Title: Background
1(No Transcript)
2Background
- The electrification programme was started by
Eskom during the late 1980s - It was further refined by the National
Electrification Forum (NELF) during the
early 1990s. - Access to electricity for households in RSA was
approximately 30. - During this period the electrification programme
was funded through the National Electricity
Regulator (NER)
3Background Cont.
- After 1994 and through the governments
initiative of RDP (Reconstruction and Development
Programme), electrification programme was
endorsed. - During 2001 the government took responsibility
for funding electrification programme. - The funds are made available from the fiscas
- Presidents State of Nation Address (universal
access in RSA by 2012)
4MANDATE OF INEP
- To manage the electrification planning, funding
and implementation process, with the aim of
addressing electrification backlog so as to reach
universal access by 2012. - Our Focus areas
- Managing the electrification planning process
- Managing the electrification funding allocation
- process
- Managing the electrification implementation
process - Monitor the INEP in line with the Energy white
paper, - the Division of Revenue Act (DoRA, Public
- Finance Management Act (PFMA),ER Act, OHS Act
- etc.
5SITUATIONAL ANALYSIS
6National backlog (Households)
7National backlog cont.(H/H)
8National backlog (Schools and Clinics)
9Electricity value chain
GENERATION
Electricity is Generated by burning of fossil
fuels (coal, oil, or natural gas), use of nuclear
technology and hydro capability
2
TRANSMISSION SUBSTATIONS
MUNICIPALITIES
1
TRANSMISSION LINES
3
TRANSMISSION (400/275 kV)
High Voltage electricity is carried between
Generation and required Distribution through
Transmission networks (or Transmission grids)
DISTRIBUTION LINES
POWER STATIONS
DISTRIBUTION (132/33 kV)
The distribution networks collect stepped down
electricity from the transmission networks and
deliver it to Redistributors /End Users
DISTRIBUTION SUBSTATIONS
The voltage levels of electricity are further
transformed to meet Distribution requirements
SERVICE CONNECTION
RETICULATION HV LINE (11 22kV)
Customer consumption is measured at the point of
supply in KWh. This information is used to
measure and bill consumption levels utilised/sold
RETICULATION LV LINE (380/220V)
10Electrification Plan (Actual data)
11Electrification Projected Trend
12CHALLENGES
- Challenges in the Electricity industry in South
Africa - Ageing electricity infrastructure
- Minimum or no investment by respective
distributors (municipalities) in the operation
and maintenance of the electricity infrastructure
to date, hence lack of maintenance. - Increased blackouts and brownouts in the country,
concern for quality and security of supply for
the 2010 FIFA World cup - Limited or lack of adequate skills at local
government level for operation and maintenance
electricity infrastructure.
13Electrification outputs Project life cycle
Pre-Engineering and Detailed design
Household connection
80
- Construction for backbone infrastructure
- Poles
- Cables MV and LV
15
5
Start
Finish
14Electrification outputs Project life cycle
Pre-Engineering and Detailed design
Household connection
80
- Construction for backbone infrastructure
- Poles
- Cables MV and LV
15
5
Start
Finish
15Projected outputs for MTEF
16DoRA FRAMEWORK
17Comments (current)
- Current framework support the projected outputs
- Connections for households, schools and clinics
- Building of bulk infrastructure
- Assist in monitoring performance
- Reallocate funding were is required (if necessary)
18Comments (future)
- Have a schedule that allows funding of DSM and
Energy Efficiency initiatives for municipalities - Framework outputs
- MW shifted through the programme
- Assist in monitoring performance
- Process to be initiated with National Treasury
19INSTITUTIONAL AND LEGISLATIVE FRAMEWORK
- Electricity Regulation Act (Act. No 4 of 2006)
completed, will be used to - Monitor compliance to the quality of supply
regulations (to be completed by the end of
October 2006. - Enforce penalties to distributors for
non-compliance - Improve integration during planning process with
municipal IDP. - Eskom progress report to municipalities as per
DoRa requirement
20THANK YOU Questions.?