Title: Perceptions on Bridge Painting Costs: Update on FHWA Study
1Perceptions on Bridge Painting Costs Update on
FHWA Study
- The 36th Annual Mid-Atlantic Quality Assurance
Workshop - Charleston, WV
- February 12, 2003
- Presented by
- Bill Shoup Bernard Appleman
- Executive Director Vice
President - SSPC KTA-Tator, Inc.
2Outline of Topics
- Background
- Perceptions about painting
- Status of FHWA Cost Study
- Conclusion
3Background
- Steel must compete with concrete
- 2 options for corrosion protection
- Painting
- Unpainted weathering steel
4Perceptions About Painting
- Difficult to do correctly by shops
- Adds considerably to cost of fabrication
- Adds considerable to time of fabrication
- Causes environmental headaches
- Makes steel less competitive
5Responding to perceptions
- Perception 1 Difficult to do correctly by shops
- Response 1 Improve effectiveness of shop
painting - Identify road blocks (e.g., unnecessary
requirements by specifiers) - Identify and disseminate best practice
(guidelines, information sharing, benchmarking) - Training of managers, operators, inspectors
6Responding to Perceptions
- Perception 2 Adds considerably to cost of
fabrication - Response 2 Develop valid cost data
- Discussed later
7Responding to Perceptions
- Perception 3 Adds considerably to time of
fabrication - Response 3 Identify fast thru-put coatings
- Modified polyurea metallic, powder
- Need to verify performance (e.g., NTPEP testing)
8Centrifugal Wheel Blast Unit A large beam is
supported by an overhead crane and carried
through a centrifugal wheel blast unit.
9A painter checks the wet film thickness of the
topcoat on the lower flange of a large beam
(foreground). Two painters apply a zinc-rich
primer to a similar beam (background).
10Responding to Perceptions
- Perception 4 Causes environmental headaches
- Response 4 Develop zero VOC coatings
- 100 solids powder coatings, thermal spray
metallic - Low VOC and low HAP coatings as possible interim
step
11Responding to Perceptions
- Perception 5 Makes steel less competitive
- Response 5 Provide valid life cycle cost data
- Need good data on
- Fabrication and installation
- Coating lifetime
- Maintenance cost
- Alternatives (unpainted steel, concrete,
composites) - Cost models available (FHWA and others)
12Status on FHWA Study on Painting Costs
- Objective
- Determine the costs for painting of new steel
bridges
13Status on Cost Study Expected Output
- Cost of painting as percent of total fabrication
(range) - Influence on these costs of
- Type of steel
- Type of structure
- Number of coats
14Detailed Factors Investigated
- Type of steel
- A588 (painted and unpainted
- A572 (painted and unpainted)
- A36 (painted)
- Number of coats
- One coat (typically inorganic zinc)
- Two or three coats (e.g., inorganic zinc/ epoxy/
polyurethane)
15Applying coal tar epoxy to H-piling with airless
spray
16Detailed Factors Investigated (continued)
- Types of structures
- Rolled bean girders
- Tub girders
- Curved girders
- Truss
17Sources of Data
- Fabricating shops
- General contractors
- DOTs and FHWA
- Paint suppliers
- Design and engineering firms
18Others Expressing Interest
- Associations (SSPC, AISC, NSBA)
- FHWA
- DOTs (KY, TX)
- Paint manufacturers
19Status
- Data received from
- 2 fabricators
- 1 general contractor
- Offers of assistance from several others
20Conclusion/Summary
- Preliminary data shows a very wide range of cost
percentages - Should be a useful tool in addressing perception
- Additional input sought (DOTs, fabricators,
general contractors)
21(No Transcript)