Title: Astronomy and Astrophysics Advisory Committee
1Astronomy and Astrophysics Advisory Committee
- Astrophysics Division and Update
- May 11, 2006
- Rick Howard
- Astrophysics Division Director (Acting)
2 Astrophysics Division Operating Missions Status
3 Astrophysics Division Developmental Missions
Status
4Astrophysics DivisionBudget Problems and Issues
- Budget problems and issues that must be dealt
with during this summers budget formulation - Additional funding in slip of HST SM4 launch
date beyond 12/07 - Level of near term contingency for JWST
- Funds required for SOFIA to support final
decision on path forward - Additional funds to cover expected GLAST replan
- Potential cost growth in Kepler
- Decision on future of WISE
- Restoration (full or partial) of funds to RA
program - Adjustments to mix within Navigator program (TPF
issue) - Direction within Balloon Program on future plan
for ULDBs
5Astrophysics DivisionBudget Principles,
Priorities Constraints (1)
- General Principles
- Follow priorities set by NRC surveys and reports
- Support Administration goals and direction
- In Practice
- Incremental budget solutions can lead to wrong
global solution - Best approach is to solve all problems at one
time each year (POP) - Slipping current missions not always the right
answer - Only solves short term budget problems
- Creates bow wave of funding requirements
downstream - Increases total mission cost far more than
inflation (marching army) - Cancellation may be more sensible option
- Applying a tax across the board not a good
approach - Spread the pain but weakens all programs
- Once or twice may have minor impact eventually
has significant impact on all projects - Reserve this approach for directed reductions
(rescissions, hurricane tax, etc.)
6Astrophysics DivisionBudget Principles,
Priorities Constraints (2)
- Priorities
- Continue healthy operating missions
- Complete and launch missions in development
- Provide for the future ( RA, technology,
balloons, concept studies) - Constraints
- Congressional direction/mandates
- Solution must balance each of the 5 years in the
budget horizon - Currently working on FY08-12 budget
- Only guaranteed budget is the single year
approved by Congress in the Operating Plan - Considerations
- Mission size/launch frequency
- Wavelength
- Mission Phase
- Long term strategy
7Wavelength Mix
8Science Theme Mix
9Mission Size Mix
10The Astrophysics Content of FY07 Budget
Future Explorer Budget is in Heliophysics
Division budget
11Astrophysics DivisionBudget Example
- Hypothetical Issue Restore15 RA funding
reduction - Solution 1 Reduce Beyond Einstein Program
funding - Hold budget to the FY06 level for FY07-08 (
14M per year) - Restores 10 (7M) in FY07 and FY08
- Restores full 15 starting in FY09 (11M per
year) - Slips first Beyond Einstein mission
- Solution 2 Apply an across the board tax
- Approximate 1 reduction to all programs
- Some programs may be protected (e.g. HST SM4)
- Solution 3 Restore as part of overall
Astrophysics budget solution during FY08-12 POP - Allows more flexible solution space
- Solution is part of Divisions overall strategy