Title: Active Control of Gas Lift Wells Simulation and Experimental Series
1Active Control of Gas Lift WellsSimulation and
Experimental Series
- Gisle Otto Eikrem
- Department of Engineering Cybernetics
- Norwegian University of Science
- and Technology
2Overview Gas Lift Wells
- Instability in multiphase flow
- Stabilization methods
- Simulaton results
- Experimental results
- Summary
3Gas Lifted Well
Well Data 2048 m vertical well 5 inch
tubing 2.75 inch production choke 0.5 inch
injection orifice
Annulus
Tubing
4Unstable Flow
5Production Curve
Optimal region
Theoretical production
Stable region
Unstable region
6Introduction Video I
7Multiphase Video I
Video of severe slugging in gas lift well
8Introduction Video II
9Multiphase Video II
Video of controlled multiphase flow Stable flow
10Stabilizing Options
- How to stabilize severe slugging in gas lift
wells - Choking
- Size of orifice / critical flow
- Increase gas rate
- Automatic control
11Minimum Flow Curve
Gravity dominated pressure drop -
unstable friction dominated pressure drop - stable
Gravity
Friction
- Gravity dominated - small rate reduction
- Pressure increase
- Decreasing inflow
- Unstable!
- Friction dominated - small rate reduction
- Pressure decrease
- Increasing inflow
- Stable
12Control Principle
The Principle behind control of severe slugging
in gas lift wells
- Stabilize pressure in bottom of well
- Production choke controls pressure
PT
13Control Structures
Casing Head Pressure
Downhole Pressure
14OLGA Results
Control of Downhole Pressure
15OLGA Results
Control of Casing Head Pressure
16The Laboratory
Production Tubes
Control Panel
Reservoir Valve and Gas Injection
17Laboratory Setup
18Control Structures
Casing Head Pressure
Downhole Pressure
19Experimental Results
Control of Downhole Pressure
20Experimental Results
Control of Casing Head Pressure
21Summary
- How to stabilize gas lift wells
- Possible control structures
- Simulation results
- Laboratory experiments