Title: Gulf of Mexico OCS Offshore General Permit
1Gulf of Mexico OCS Offshore General Permit Region
6 NPDES Permit No. GMG290000 40 CFR Part 435,
Subpart A
Sharon Haggard US EPA, Region 6
Presentation for the Gulf Coast Environmental
Affairs Group Dallas, Texas November 8, 2007
2Overview
- Introduction
- NetDMR
- Region 6 Suggested Forms
- Response to the GCEAGs questions
- Additional Information
3NetDMR
- Interested in joining the NetDMR Workgroup?
- Conference Calls
- Web sessions to view system design and
capabilities - Will need a few participants for Pilot testing
- Summer 2008
- Contact Michael Barrette
- barrette.michael_at_epa.gov
4Notice of Intent (NOI), page 1
1445 Ross Ave., Suite 1200 Dallas, TX 75202-2733
72 Fed. Reg. No. 109, p. 31575, October 1, 2007
Cooling Water Intake Y/N
Do not abbreviate lease area names.
Section E Cooling Water Intake
Modified October 1, 2007
Permit Expires Midnight September 30, 2012
5Notice of Intent (NOI), page 2
1445 Ross Ave., Suite 1200 Dallas, TX 75202-2733
72 Fed. Reg. No. 109, p. 31575, October 1, 2007
NOTE You will only receive SBM and/or Cooling
Water Intake outfall numbers, and corresponding
Discharge Monitoring Report forms, for those
lease areas/blocks so marked as Y for yes on
the NOI form.
6Notice of Termination (NOT), page 1
1445 Ross Ave., Suite 1200 Dallas, TX 75202-2733
72 Fed. Reg. No. 109, p. 31575, October 1, 2007
Modified October 1, 2007
Permit Expires Midnight September 30, 2012
7Notice of Termination (NOT), page 2
1445 Ross Ave., Suite 1200 Dallas, TX 75202-2733
72 Fed. Reg. No. 109, p. 31575, October 1, 2007
8Notice of Termination (NOT), page 2
Deadline to Submit NOT and its corresponding
final DMRs In accordance with Part I.A.3. Of the
permit Lease block operators shall submit a
Notice of Termination (NOT) to the address above
within 60 days of termination of lease ownership
for lease blocks assigned to the operator by the
Department of Interior. In the case of temporary
operations such as hydrostatic testing, the NOT
shall be submitted within 60 days of termination
of operations. The Discharge Monitoring Report
(DMR) for the terminated lease block shall be
submitted with the NOT, or with the annual DMR
submittal. The NOT shall be effective upon the
date it is received by the EPA.
9Transfer Agreement (TA), page 1
1445 Ross Ave., Suite 1200 Dallas, TX 75202-2733
72 Fed. Reg. No. 109, p. 31575, October 1, 2007
Cooling Water Intake Y/N
Do not abbreviate lease area names.
Section D
10Transfer Agreement (TA), page 1
If No, please clearly describe the portion of
Operator As coverage to be transferred to
Operator B and that portion to be retained by
Operator A in an attachment to this TA.
Modified October 1, 2007
Permit Expires Midnight September 30, 2012
11Transfer Agreement (TA), page 2
1445 Ross Ave., Suite 1200 Dallas, TX 75202-2733
72 Fed. Reg. No. 109, p. 31575, October 1, 2007
NOTE You will only receive SBM and/or Cooling
Water Intake outfall numbers, and corresponding
Discharge Monitoring Report forms, or those lease
areas/blocks so marked as Y for yes on the TA
form.
12Transfer Agreement (TA), page 2
Notice to Operator A Operator A, where they are
releasing their coverage in its entirety, are
reminded of Part I.A.3. Of the permit in regard
to the submission of their final DMRs. The final
DMRs shall be submitted with the Transfer
Agreement forms, or with Operator As annual DMR
submission.
Notice to Operator B Operator B must collect and
report their own samples for the lease/block
acquired in the Transfer Agreement. They cannot
utilize samples collected by Operator A.
13GCEAG question 5
- Question The NOI and NOT on the EPA R6 website
still reference the old permit and the forms
still have the expiration date 11/5/07. Will
operators be able to submit NOI, NOT and
transfers using these expired forms?
- Answer No. These forms all cite the legal
references to - the previous permit and cannot be used. For
example, - you cannot ask for coverage under a permit that
has expired, which is what you are doing when you
use the - old forms.
14GCEAG question 6
- Question If the expired forms are not to be
used, how - does an operator request coverage in the interim?
- Answer You can create your own temporary
document - and forward the request via a cover letter. You
can use - the previous permit form as a guide for
creating your temporary document to ensure it
contains all the required elements.
15GCEAG question 7
- Question When does EPA R6 expect new NOI, NOT
and transfer forms to be available for use under
the new GP - on the EPA R6 website?
- Answer Soon. They have been created and are in
the process of being added to the offshore
website www.epa.gov/region6/offshore .
I anticipate them being on the website
sometime late this week or early next week. In
the meantime, and as another interim idea to
question 6 above, you have before you a hard
copy as part of todays presentation to use to
make copies from. Please be aware that the web
will only be a fill and print version. You
will have to purchase special software to enable
you to save and print these forms. So, if you
find you need to fix it but you have already
taken it from your screen, you will have
to re-create it.
16GCEAG question 8
- Question Does each page of the interim request
need to have a certification?
- Answer Yes. The accompanying pages need to
reflect - the same information as the first page. This
procedure is no different than signing and
certifying each page of the DMR or No
Discharge/No Activity List.
17GCEAG question 9
- Question Does each page of the interim request
need to have a original authorized signature?
- Answer Yes. The accompanying pages need to
reflect - the same information as the first page. Again,
as per question 8 above, this procedure is no
different than signing and certifying each page
of the DMR or No Discharge/No Activity List.
18GCEAG question 10
- Question If an operator had authorized
signatures of individuals other than company
officials on file, do they need to reestablish
these signature authority under the new GP?
- Answer No. However, I do want to remind
everyone that change occurs often with the
industry in terms of who is doing what, including
signature authorities, mailing addresses,
contacts, etc. More times than not, I am the
last to find out. Failure to provide current
information creates a domino effect. For
example, I have an operator who relies on EPAs
preprinted DMR forms. I, in turn, relied on the
most recent information provided, only to have
the Post Office return the package stating
Forwarding Order Expired. cont
19GCEAG question 10 cont.
- Since I rarely have a rainy day to spend trying
to find you, I just have to place the package in
the compliance file we maintain on you to
demonstrate I tried to send you information,
but was not able. The domino effect continues
when we pursue enforcement action against you
for failure to report in accordance with the
permit. So, it is very important to keep
information on record with the EPA current at all
times.
20GCEAG question 11
- Question Does an operator have to file a new
request to utilize the OOC DMR forms that have
been or will be developed by the OOC?
- Answer Yes. The previous form represented the
old permit. The new permit picked up additional
requirements, as well as dropping some
requirements from the previous permit.
Consequently, the DMR form changed. And,
requiring operators to request authorization to
use the new OOCs facsimile of the offshore
general permit DMR form is consistent with EPAs
policy for all of its NPDES permits that it
tracks (i.e., wastewater treatment plants).
21GCEAG question 12
- Question Have those forms been developed by the
OOC and has EPA approved their use?
- Answer Not yet. Marsha Dupont from
Environmental Enterprises and I have been in
constant communication about the status of the
new DMR form. Marsha will create a facsimile of
the DMR for EPAs approval, prior to it being
posted on the OOCs web site for use. A
few nuts and bolts here...I do have the new DMR
form in draft, but have to petition to my
Headquarters to create some new STORET codes to
reflect the cooling water intake requirements.
Until then, I cant finalize it to build it into
the database. But, I do fully expect the form
to be ready for the first group affected which
will be operators with a 01/28/08" DMR
submission deadline.
22GCEAG question 13
- Question Does EPA expect two sets of DMRs for
companies that had a DMR date prior to the new
permit one to cover the old permit time, and one
to cover the remainder of the year under the new
permit?
- Answer Yes, in accordance with Part II.D.4. of
the permit (both the previous and the reissued
permit). - This gets a little complicated to explain, but
bear with me. Three of the groups - the 01/28,
the 04/28, and the 07/28 groups - will have to do
what I call split reporting. The 10/28 group
lucked out as the permit was reissued on the
first day of their assigned monitoring period.
cont
23GCEAG question 13 cont.
- For example, the 01/28 group will have to
report information on the previous permit DMR
(for the previous permit), as well as report
information on the reissued - permit DMR for the new permit. The monitoring
period at the top of both sets of DMR forms will
have to be the - same, but the operator must use the comment
field to reflect the split of time. The
monitoring period at the top - of the form must remain the same on both sets of
DMR forms as this is that operators assigned
monitoring - period and it is the measurement tool my
- database uses for certain types of violations.
cont
24GCEAG question 13 cont.
- So, an 01/28/08" operator will reflect the
monitoring - period From 01/01/07 To 12/31/07" at the top of
the - DMR form for both permits, but in the Comment
Field - they are to state From 01/01/07 to 09/30/07"
for the previous permit DMR and From 10/01/07 to
12/31/07" - on the DMR for the new permit. cont
25GCEAG question 13 cont.
- This brings up another issue. Some operators
have elected to continue to use EPAs preprinted
DMR forms. That is their option. But, it will
present a problem for those caught up with the
split reporting. Under my current database
system, PCS, I cannot have both the old and the
new permit running current in the system at the
same time. One must be ghosted, while the
reissued permit takes the place of the previous
permit. This means that I cannot go back and
order preprints under the previous permit. cont
26GCEAG question 13 cont.
- So, in order for all operators affected by the
split reporting to comply with their DMR
submission, they will have to use the OOCs DMR
form for the previous permit. NOTE Both
the OOCs web site as well as EPAs will have
both versions running until the last group
affected (the 07/28 group) completes their
annual submission for 07/28/08. After that,
the previous permit DMR will go away. And, both
the OOCs web and EPAs will identify which DMR
is for which permit. cont
27GCEAG question 13 cont.
- What does this mean for those operators who want
to continue using EPAs preprinted DMR forms?
They will have to submit a one-time-only request
for retro-authorization to use the OOC DMR for
the previous permit. And, if they want, they can
continue to use EPAs preprinted DMR form for
their reporting requirements under the new
permit. They just need to clarify that fact in
their written request (signed and certified in
accordance with Part II.D.10. of the permit).
28GCEAG question 16
- Question If a toxicity was not taken prior to
the permit expiration (clarify which date this
is), will a toxicity taken in the last three
months under the new GP be acceptable and not be
a permit noncompliance?
- Answer 1) The previous permit expired early - at
midnight of September 30, 2007. (It was
originally set to expire at midnight of November
5, 2007.) - 2) This scenario is a permit
noncompliance. Toxicity test cannot be combined
for both permits.
29GCEAG question 17
- Question Are toxicity tests to be taken on a
report period basis in the new GP or on an annual
basis? Is the annual basis calendar year?
- Answer The permit requires it to be annual,
based on the operators assigned monitoring
period see Part I.B.4.b)vi) and Part I.D.3.j) of
the permit for Produced Water Toxicity and Part
I.B.11.b) of the permit for Miscellaneous
Discharge Toxicity.
30GCEAG question 31
- Question In the past industry was told that any
submittal to the EPA R6 should be via some
traceable means (i.e., certified mail green card,
federal express, UPS). However, some of these
submittals, although stamped as received by EPA
R6, did not reach the appropriate individual at
R6 and subsequent AO were issued for failure to
report, when in fact, the reports had been
submitted, stamped received. - How best should industry be assured of delivery
to the EPA R6? What measures is EPA putting into
place to make sure that the mail room is more
aware of the importance of documents delivered
during the end of report period time frames?
31GCEAG question 31 cont.
- Answer I had suggested operators submit, in
particular NOIs, via a mail receipt system (USPS,
FedEx, UPS), due to the large volume of documents
I receive daily from the industry (I cant always
get to things the day I receive them). My
suggestion was for the benefit of the industry
in order for them to place that mail receipt,
along with a copy of the NOI (or Transfer
Agreement), on the rig/platform, to demonstrate
to inspectors (MMS/Coast Guard) and/or third
parties that they had applied for NPDES coverage.
cont
32GCEAG question 31 cont.
- Then, operators decided they wanted to send other
documents (i.e., DMRs) via a mail receipt as
well, in order to track when EPA actually
received them. - With any large organization, there is always a
percentage of mail that gets mis-routed
unintentionally. But, I have noticed that the
industry is not always using the proper address
for their documents. And other times, the
industry will use the green card as the TO
label on the package. cont
33GCEAG question 31 cont.
- The contractor in EPAs mail room signs for a
large volume of mail every day, so when it comes
time to run the mail through their process for
sorting then delivering, the green card that
was pulled off for return to the sender leaves a
loss of required information on the envelope.
The contractor has no idea who the mail should go
to. On top of that, since 9/11, we have
implemented stricter mail handling procedures to
safeguard the employees and staff of the EPA.
cont
34GCEAG question 31 cont.
- So, when a package appears suspicious as the
one with the missing green card that was used as
a TO label, the package gets placed into
suspicious mail and procedures are used to
determine if it is safe to open and to whom it
should be given. - So, sometimes mail does not get received properly
because it is not properly addressed, or green
cards are used as the TO label. - In addition, we had a great deal of trouble with
the Post Office losing our mail. This is why the
new permit requires operators to send items to
the physical address vs. the P.O.
Box address.
35GCEAG question 33
- Question The NOI, NOT and transfer forms all had
effective dates as well as date of execution of
the form. Why then does EPA R6 not honor the
effective date stated on the form, especially in
the cast of NOT when the final DMR has been
submitted and no additional monitoring is
required? Where is this addressed in the GP?
- Answer The effective date appeared on the old
forms, because operators wanted to be able to
state when events occurred on their end.
However, for EPAs purposes, we do not rely on
that date. In fact, because it created
confusion, I had that statement removed from the
new permit forms. cont
36GCEAG question 33 cont.
- We use the Postmark date of the NOI as the date
when coverage begins (we used to say coverage
began with submission of the NOI, but the
industry wanted a definition of submission - so
our management determined submission to mean
postmark - See Part I.A.2.). But, we use the
date EPA actually received the NOT as the
effective date for when coverage is terminated.
This policy is not in the general permit, but is
the policy we use for all our NPDES permits.
cont
37GCEAG question 33 cont.
- The received date is when EPA officially became
aware of the request for termination and has
always been the date we used for termination.
So, operators need to bear in mind when they
submit a NOT as it relates to final DMRs. But,
the permit (Part I.A.3.) gives operators the
option to submit final DMRs with the NOT thus
having to avoid reminding themselves to report it
at their annual submission deadline.
38GCEAG question 34
- Question How soon will the database be updated?
- Answer Im working on it...
39Additional Information
- Application Process Questions
- Ms. Sharon Haggard, Environmental Specialist
- (214) 665-6472, haggard.sharon_at_epa.gov
- Compliance and Enforcement Questions
- Robert Houston, Environmental Engineer
- (214) 665-8565, houston.robert_at_epa.gov
- Anthony Loston, Environmental Engineer
- (214) 665-3109, loston.anthony_at_epa.gov
- Permit Questions
- Scott Wilson, NPDES Permit Writer
- (214) 665-7511, wilson.js_at_epa.gov
40Additional Information cont.
- Alternative to 24-Hour Hotline
- Send an e-mail to r6genpermit_at_epa.gov
- 24-Hour Hotline
- (214) 665-6595