Title: Traffic Management Act 2004 / New Roads
1Traffic Management Act 2004 / New Roads Street
Work Act 1991
- Coordination Regulation Update February 2008
- (Coordinators)
2Agenda
- Part 1 TMA Background
- Part 2. Executing our TMA NRSWA duties.
- Part 3. Permits.
- Part 4. Summary.
3Part 1 TMA Background
4Summary of TMA
- To minimise, as far as possible, the impact of
traffic congestion. - The Act Covers
- Pt 1. Traffic officers (Highways Agency)
- Pt 2. Network management duty (Traff Managers)
- Pt 3. Permit schemes
- Pt 4. Street works (amendments to NRSWA 1991)
- Pt 5. Road enforcement (amendments to HA 1980)
- Pt 6. Traffic Offences
5Intervention Triggers
- A complaint about congestion.
- A report to Dft.
- If, from either of these sources, the Secretary
of State suspects that an Authority MAY be
failing, then the intervention process could be
initiated.
6Intervention Assessment Cost
- Assessed whether the Highway Authority has
- Coordinated works
- Ensured parity
- Taken regulatory action (where appropriate).
- Adopted performance measurements
- Met targets.
- Costs
- Replacement of TM by Traffic Director from Dft.
- Pay Dft costs up to 250,000/year.
- Lose Excellent status.
7Part 2 Executing Our TMA NRSWA Duties
8The Traffic Manager
- Peter Bayless
- Final decision on Traffic issues.
- Traffic Manager Board Meets quarterly.
- Street works manager, passenger transport, area
directors, transport policy, police, highways
agency, emergency planning, corporate
communications. - Discusses sets policy
- Operational group discusses performance.
9Parity
- Parity is an important principle in exercising
the duty. Authorities must lead by example,
applying the same standards and approaches to
their own activities as to those of others.
Para 68 Network
Management Duty Guidance document.
10Parity in Coordination
- HCC works promoters to amend their processes /
procedures / contracts. - THC contains TMA clause including penalties.
- Performance measured using indicators.
- Coordinators must be neutral.
11Coordination Pt 1 (Being Proactive)
- Duty to coordinate S59 NRSWA.
- Duty to keep traffic moving S16 TMA.
- Does the scheme warrant a T.M. Plan ?
- Does the scheme warrant any pre-meetings ?
- Are there any existing restrictions, eg TS
streets, S58, S.E.Ds, SSSIs, etc ? - Will it affect other networks / div routes
(including internal borders) ?
12Coordination Pt 2 (Being Proactive)
- Will it affect emergency services / buses ?
- Does a road require a standard TM plan for all
activities ? - Plans for A27, A32, A3024 already being written.
- Is consultation with stakeholders required.
- Does the Traff Manager need to know ?
- All considerations and decisions need to be
documented.
13Coordination Groups
- Regional coordination group
- One coordinator from each area.
- Discusses cross border activities.
- Reviews and disseminate new legislation.
- Assess performance of coord on past activities.
- Traff Manager Board / Op Group
- Local Coordination meetings
- Individual coordinators
14Registerable Works (What needs a notice)
- Works / activities need a notice if they
- Involve the breaking up or RS of any street.
- Involve opening the cway or cycleway of a
traffic sensitive street at traffic sensitive
times. - Require any form of temporary traffic control.
- Reduce the lanes available on a cway of 3
lanes. - Require a temporary traffic regulation order or
notice, or the suspension of pedestrian
facilities. - Require the reduction in the width of existing
cway of a traffic sensitive street at a traffic
sensitive time. - HCC has a legal duty to register (notify) using
the same categories.
15Non - Registerable Works (What DOES NOT need a
notice)
- Road markings
- Pole testing
- OM / RM works (HCC works only)
-
- Unless conditions 2 6 in the previous slide
apply. (Work in TS time, TC or TTRO needed) -
- Pole testing requires registration 10 days after
completion.
16Revised Works Type Classifications
Immediate Emergency - Unplanned activities undertaken to immediately resolve life threatening problems. Urgent - Unplanned activities undertaken to put an end to unplanned interruption of service.
Minor works Any planned activity that is to take 3 days or less
Standard Works Any planned activity that is to last longer than three days, but less than, or equal to ten days.
Major Works Any planned activity that is to last 11 days or more or any planned activity that requires a temporary traffic order or any activity identified on an annual programme or planned 6 months in advance.
17TMA Minimum Noticing for Coordination
Immediate S74 In progress 2 hours after start S74 Wks Closed within 1 working day
Minor works S55 - 3 Days S74 In progress within 1 working day of actual start S74 Wks Closed within 1 working day of actual completion
Standard Works S55 10 Days S74 In progress within 1 working day of actual start S74 Wks Closed within 1 working day of actual close
Major Works S54 3 Months S55 10 Days S74 In progress within 1 working day of actual start S74 Wks Closed within 1 working day of actual close
18Initial Notices
- New notice type.
- Not mandatory.
- Served at initial design stage.
- Only general details required.
- Not used to book road space.
- Used to ID potential clashes and allow other
works promoters to plan their works.
19Coord Notice Some Key Points
- Notices must be served in a timely manner.
- Durations must be realistic.
- Locations must be accurate.
- 8 digit Grid refs (000000.00) are mandatory and
must be realistic. - Polygons for works area required from 2009.
- TM info is mandatory.
- One works / street.
- Notified works must be started or notice
abandoned. - Notices have validity periods.
20S74 Overruns and Durations
- DfT have not yet revised the S74 rules, although
a draft has been consulted on. - Valid reasons for the required extension must be
clearly stated. - Any extension must be agreed with the local
coordinator BEFORE the revised S74 notice is
submitted. - Strict time limits for responses by from works
promoters AND coordinators.
21Agreements
- The Code introduces agreements
- Works promoters must get permission from the
local coordinator / Traffic (HQ) for - Working during a Restriction.
- Early start
- Extension
- Use of a provisional street
- Notice error correction
- Placing apparatus in a protected street.
22Noticing IT Systems
- Exor, Street Works Manager is the Register and
coordination tool for local coordinators. - Elgin is a supplementary tool used by both
coordinators and works promoters. - Elgin also designed to be a quick and dirty
noticing tool provided to HCC works promoters. - Both are (will be !) compliant with the TMA regs.
23www.elgin.gov.uk
24Elgin
- Fulfils HCC requirement to publish all works on a
map on the web. (e-gov requirement). - Fulfils map based requirement for TMA.
- GIS copy of whats in or Street Works Register.
- Allows cross border ID of works.
- Used by emergency services to plan routes.
- Totally reliant on data accuracy.
25Regulation (Reactive Coordination)
- S74 Duration challenges.
- S56 Direction of timings.
- Can now be used during works.
- S56A Directions for location of NEW apparatus.
- S66 Undue delay / obstruction.
- Applies to HCC works via parity / PIs.
- Need to document decisions.
26Monitoring Works for Compliance
- Noticing and regulation monitored by Traffic
(HQ). - Site inspections will confirm timing and location
accuracy. - No extra inspections (yet).
- Extra checks at Cat A stage.
- Non compliances need to be reported to Traffic
(HQ) for possible FPN.
27Fixed Penalty Notices
- Comes into force May 12th 2008.
- Served for noticing non compliance.
- Dates, times, location etc.
- NOT SLG or overruns.
- If SU disputes, then we MUST go to court.
- Evidence for non-compliances must be supplied as
per a court case. - 120 / 80 fine per offence.
28Performance Measurement
- PIs reported to Traffic Manager / DfT.
- Utility Cos may face fines / penalties / FPNs.
- HCC Works Promoters will need to explain poor
results. - PIs include
- Compliance with notice rules.
- Compliance with S74 / S56 / S66 directions.
- Number of overruns
- Notice accuracy
- Issuing of directions / documenting decisions
29Licensed Activities
- NRSWA 1991, S.50 Private apparatus
- Licence needs reviewing for TMA.
- Legal requirement to hold records on Register
(SWM). - All TMA NRSWA applies to licence holder.
- HA 1980, Skips / Scaffold etc
- No new requirements in latest Code.
- Should be recorded on Register for coord.
30Temp Traffic Control
- Not covered specifically by TMA, but are a source
of congestion. - SEHAUC form.
- Notice of 2 way.
- Permission required for multiway.
- Need to consider existing permanent controls.
- Stop / Go boards must be available on site.
- MANUAL CONTROL during TS times on TS streets.
31Coordinating Non Works Activities
- Works promoters should advise of
- Diversion routes road closures.
- Events need to be considered.
- Managed through DCs licensing.
- Traffic (HQ) advice for significant events.
- Central event database developed.
- DC activities
- Street sweeping, bus shelters etc.
- NM Duty states we should liaise to ensure that
they apply similar rules.
32NRSWA S58
- It is NOT a coordination notice.
- Up to 5 years protection.
- Exceptions
- Emergency works (obviously !) and customer supply
- Substantial cway fway schemes in excess of
30Lm can be protected. (SD not included). - Protection can be imposed following major SU
work. (S58A). - Restrictions also apply to HCC works.
33S58 Protection
Reconstruction 5 Years
Resurface 3 Years
Other substantial works 1 Year (6 months for Cat 3 4 rds)
Customer connections 20 days
34NRSWA S58 Revised Procedure
- 3 Months prior to works start
- Promoter sends details to Traffic HQ via notice.
- Details recorded on Register (via notice)
- Traffic HQ then sends to all interested parties.
- Traffic HQ publishes details on website.
- Promoter raises details at coordination meeting.
- 20 days to reveal any planned works.
- Works must start within 6 months of notified date
- Works promoter sends final S58 on completion of
work.
35Gazetteer - Special Designations
- Significant aid to works planning.
- TS, SED, Protected Street. Mandated by
legislation. - Other info, eg special surfaces, SSSIs.
- HUs responsible for deciding what info to add as
they have to enforce restrictions. - Data comes from a number of sources and owners
are responsible for accuracy.
36Part 3 Permits
37Permits
- Permission required to work on the highway.
- Heavy restrictions will apply to ALL.
- Probably only apply to strategic network.
- Working group set up to investigate.
- Kent CC have already applied to SoS to start
permit scheme later in 2008. - SUs will have to pay up to 240 for each permit.
- Permit approval will need to come from the
coordinators.
38Part 4 Summary
39In Summary
- TMA is not just about notices.
- Proactive coordination needed at all stages.
- Decisions need to be documented.
- Will require a change of procedures.
- More contact with works promoters
- Need to take on board parity.
- Need to adopt performance measures.
40Any Questions ?