Title: PROJECT CASH FLOW
1PROJECT CASH FLOW
ARE 413 CONSTRUCTION MANAGEMENT By MOHAMMED
JALALUDDIN LECTURER CONSTRUCTION ENGINEERING
MANAGEMENT DEPT Handout 11
2Presentation Outline
- Cash Flow
- Cash Flow Projection / What is Cash Flow
Projection - Example Cash Flow of Simple Project
- S-Curve
- Cash Flow to Contractor
- Progress Payment
- Contractors Expenses and Income Profile
- Contractors Financing
- Overdraft
- Mobilization Advance Payment
3Objectives of Class
- To introduce cash flow concept during the life
of a project and example of cash flow projection
of simple project - To draw the Contractors Expenses and Income
Profile - To know the Contractors sources of Financing
-
4Cash Flow Projection
- Projection of Income and expenses during the life
of the project - Several time scheduling aids used by contractor
5Project S-Curve
- Owner requires contractor to provide an S curve
of estimated progress and costs - Cumulative costs across the duration of the
project - A graphical portrayal of the outflow of monies
(both direct indirect)
6Cash Flow
Source Dr. L. K. Gaafar
7Cash Flow
Source Dr. L. K. Gaafar
8Cash Flow to the Contractor
- Progress Payments - Flow of money from owner to
the contractor - Estimates of work completed by the contractor
periodically and (usually monthly) and verified
by owners reps - Evaluation based on type of contract
- Lump Sum Percentage of total contract completion
- Unit Price Actual field measurements of work
completed
9Progress Payments
- Contractor prepares a monthly progress claim
(bill) usually at the end of each month - The Owner evaluates the bill and pay contractor
within the time period stipulated in the contract
(usually within 30 days) - Owner keeps a retainage of 10 from each payment
(usually until cumulative progress bills reach
50 of the total contract sum)
10Sample S Curve
11Contractors Income Profile
- Stair-step appearance since the progress
payments are paid in discrete amounts
Duration
12Contractors Expenses and Income Profile
- Clear indication of expenses and income
- The difference between Expenses and revenue makes
it necessary for the contractor to obtain
temporary financing
Duration
13Expenses and Income Profiles
14Expenses and Income Profiles
15Contractors Financing
- Usually a bank extends a line of credit against
which the contractor can buy materials, make
payments and pay other expenses while waiting for
reimbursement from owner. - Bank charges interest on the outstanding balance
(overdraft) - Good policy to to try to minimize overdraft
16Overdraft depends ON
- Amount of markup (or profit) applied to
contractors bid - Amount of Retainage withheld by the owner
- Delay between billing and payment by the owner
17Banks evaluation of construction contractors
- High risky borrowers
- If the contractor defaults, the loan is secured
only by some materials inventories and partially
completed construction - Charges very high interest rates on borrowings
18Mobilization Advance Payment
- Some contractors offset the overdraft borrowing
requirement by requesting mobilization, money
from owner - Influence of mobilization on payment and income
profiles
19Expenses and Income Profiles (with mobilization
advance)
20Mobilization Advance Payment
- Some owners issue 20 of the advance payment at
the inception against a bank guarantee submitted
by the contractor - The advance payment recovered in each progress
payment at a rate of 20. - Since the owners are less risky than the
contractors, they can borrow short-term money at
a lower interest rates - Transfer the interim financing requirement from
contractor to the owner - Overall cost savings to owner and the contractor
21Overdraft Requirement
- The contractor needs to know what is the maximum
overdraft during the construction project - Uses Income and expenses profiles to asses the
overdraft - Tabulate the expenses and revenues and find the
maximum overdraft
22Plot of maximum overdraft
23Composite Overhead Profiles
24Comparison of Payment Schemes
- Rate-of-return (ROR) analysis is helpful in
comparing the economic value to a contractor of
varying payment schemes - Examining the economic impact of
- varying retainage policies
- delay in payment strategies
- payment of mobilization
- Evaluate the net present value between Revenue
and Expenses
25Summary
- Projection of Income and expenses during the life
of the project - The difference between Expenses and revenue makes
it necessary for the contractor to obtain
temporary financing - Usually a bank extends a line of credit against
which the contractor can buy materials, make
payments and pay other expenses while waiting for
reimbursement from owner - References Janaka Y. Ruwanpura