Title: Victoria Chamber of Commerce March 13, 2002
1Victoria Chamber of CommerceMarch 13, 2002
2Current Vancouver Island Electricity Supply
- 80 of Vancouver Islands electricity is supplied
by sub-marine cables from the mainland - 20 is supplied by six Hydro plants on the Island
- High Voltage Direct Current (HVDC) cable system
to the Island is deteriorating (scheduled for
complete retirement by 2007 - this transmission
capacity needs to be replaced)
3The Proposed Pipeline (contd)
- 140 km natural gas transmission pipeline from the
Sumas supply hub to an interconnect with the
Centra transmission system on Vancouver Island
near Duncan - Canadian segment
- 60km - 44km marine and 16 km on -island
4Growing Demand for Electricity
- Forecasted growth 30-40 Megawatts per year on
Vancouver Island - Increase in electricity intensive technologies
businesses - Increased square footage of residential
structures - Increased disproportionate use of electrical
heating systems versus gas, wood and oil (BC 20
- VI 40) - Need for secure reliable power to attract new
businesses - Population growth 21 since 1991
5Vancouver Island Electricity Supply Demand
6Options 2002 - 2007
Option 1 Repair/Replace HVDC cables 230
million New mainland generation 600 (VIGP
1 2 equiv. ) New mainland transmission
upgrades 50 Centra Gas System
upgrades 110 Total 990 million
7Options 2002 - 2007
Option 2 Demand Side Management 75
million (300 million province wide) Green
Alternative Energy 3.4 billion Biomass,
Wind, Wave, Micro-Hydro No transmission
costs considered Centra upgrade 110
million Total 3.585 billion Capacity Only
(i.e.) no guarantee the power is there when you
need it
8Options 2002 - 2007
Option 3 GSX Pipeline 260 VIGP 1 (Duke
Point) 300 VIGP 2 (unknown) 300 Total
860 million Shared joint-venture costs
9Options 2002 - 2007
Option 4 GSX Pipeline 260 million VIGP
(Duke Point) 300 Demand Side Management
75 Green and Alternative Energy 525
Total 1.16 billion Objective to defer VIGP
2 (third plant) 5 to 10 years. Shared joint
venture costs
10Georgia Strait Crossing Project
- New natural gas marine pipeline connection
between the mainland and Vancouver Island - BC natural gas
- Safest environmental and seismic route
- Joint project between BC Hydro and Williams -
share cost - Approx. cost - 260 million Cdn.
- NEB oral hearings begin June 17, 2002
- In-service date - Oct. 2004
11Vancouver Island Generation Project
- Replacement project for the Project Alberni
Generation Project - Site acquisition complete April 2002
- Submit Application to BC Environmental Assessment
Office (BCEAO) late Spring 2002 - Anticipated construction period - Spring 2003-Nov
2004 - In-service date of November 2004 is critical
12Site Criteria
- Social, environmental and economic considerations
- Industrial zoning
- Community support
- 10 acres flat plus 10-15 acres construction
staging - Fresh water and waste
- Access to gas pipeline and transmission corridor
13Site Selection Process
- 12 sites shortlisted to 4
- City of Nanaimo, Duke Point (2)
- Nanaimo Regional District (1)
- District of North Cowichan(1)
- Duke Point is the preferred option at this time
14Delay Consequences Beyond 2004
- Peak season November - February curtailments
- major customers, shutdowns, economic dislocation
- location specific brownouts - North Island, West
Island, South Island - Large customers switch to high polluting fuels
- Purchases from market - more expensive, more coal
15Vancouver Island Alternative/Green Generation
- Wind 10 megawatts
- Micro-hydro 7-9 megawatts
- Wave 3-4 megawatts
- Biomass 200 MW
- Challenges
- cost
- location
- connection
- reliability
- volume
16Demand Side Management/ Power Smart
- 1990-2000
- annual reduction of 2500 GWh of consumption or
would require 500 MW additional generation - 350 million
- 2002 - 2012
- annual reduction of 3500 GWh
- 600 million
- examples - energy audits, LED, SUCH
17Questions