (painted and unpainted)
  • A36 (painted)
  • Number of coats
  • One coat (typically inorganic zinc)
  • Two or three coats (e.g., inorganic zinc/ epoxy/
    polyurethane)

15
Applying coal tar epoxy to H-piling with airless
spray
16
Detailed Factors Investigated (continued)
  • Types of structures
  • Rolled bean girders
  • Tub girders
  • Curved girders
  • Truss

17
Sources of Data
  • Fabricating shops
  • General contractors
  • DOTs and FHWA
  • Paint suppliers
  • Design and engineering firms

18
Others Expressing Interest
  • Associations (SSPC, AISC, NSBA)
  • FHWA
  • DOTs (KY, TX)
  • Paint manufacturers

19
Status
  • Data received from
  • 2 fabricators
  • 1 general contractor
  • Offers of assistance from several others

20
Conclusion/Summary
  • Preliminary data shows a very wide range of cost
    percentages
  • Should be a useful tool in addressing perception
  • Additional input sought (DOTs, fabricators,
    general contractors)

21
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com