Title: Integrated Asset Delivery Framework
1Integrated Asset Delivery Framework
2Integrated Asset Delivery Framework
Even if a Integrated Asset Delivery Framework
Building doesnt look unusual, it can save in the
order of 50 in energy and greenhouse gas
emissions, compared to current good practice.
Much of this is due to a new design process, one
based on the well-tested principles of skills and
teamwork.
3What is Integrated Asset Delivery Framework?
- Integrated Asset Delivery Framework is a program
for the delivery of high-performance buildings.
The goal is to help designers to achieve a very
high level of performance, including - A 50 improvement in energy performance relative
to current good practice, - Reductions in resource consumption, such as land,
water and materials, - Significant reductions in atmospheric emissions,
solid and liquid wastes, - Superior indoor air quality, thermal comfort,
illumination and acoustic environment, - Improved functionality, adaptability and
maintainability.
4The conventional design process
- To assess the Integrated Asset Delivery
Framework, we first need to examine the
conventional design process. It is essentially
linear in nature
5The conventional design process
- It begins with pre-design functions, such as the
preparation of a Design Brief and Functional
Program, to be carried out by the client. This is
followed by the first two phases within the
responsibility of the design team, Schematic
Design and Design Development. Percentage figures
indicate recommended percentage of total fees
allocated to the task.
Design Development 15
Schematic design 10
6The conventional design process
- These are in turn followed by Detail
Documentation (drawings and specs), Tender
Process, and Site Inspections during the
Construction Stage. These three phases account
for 75 of the total fees.
7The conventional design process
- In the conventional process, attempts are often
made to introduce bright ideas during the
preparation of construction documents (or even
later!), since they were not considered earlier.
This is costly and disruptive to the process.
8The conventional design process
- To summarise the problems
- The main design parameters (massing, orientation,
fenestration pattern) are often determined by the
client and architect in the Schematic Design
phase. - Input on orientation for passive solar,
daylighting potential, measures to control solar
overheating etc. is often only sought in the
Design Development phase. - By this time, the client and architect may be
locked into a sub-optimal solution
9The conventional design process
- problems
- Engineers and specialists are locked out of the
initial design decisions, and architects are
poorly placed to acquire detailed knowledge about
new technologies and processes such as
performance simulation. - Advanced systems and features are often added
on to the basic design in later phases, but this
does not lead to very high levels of performance,
disrupts the process, and is very costly. - Or design in haste, repent at leisure.
10The two core processes compared
Integrated Asset Delivery Framework
Conventional Process
11Integrated Asset Delivery Framework
- We define the integrated development process as
- Including a wide range of technical skills in the
design team, - Adding a design facilitator and an energy
simulation specialist to the team, - Commencing with teamwork from the very start of
the Concept Design Stage, - Adding new functions to the process, and
- Defining performance goals at the outset and
referring to them throughout.
12Integrated Asset Delivery Framework
- What are the features of the Integrated Asset
Delivery Framework? - It brings engineering and specialist skills to
the table at a very early stage. - A broad range of performance issues are
considered. - It keeps options open on the basic features of
the design until the potential performance of
alternatives can be assessed. - Conversely, the client is not hustled into a
premature commitment to a primarily visual
solution.
13Integrated Asset Delivery Framework
- What are the features...?
- The architect plays the role of a team leader and
is not the predominant decision-maker during
Concept Design and Design Development. - Friction can be avoided by informing consultants
about the process before they are retained. - The architect acquires valuable new technical
skills, while the client and engineers gain
insight into the complexities of architectural
design. - Engineers have a chance to show how much they can
contribute to the early design phases.
14Integrated Asset Delivery Framework
- What are the features...?
- Integrated Asset Delivery Framework provides
access to specialists as needed for short-term
advice, such as daylighting, thermal storage,
glazing characteristics, material selection, etc. - Note that, as in conventional projects, most of
the hard work is up to the design team. The
program is not intended for neophyte designers,
and our process just provides support and helps
the team to make the right decisions.
15Integrated Asset Delivery Framework
The first step is to work with the client to
ensure that the right team is in place before
design begins
Integrated design team
Committed client
Committed and skilled design team
Specialists
Design Facilitator
16Integrated Asset Delivery Framework
Core design team Team specialists
The relationship between the actors looks
something like this
Conventional roles
Committed client
Cost consultant
Management and technical advice
Contractor
Energy specialist
Environmental specialist
Design Facilitator
Facility manager
Management and technical support
O M staff, tenants...
17Integrated Asset Delivery Framework
- It is important to note that
- The architect and engineers still retain their
professional responsibilities and liabilities,
and therefore are the final arbiters of design
decisions. - The Design Facilitator is to be an adviser, and
is to support the design team in their work
without disrupting the process. This requires an
ability to make rapid decisions and also to
provide helpful information and support quickly. - The design professionals should be paid on a
lump-sum basis or equivalent that will avoid
penalising them financially for reducing the size
and cost of mechanical systems.
18Integrated Asset Delivery Framework
- Before design work begins, some preliminary
questions should be asked - Could a renovation serve the purpose instead of a
new building? - If new construction is needed, has the best site
been chosen, e.g. avoiding the use of
agricultural land? - Has the design brief and functional program been
developed with due care?
19Integrated Asset Delivery Framework
Preliminary energy analysis
Perform a global performance assessment
Define performance goals
Concept Design Report
Design iterations
Integrated design team
Develop concept design(s)
Concept Design Phase
Examine functional requirements
Examine site development issues
20Designiterations
Develop preliminary building envelope design
Select building structural system
Develop preliminary lighting and power system
design
Develop preliminary design for ventilation,
heating and cooling systems
Develop preliminary fenestration design
Design Development Phase
21New technologies and procedures are implemented
22Design iteration is sometimes necessary but not
recommended
Schematic Design Report
Pre-Construction Report
Final Life Cycle Cost Analysis
Complete contract documentation, including
working drawings and specifications
Develop Quality Management strategies for
construction and commissioning
Develop Quality Management strategies for
operation
Contract Documentation and Beyond
23Construction, Commissioning and Operation
Commissioning Report
Provide as-built documentation and operating
manuals
Operate
Site Inspections (Construction)
Carry out commissioning
Procure materials and equipment
Monitor operational performance
Train operating staff
24Integrated Asset Delivery Framework - in full
Contract Documentation and Beyond
Construction, Commissioning and Operation
Concept Design
Design Development
25New technologies and procedures are implemented
A way to summarise the technical aspects of the
process is to think of it this way
- First make use of the passive solar potential by
using orientation and configuration to maximize
solar potential during the heating season and
daylighting all year around
- Second, reduce heating and cooling loads through
the use of a high-performance building envelope,
carefully located glazing and by reducing
electrical consumption
- Then meet the reduced load requirements through
efficient plant systems and distribution
systems...
- while always remembering the need for a
high-quality indoor environment, maintainability,
economy and measures to reduce environmental
loads.
26New technologies and procedures are implemented
Specific design features depend on the specific
building and its location nevertheless consider
the following
- Provision of adequate space for bicycles and
solid waste recycling,
- High-volume flyash cement and a lean structure,
- Trees as part of the solution to reduce cooling
loads,
- Spectrally-selective glazing with exterior
sunshades and light shelves to maximize
daylighting potential,
- High-efficiency direct/indirect ambient lighting
plus task lighting,
- Daylight sensors for perimeter lighting zones,
27New technologies and procedures are implemented
Specific design features to consider...
- Use of natural ventilation where possible,
- Operable windows or a backup ventilation system,
- 100 displacement fresh air system with heat
recovery,
- Sizing of drives, boiler chillers to maximize
operation at full loads.
- Minimal size of lighting and HVAC zones,
- Control systems that are user-friendly and are
consistent with the complexity of building
systems,
- Materials chosen for low emissivity and embodied
energy, use of recycled materials, and an
assembly design that focuses on future
demountability.
28Integrated Asset Delivery Framework
What are the results?
- More time is spent in Concept and Design
Development tasks, but time is saved and problems
are minimized during the contract documentation
stage.
- The process results in better buildings ones
with energy and emission performance roughly half
of current good practice, healthier and more
comfortable indoor environments, and with more
ability to adapt to changing future needs.
- Operating costs are considerably reduced because
of reduced operating energy consumption.
- Maintenance and replacement costs are reduced
because of smaller mechanical plants and more
efficient equipment.
29Integrated Asset Delivery Framework results
Selected data on some high performance buildings
30Integrated Asset Delivery Framework
Available support tools
- The Environmental Performance Guide for Buildings
internet site at asset.gov.com.au/environmentguide
.
- Environmental Performance Guide for Buildings
assessment for spreadsheet used for quick global
performance assessments during concept and design
development.
- Energy analysis software, for preliminary energy
performance analysis.
- Energy simulation software.
- A technical and economic screening of
possibilities for renewable energy.
31Integrated Asset Delivery Framework
Finally...
- We can help you and your designers to design a
better building, one that is more functional and
more environmentally responsible.
- and you can help us to improve the program.
For further information, contact Chris Oh
chris.oh_at_dpws.nsw.gov.au