PROJECT CASH FLOW - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

PROJECT CASH FLOW

Description:

Bank charges interest on the outstanding balance (overdraft) ... The contractor needs to know what is the maximum overdraft during the construction project ... – PowerPoint PPT presentation

Number of Views:2611
Avg rating:3.0/5.0
Slides: 26
Provided by: Jan397
Category:
Tags: cash | flow | project | overdraft

less

Transcript and Presenter's Notes

Title: PROJECT CASH FLOW


1
PROJECT CASH FLOW
ARE 413 CONSTRUCTION MANAGEMENT By MOHAMMED
JALALUDDIN LECTURER CONSTRUCTION ENGINEERING
MANAGEMENT DEPT Handout 11
2
Presentation Outline
  • Cash Flow
  • Cash Flow Projection / What is Cash Flow
    Projection
  • Example Cash Flow of Simple Project
  • S-Curve
  • Cash Flow to Contractor
  • Progress Payment
  • Contractors Expenses and Income Profile
  • Contractors Financing
  • Overdraft
  • Mobilization Advance Payment

3
Objectives of Class
  • To introduce cash flow concept during the life
    of a project and example of cash flow projection
    of simple project
  • To draw the Contractors Expenses and Income
    Profile
  • To know the Contractors sources of Financing

4
Cash Flow Projection
  • Projection of Income and expenses during the life
    of the project
  • Several time scheduling aids used by contractor

5
Project S-Curve
  • Owner requires contractor to provide an S curve
    of estimated progress and costs
  • Cumulative costs across the duration of the
    project
  • A graphical portrayal of the outflow of monies
    (both direct indirect)

6
Cash Flow
Source Dr. L. K. Gaafar
7
Cash Flow
Source Dr. L. K. Gaafar
8
Cash Flow to the Contractor
  • Progress Payments - Flow of money from owner to
    the contractor
  • Estimates of work completed by the contractor
    periodically and (usually monthly) and verified
    by owners reps
  • Evaluation based on type of contract
  • Lump Sum Percentage of total contract completion
  • Unit Price Actual field measurements of work
    completed

9
Progress Payments
  • Contractor prepares a monthly progress claim
    (bill) usually at the end of each month
  • The Owner evaluates the bill and pay contractor
    within the time period stipulated in the contract
    (usually within 30 days)
  • Owner keeps a retainage of 10 from each payment
    (usually until cumulative progress bills reach
    50 of the total contract sum)

10
Sample S Curve
11
Contractors Income Profile
  • Stair-step appearance since the progress
    payments are paid in discrete amounts


Duration
12
Contractors Expenses and Income Profile
  • Clear indication of expenses and income
  • The difference between Expenses and revenue makes
    it necessary for the contractor to obtain
    temporary financing


Duration
13
Expenses and Income Profiles
14
Expenses and Income Profiles
15
Contractors Financing
  • Usually a bank extends a line of credit against
    which the contractor can buy materials, make
    payments and pay other expenses while waiting for
    reimbursement from owner.
  • Bank charges interest on the outstanding balance
    (overdraft)
  • Good policy to to try to minimize overdraft

16
Overdraft depends ON
  • Amount of markup (or profit) applied to
    contractors bid
  • Amount of Retainage withheld by the owner
  • Delay between billing and payment by the owner

17
Banks evaluation of construction contractors
  • High risky borrowers
  • If the contractor defaults, the loan is secured
    only by some materials inventories and partially
    completed construction
  • Charges very high interest rates on borrowings

18
Mobilization Advance Payment
  • Some contractors offset the overdraft borrowing
    requirement by requesting mobilization, money
    from owner
  • Influence of mobilization on payment and income
    profiles

19
Expenses and Income Profiles (with mobilization
advance)
20
Mobilization Advance Payment
  • Some owners issue 20 of the advance payment at
    the inception against a bank guarantee submitted
    by the contractor
  • The advance payment recovered in each progress
    payment at a rate of 20.
  • Since the owners are less risky than the
    contractors, they can borrow short-term money at
    a lower interest rates
  • Transfer the interim financing requirement from
    contractor to the owner
  • Overall cost savings to owner and the contractor

21
Overdraft Requirement
  • The contractor needs to know what is the maximum
    overdraft during the construction project
  • Uses Income and expenses profiles to asses the
    overdraft
  • Tabulate the expenses and revenues and find the
    maximum overdraft

22
Plot of maximum overdraft
23
Composite Overhead Profiles
24
Comparison of Payment Schemes
  • Rate-of-return (ROR) analysis is helpful in
    comparing the economic value to a contractor of
    varying payment schemes
  • Examining the economic impact of
  • varying retainage policies
  • delay in payment strategies
  • payment of mobilization
  • Evaluate the net present value between Revenue
    and Expenses

25
Summary
  • Projection of Income and expenses during the life
    of the project
  • The difference between Expenses and revenue makes
    it necessary for the contractor to obtain
    temporary financing
  • Usually a bank extends a line of credit against
    which the contractor can buy materials, make
    payments and pay other expenses while waiting for
    reimbursement from owner
  • References Janaka Y. Ruwanpura
Write a Comment
User Comments (0)
About PowerShow.com