Title: Net%20Metering%20and%20Utility%20Interconnection
1Net Metering and Utility Interconnection
Presented by Bill Brooks Brooks Engineering
2Technical Interconnection Issues Codes and
Standards
3Who Has a stake in the PV Industry?
- Million Solar Roofs Partnerships
- Electric utility companies
- Electric customers wanting to install a PV system
- PV component manufacturers
- PV equipment and system dealers
- Local jurisdictions enforcing building codes
4Why Do We Need PV Codes and Standards?
- To facilitate the broad acceptance of the
technology among local jurisdictions and
interconnecting utilities. - To maintain minimum requirements for PV products
and their installation. - To standardize and reduce the cost of testing and
certification.
5Who sets codes and standards?
- National Fire Protection Association (NFPA)
- National Electrical Code (NEC)- Electrical Power
System Installation--developed in conjunction
with electrical trade and industry experts. - Underwriters Laboratory (UL)
- Standards for Electrical Equipment
Safety--developed in conjunction with
manufacturers. - Institute of Electrical and Electronic Engineers
(IEEE) - Standards for electrical and electronic
equipment--developed in conjunction with
applicable industry experts. - International (IEC, CENELEC, etc)
6What are the applicable codes and standards for
PV systems?
- NEC Article 690 - Solar Photovoltaic Systems -
Building codes - UBC, SBC, BOCA, local codes - UL Standard 1703, Flat-plate Photovoltaic Modules
and Panels - IEEE 929-2000, Recommended Practice for Utility
Interface of Photovoltaic (PV) Systems (approved
in January 2000) - UL Standard 1741, Standard for Static Inverters
and Charge Controllers for Use in Photovoltaic
Power Systems (published in May 1999)
7What are the common interests of Utilities and
PV manufacturers?
- Provides predictable requirements for design and
installation. - Utility protection departments need to reduce
costs. - Inverter manufacturers need to standardize their
designs to keep costs lower. - Over 3000 utilities with a similar number of
interconnection requirements. - Consensus IEEE standard makes it unnecessary for
utilities to utilize an independent standard. - Inverter manufacturers can build one design that
is widely applicable.
8Utility Interconnection Issues
- Personnel safety
- Equipment protection
- Service reliability
- Power quality
9Utility Interconnection Requirements
- IEEE standard 929
- UL standard 1741
- Utility practice and requirements
- Public utility commission statutes
10UL 1741 Standard for Static Inverters and Charge
Controllers for Use in Photovoltaic Power Systems
- First released in May of 1999
- Has been revised to match IEEE 929-2000
- Compliance with revised document required on
November 7, 2000) - New title reads Standard for inverters,
converters, and controllers for use in
Independent Power Systems.(Nov 8)
11What is UL 1741 and how does it relate to IEEE
929?
- First official version published in May of 1999.
Final version released November of 2000. - 1741 incorporates the testing required by IEEE
929 (frequency and voltage limits, power quality,
non-islanding inverter testing) - 1741 testing includes design (type) testing and
production testing. - Line-tie inverters should have the
wordsUtility-Interactive printed directly on
the listing labelthis makes identification of
the listing much more straightforward (several
inverter manufacturers currently using this
designation).
12How Does a Utility, or a PV-System Purchaser,
Know If An Inverter Meets The Requirements of
IEEE 929?
If it meets the testing requirements of test
standard UL 1741 and has the words
Utility-Interactive printed directly on the
listing label
13Terms and Conditions for Interconnection
- May involve the following
- Metering options
- Size restrictions on metering options
- Carryover credit on monthly billings
- Net Meter or differing buy and sell rates
- Outdoor disconnect requirements
- Insurance requirements
- Interconnection costs
14Net Metered Systems in California(Similar to
some other states)
- Requires a contract with the serving utility
company. - Inverter must be acceptable to utility for
interconnection. - Utility also may have a list of acceptable manual
disconnects to choose from. - Starting January 1, 1999, systems are to be
billed on annual basis. - Starting January 1, 2001, systems may elect
time-of-use net metering (up to 30 increased
financial benefit)
15IEEE 929-2000
- Passed by IEEE Standards Board in January, 2000.
- Represents an excellent primer on PV inverter
interconnection issues.
16The Need for PV Interconnection Standards
- Many utilities were using Rotating Machinery
requirements for PV systems - Many of the Interconnection Requirements were
established in early PURPA days - too many requirements
- telemetery and Utility Grade type relays
- special (and costly) engineering were needed for
each specific utility requirements
17Purpose of IEEE 929
- This recommended practice contains guidance
regarding equipment and functions necessary to
ensure compatible operation of photovoltaic
systems which are connected in parallel with the
electric utility. This includes factors relating
to personnel safety, equipment protection, power
quality and utility system operation. - Power Quality
- Safety and Protection
18IEEE 929 Working Group Consisted of Utilities
and Industry
19What Does IEEE 929Really Impact?
PV Array
Utility System
M
Inverter
20IEEE 929 Outline
- Introduction
- 1. Overview (scope purpose)
- 2. References
- 3. Definitions (inverter, islanding, PCC, quality
factor, etc) - 4. Power quality
- 5. Safety and protection functions
- Annexes
21Power Quality
- Power quality problems in general are rising
because of proliferation of non-linear loads on
utility systems -- all customers suffer - PV should not add to that problem
22Power Quality
- Power Quality
- 1. Service Voltage
- 2. Voltage Flicker
- 3. Frequency
- 4. Waveform Distortion
- IEEE 519
- 5. Power Factor
23Safety and Protection Functions
- 1. Response to Abnormal Utility Conditions
- a. Voltage Disturbances
- b. Frequency Disturbances
- c. Islanding Protection
- d. Reconnect After a Utility Disturbance
- 2. Direct Current Isolation
- 3. Grounding
- 4. Manual Disconnect
24Response to Abnormal Utility Conditions
Trip time refers to the time between the
abnormal condition being applied and the inverter
ceasing to energize the utility line. The
inverter will actually remain connected to the
utility to allow sensing of utility electrical
conditions for use by the reconnect feature.
25Terminology
- Power Conditioning Unit or Inverter
- Line-Commutated Inverters
- Self-Commutated Inverters
- Inverter Shut Down
- The PV Inverter as a UPS
- Power Factor
- Controls Integrated into the Inverter
- Islanding
26The PV Inverter as a UPS
- Some inverters are designed to provide
uninterruptible power to critical loads - The power to critical loads is maintained when
the connection to the utility is severed - When the inverter ceases to energize the utility
line (due to abnormal conditions, the inverter
will continue to maintain the loads connected to
a special distribution panel isolated from the
utility, also no power flows to the utility
27IEEE 929- Annexes
- Annex A (Normative) Minimum Test Procedure for
a Non-Islanding PV Inverter - Annex B (Informative) - Bibliography
- Annex C - PV Inverters and the Utility Interface
(Terminology) - Annex D - Disconnect Switches Utility
Procedures - Annex E - Islanding as it Applies to PV Systems
- Annex F - The PV Inverter Under Utility Fault
Conditions - Annex G - Dedicated Distribution Transformer
28ManualDisconnect Switch
PV Array
Local Loads
Utility System
M
Inverter
29Islanding Testing
30Why do we need testing?
- Utility engineers are required to do testing of
system protection equipment - Testing has a profound impact on an engineers
understanding of how things work. - Example New York utilities require special
tests. - Tests designed to pit PV inverters against
notorious NY waveforms - Three utility engineers from NY visited Sandia to
witness tests - After first day into three-day test procedure,
they said, Lets do something more interesting.
31Anti-Islanding Requirements
- Typical island (no balance between load and
island) - Trip time - 10 cycles (to avoid interference with
reclosing) - Balanced island (real power load between 50
and 150 of PV output, Q ? 2.5) - Trip time - 2 seconds
32non-islanding test procedure
- The load should have a real power match as close
as reasonable (at least within 20) to the PV
system output - and a Q (quality factor) ? 2.5, where QR(C/L)½
- the selected Q ? 2.5 equates to an uncorrected
power factor of 0.37. As power factor increases,
Q decreases. Thus, the test requirement that Q ?
2.5 equates to lines with uncorrected power
factors from 0.37 to unity - RLC load that has been tuned to 60Hz
33Sandia Anti-Islanding Method Basic Concepts
- Frequency and voltage trip points are used
- Error signal from frequency and voltage is
calculated each ½ cycle - Frequency and voltage are then tweaked in the
same direction as error signal - If tweaking results in change, then accelerated
tweaking results to push frequency or voltage to
trip points
34Test Circuit Used at Sandia
35Less Than Sandia SchemeBalanced load and
generation (25 of Capacity)
36Less Than Sandia Scheme(125 of Inverter
Capacity)
37Less Than Sandia Scheme Balanced load and
generation (100 Capacity)
38Sample Test-Using Sandia Anti-Islanding
MethodNote that trip time meets typical
criteria even though test is with balanced
conditions
39Sample Motor Load TestsUsing Sandia
Anti-Islanding MethodRequired trip time - 2
seconds
40Motor Load TestsGeneration to load ratio impacts
41IEEE 1547
- Standard for Interconnecting Distributed
Resources with Electric Power Systems - Approved at June 2003 IEEE Standards Board
Meeting
42IEEE Standards Classification
- Standards documents with
- mandatory requirements (shall)
- Recommended Practices documents in which
- procedures and positions preferred
- by the IEEE are presented (should)
- Guides documents in which alternative approaches
- to good practice are suggested but
- no clear-cut recommendations are made (may)
- IEEE Standards are Voluntary.
431547 Body of Standards
1547 Standard for Interconnecting Distributed
Resources with Electric Power Systems
Guide for Networks
Guide for Impacts
P1547.3 Draft Guide for Monitoring, Information
Exchange and Control of DR Interconnected with
EPS
Guide for Islanding Anti-Islanding
Guide For Interconnection System Certification
1547.1 Draft Standard for Conformance Test
Procedures for Equipment Interconnecting
Distributed Resources with Electric Power Systems
P1547.2 Draft Application Guide for IEEE P1547
Draft Standard for Interconnecting Distributed
Resources with Electric Power Systems
DP Specifications and Performance
The above schematic identifies existing
standards development projects and potential
future activities under discussion by P1547 Work
Group members.
441547 Interconnection Is The Focus
Area Electric Power System (EPS)
Interconnection System
Distributed Resource (DR) unit
451547 Interconnection Terms
46IEEE 1547 Contents
- INTRODUCTION
- 1.0 OVERVIEW
- 1.1 Scope
- 1.2 Purpose
- 1.3 Limitations
- 2.0 REFERENCES
- 3.0 DEFINITIONS
47IEEE 1547 Contents
- 1.1 Scope
- This standard establishes criteria and
requirements for interconnection of distributed
resources (DR) with electric power systems (EPS). - 1.2 Purpose
- This document provides a uniform standard for
interconnection of distributed resources with
electric power systems. It provides requirements
relevant to the performance, operation, testing,
safety considerations, and maintenance of the
interconnection. - The requirements shall be met at the point of
common coupling (PCC), although the devices used
to meet these requirements can be located
elsewhere. This standard applies to
interconnection based on the aggregate rating of
all the DR units that are within the Local EPS.
The functions of the interconnection system
hardware and software that affect the Area EPS
are required to meet this standard regardless of
their location on the EPS. - The stated specifications and requirements, both
technical and testing, are universally needed for
interconnection of DR, including synchronous
machines, induction machines, or power
inverters/converters, and will be sufficient for
most installations.1 - 1 Additional technical requirements and/or tests
may be necessary for some limited situations.
48IEEE 1547 Contents
4.0 INTERCONNECTION TECHNICAL SPECIFICATIONS AND
REQUIREMENTS 4.1 General Requirements 4.2
Response to Area EPS Abnormal Conditions 4.3
Power Quality 4.4 Islanding 5.0
INTERCONNECTION TEST SPECIFICATIONS AND
REQUIREMENTS 5.1 Design Test 5.2 Production
Tests 5.3 Interconnection Installation
Evaluation 5.4 Commissioning Tests
5.5 Periodic Interconnection Tests ANNEX A
(INFORMATIVE) BIBLIOGRAPHY
49IEEE 1547 Contents
- 4.1 General Requirements
- 4.1.1 Voltage Regulation (Dont!)
- 4.1.2 Integration with Area EPS Grounding
(Coordinate) - 4.1.3 Synchronization (lt5 voltage fluctuation,
no flicker) - 4.1.4 Distributed Resources on Distribution
Secondary Grid and Spot Networks - 4.1.4.1 Distribution Secondary Grid Networks
- 4.1.4.2 Distribution Secondary Spot Networks
- 4.1.5 Inadvertent Energization of the Area EPS
(Dont!) - 4.1.6 Monitoring Provisions
- 4.1.7 Isolation Device (Disconnect Switch)
- 4.1.8 Interconnect Integrity
- 4.1.8.1 Protection from Electromagnetic
Interference (C37.90.2) - 4.1.8.2 Surge Withstand Performance (C62.41 or
C36.90.1) - 4.1.8.3 Paralleling Device (withstand 220 of
rated voltage)
50IEEE 1547 Contents
- 4.2 Response to Area EPS Abnormal Conditions
- 4.2.1 Area EPS Faults (detect faults, cease to
energize) - 4.2.2 Area EPS Reclosing Coordination
(coordinate) - 4.2.3 Voltage (lt60V,106V 132V, gt144V)
- 4.2.4 Frequency (59.3 60.5 Hz)
- 4.2.5 Loss of Synchronism (not required unless
there is flicker) - 4.2.6 Reconnection To Area EPS (up to 5 min,
C84.1 Range B) - 4.3 Power Quality
- 4.3.1 Limitation of DC Injection (gt0.5 of rated
output current) - 4.3.2 Limitation of Flicker Induced by the DR
(Dont) - 4.3.3 Harmonics (IEEE 519)
- 4.4 Islanding
- 4.4.1 Unintentional Islanding (Dont)
- 4.4.2 Intentional Islanding (Dont know)
51IEEE 1547 Contents
- 5.0 INTERCONNECTION TEST SPECIFICATIONS AND
REQUIREMENTS - 5.1 Design Test
- 5.1.1 Response to Abnormal Voltage and Frequency
- 5.1.2 Synchronization
- 5.1.3 Interconnect Integrity Test
- 5.1.3.1 Protection From Electromagnetic
Interference (EMI) - 5.1.3.2 Surge Withstand Performance
- 5.1.3.3 Paralleling Device
- 5.1.4 Unintentional Islanding
- 5.1.5 Limitation of DC Injection
- 5.1.6 Harmonics
- 5.2 Production Tests
52IEEE 1547 Contents
- 5.3 Interconnection Installation Evaluation
- 5.3.1 Grounding Integration with Area Electric
Power System - 5.3.2 Isolation Device
- 5.3.3 Monitoring Provisions
- 5.3.4 Area EPS Faults
- 5.3.5 Area EPS Reclosing Coordination.
- 5.4 Commissioning Tests
- 5.4.1 Unintentional Islanding Functionality Test
- 5.4.1.1 Reverse-Power or Minimum Power Test
- 5.4.1.2 Non-Islanding Functionality Test7
- 5.4.1.3 Other Unintentional Islanding
Functionality Tests - 5.4.2 Cease to Energize Functionality Test
- 5.5 Periodic Interconnection Tests
53SCC21 Interconnection Projects
53
54SCC21 Interconnection Projects
54
55SCC 21 Contact Information
- Dr. Richard DeBlasio
- email ddeblasi_at_nrel.gov
- voice (303) 275 - 4333
- Mr. Tom S. Basso
- email thomas_basso_at_nrel.gov
- voice (303) 275 - 3753
- IEEE SCC21 -- IEEE Standards Coordinating
Committee 21 on Fuel Cells, Photovoltaics,
Dispersed Generation, Energy Storage
http//grouper.ieee.org/groups/scc21/ - P1547 Draft Standard for Interconnecting
Distributed Resources - with Electric Power Systems -- web site and
archives - http//grouper.ieee.org/groups/scc21/1547
- http//grouper.ieee.org/groups/scc21/1547/ar
chives/
NREL 1617 Cole Blvd. MS-1614 Golden, CO
80401-3393 http//www.nrel.gov
55