Title: ACTIVE Principles of Lean Thinking
1- ACTIVE Principles of Lean Thinking How they are
applied in practice - 1st July 2004
2Overview of PROjEN
- Management owned, Founded in 1978
- 60 multi-disciplined project professionals
(approx 70 staff) - Key services include feasibility studies, capital
justifications, front-end engineering, turnkey
responsibility - Additional services include capital planning
support, training and legislation compliance
support in ATEX, IPPC, CDM etc - Key markets served are the Food and
Pharmaceutical sectors, plus Waste, Chemical and
General Manufacturing industries - ISO 90012000, RoSPA Gold in 2002 2003 2004
- Voted European Construction Institutes ACTIVE
Contractor of the Year for 2003, Project of
the Year 2004
3Recent Projectsand Clients
- 5 million R22 Refrigeration Replacement
- 250k New Sampling Facility
- 850k Automation of existing plant
- 90k Steam Main Upgrade
- 400k Packing Line Relocation
- 1.4 million Site Relocation
- 10k Capex Planning Consultancy
- 80k Custard Gravy Line Relocation
- 4.4 million Glass Condenser Replacement
- 25k Demolition Studies
- Onsite Alliance working at Kodak, AZ, Aventis,
BNFL, Vauxhall
4What is ACTIVE?
- Achieving
- Competitiveness
- Through
- Innovation
- Value
- Enhancement
5ACTIVE 1996 Action Plan
- Inefficient business processes which have
produced a culture of confrontation rather than
co-operation must be eliminated - Cultural change will be necessary at all levels,
both throughout the entire supply chain and
vertically throughout each of the organisations
involved in the industry - Within the project environment the greatest
opportunities for effecting value improvements
are to be found in the earliest stages of
projects
6 ACTIVE Principles of Effectiveness
ACTIVE seeks to achieve a competitive world class
process engineering and construction industry
with satisfied clients, thriving contractors and
suppliers by transforming the way in which they
deliver projects worldwide. This will be
achieved through more effective
- Project Risk Management
- Using a structured process for managing risk and
assigning responsibility to those in the supply
chain best able to manage it - Innovation Continuous Improvement
- Encouraging a challenge culture with processes
for capturing learning and regarding innovative
ideas throughout he supply chain - Project Execution
- Managing the implementation process to integrate
activities efficiently to successfully achieve
project objectives - Performance Measurement
- Defining key performance indicators which
demonstrate the achievement of project goals and
benchmarking performance to drive improvement
- Project Concept Definition
- Setting clear aligned objectives and scope with
defined, well understood implementation
strategies - Project Team Management
- Establishing an maintaining a single integrated
team with clearly defined roles and
responsibilities and shared common objectives - Supply Chain Relationships
- Ensuring that supply chain relationships work to
maximise value and equitably share both risks and
benefits - Information Management Communications
- Timely management of relevant information using
appropriate technology and clear documentation to
aid communication throughout the team
7Common issues encountered in Construction
Projects Production
- A complex supply chain precedes construction just
as it precedes production - Constructability processes ensure that the
construction process is designed at the same time
as the asset, which is fundamental to production,
but is rarely used to its full extent - Shortages of information, materials, equipment
and resources reduce the efficiency of a
construction project just as in production - When delays occur resources are diverted to lower
priority work or short term fixes reducing
efficiency producing rework - Project plans build in float which gets used as
they do with pre-lean production plans - Site area is wasted with excessive material
storage just as production can hold excessive
buffer stocks and WIP - Each of the parties seek to optimise their part
which results in sub-optimisation of the project
as a whole because the interdependancies are not
fully understood
8Lean Project Delivery employing ACTIVE Principles
- Effective project selection and prioritisation to
ensure strategic alignment - Use of flexible stage and gate project framework
with gates used as entry not exit points - Work package overlap to shorten schedule
- Early decision making
- Integrated work teams with shared objectives
- Projects well defined and value streams
identified - Effective and flexible project teams
- Individuals with high level of competence and
can-do attitude - Excellence built into core project management
techniques and controls
9Lean Project Delivery employing ACTIVE Principles
(Contd)
- Higher than normal peak demands as a result of
parallel approach - Requirement for highly effective risk management
techniques - Strong ownership Project Sponsor
- Stakeholder involvement
- Value analysis to shorten schedules
- Constructability/Buildability 3D Modelling
- Elimination of waste
- Effective supplier selection
- Early commencement of operator training
- Projects closed formally
- Post-Implementation reviews
10CASE STUDY
- ECI ACTIVE Project of the Year 2004
- for GlaxoSmithKline
- Stevenage RD Site
11Background
- Modifications to refrigeration and Heat Transfer
Fluid (HTF) distribution systems - Existing compressors handling R22 refrigerant
being replaced with ammonia refrigeration
packages - Environmental compliance
- Increased capacity
- New building
- New HTF pumps and associated controls integrated
with existing plant - Critical project timescales installation and
commissioning must be completed during 30 day
shutdown period
12Lean Principles Employed
- Stage Gate process with parallel working
- Strong project sponsorship and business benefits
focus - Collaborative approach employing common systems
and procedures with common objectives - Empowered integrated Project Team on Site
- Identification of concurrent engineering
opportunities - Minimised shutdown period
- Front end design and long lead time equipment
costs pre-sanctioned - Suppliers and Construction Management involved in
front end development phase - Shortened design phase
- Minimised risk, maximised opportunities
- Constructability/Buildability focus
13Lean Principles Employed (Contd)
- Commissioning considered at design phase
- High emphasis on risk management throughout
- Value engineering on building
- Cost savings
- Shortened schedule
- Suppliers selected with existing partnership
agreements - Location and layout of construction site
carefully considered - Increased efficiency
- Minimise on-site inventory
- 3D modelling employed
14GlaxoSmithKline Medicines Research Centre Gunnels
Wood Road Stevenage Hertfordshire
PROJEN PLC Winnington Avenue, Northwich, Chesire,
CW8 4EE Telephone 01606 871111 Facximile
01606 871133 E- mail mailbox_at_projen.co.uk
WEST - PRIMARY SYSTEM, TEMPORARY FEED RETURN
PIPING Doc. No SKETCH 42 19.03.04
15ECI ACTIVE Project of the Year, 2004
- Judges comments
- An excellent example of contractor and client
working together using ACTIVE Principles - An excellent front end project with the
contractor, PROjEN, using PDRI and an integrated
team approach - Two notable achievements were the vendor
selection process and the project risk assessment
process
16Conclusions
- There are sufficient similarities between
production and construction projects to adopt
Lean Thinking concepts to project management - ECI ACTIVE Principles and Lean Thinking overlap
and compliment each other in a number of areas - PROjEN and their clients have gained significant
advantage from employing ACTIVE Principles in a
spirit of collaboration to reduce both project
timescales and costs
17- ACTIVE Principles of Lean Thinking How they are
applied in practice - 1st July 2004