Title: Avnel Gold Mining Limited
1Avnel Gold Mining Limited
TSX AVK, AVK.WT
2PRESENTATION DISCLAIMER
- Caution Regarding Forward Looking Statements
- Statements regarding the corporations plans
with respect to the Kalana Mine and exploration
of the Kalana Permit are forward-looking
statements. There can be no assurance that the
planned ongoing development of the Kalana Gold
Mine will be completed as forecast or that the
exploration program on the Kalana Permit will
identify minerals resources. -
- The TSX has neither approved nor disapproved the
form or content of this information release.
3Emerging Gold Producer
- Canadian Main Board listed mining company
operating in Mali - Current production of 19,000oz p.a. rising to
27,000oz p.a. _at_275/oz cash cost - Currently defined resources of 1.0M oz, including
428,000ozs PP Reserves - Exploration success on 387 sq.km Permit close to
mine - Highly experienced management team
4Growth Strategy
- Increase annual production at existing Kalana
underground mine to 30,000ozs at 275/oz by 2008.
Potential to increase to 50,000 ozs per annum by
2010 - Explore Permit and identify potential new ore
resources, such as the Djirila discovery - Convert Kalana open pit resources (3M tonnes
containing 449,000 ozs) into reserves - Construct new gold plant to process Kalana ore
and new satellite ore resources- target 150,000
to 200,000 ozs per annum.
5Mali - Overview
- Stable democracy
- Established mining code
- Several world class mines resulting from
discoveries Sadiola, Loulo, Syama, Morila etc. - Good infrastructure particularly at Avnels
Kalana Mine site
6Permit
- Avnel owns 80 interest in Kalana Permit (mine
exploration) in Mali (20 Mali Government) - Unique 30 year mining permit for both Kalana Gold
Mine and surrounding 387 km2 concession area - No loss of property over permit duration - 30
years to explore and develop - can be extended - US2.5 million acquisition cost for mine and
concession in 2003
7Morila
Guinor
Syama
Siguri
8Kalana Gold Mine Mineral ResourcesDecember 2005
- Measured Indicated Resources
- Underground veins 1,631,000t 14.2g/t
747,000 oz - Underground stockwork 247,000t 4.2g/t
34,000 oz - Open Pit 873,600t 7.12g/t
200,000 oz - Tailings 294,000t 2.04g/t
19,000 oz - TOTAL 3,045,000t 10.2g/t 1,000,000
oz - Inferred Resources
- Underground 429,000t 6.2g/t 85,000 oz
- Open Pit 2,261,000t 3.4g/t 249,000 oz
- Resources classified under NI 43-101
9Underground Reserves Dec 2005
- Proven 55,000t _at_ 15.8g/t 28,000 oz
- Probable 881,000t _at_14.1g/t 400,000 oz
- Total 936,000t _at_14.2 g/t 428,000 oz
- Reserves lie between 100m and 300m below
surface. - Reserves based on NI 43-101. The Reserves are
included in the Measured Indicated Resources.
10Drill Holes - Veins 1,18,19,20
Surface
400rl
No 1 shaft
No 1 shaft
No 2 shaft
No 2 shaft
Kalana 1 open pit
Kalana 1 open pit
295 level
100 level
Vein 1
Vein 1
Vein 18
Vein 18
Vein 19
Vein 19
Vein 20
Deeper Veins 21,22 23 (not shown) are in the
indicated inferred resources
Vein 20
300 level
Deeper Veins 21,22 23 (not shown) are in the
indicated inferred resources
100 level
11Mine Operation
- Shallow underground mine (100m to 300m depth)
- High Grade quartz veins (1.4m width)
- Conventional mining with handheld drills, winches
and 3t locomotives - Grid electric power on site
- Gravity plant budget 79 to 84 gold recovery
- Production 2004 - 7,396 ozs 2005 -14,900 ozs
- 2006 estimate 18,900 ozs
- Focus on shaft deepening and mine development
12No.1 Vein o/crop
No. 1
No. 2
crusher
plant
Power grid
View of Surface Infrastructure
13Mine Operation
- Mine currently planned to produce over 26,000oz
p.a. from 2008 to 2014 - Operating costs expected to drop US275/oz by
2008 - Head grade expected to average 17.3 g/t with mill
recovery (gravity only) of 79 to 84 - Mine grades are generally exceeding reserves
forecast. Block Factor 170 in 2005 - Priority - open up new areas and deepen shafts
141Shaft
2 Shaft
100
150
North
South
180
220
260
15Mine Development Schedule
- Deepen 2 Shaft to 190 level- Sept 2006
- Develop 150 level North to vein 18- Oct 2006
- Develop 180 level South to vein 18/18a- June 2007
- Develop 180 level North to vein 18/19- December
2007 - Deepen 1 Shaft to 300 level- December 2008
- Develop 220 level South to vein 18/18a- September
2008
16Higher Gold Grade Trend
- Grade increasing as mining dilution reduces and
higher in situ gold values than reserves estimate - 2004 10.6g/t
- 2005 17.2g/t
- 2006 25.0g/t (quarter 1)
- Ore Reserve Reconciliation (vein 1)
- 2005 actual grade 19.15g/t vs 14.4g/t reserve
grade - Block factor Au content 170 (70 more gold)
- Block factor tonnes 130 (30 more tonnes)
- 1985-2001Block factor Au content 130
17Key Sensitivity Parameters
- Business Plan
Expansion - FCF _at_375/oz 24M 39M
- IRR _at_375/oz 17 28
- FCF _at_625/oz 63M 101M
- FCF _at_10 grade 34M 52M
- FCF _at_625/oz 78M 122M
- 10 grade
- Free Cash Flow pre tax
18Mine Exploration and Development
- Underground drill program to increase data
density (and possibly grade) for ore reserve
blocks between 180 and 260 levels- scheduled
2008/2009 - Infill underground drilling programme to convert
inferred resources into indicated resources-
scheduled for 2009/2010 - Assess optimum expansion potential of the
underground mine - Infill drill the surface deposits ( Indicated
Inferred Resources 468,000ozs) and establish open
pit designs- schedule 2008 - Investigate suitable mill size given potential
ore supply from surrounding area
19Permit Exploration Strategy
- To find proximal resources to existing Kalana
Mine - and within the Permit- establish a Gold
Camp - Soil geochemistry is most effective first stage
exploration tool - To drill priority targets (9 gold anomaly targets
identified on the 40 of the Permit area sampled) -
20Exploration Results - Phases 1 2April to
December 2004
- 10 priority grids sampled
- Geochemical sampling results show significant
Au-in-soil anomalies on 9 grids - Au-As anomalies show good correlation
- Significant structures identified with 1km
strike length and 200m width on 9 grids
21Location of Priority Grids
SOIL GEOCHEMISTRY GOLD ANOMOLIES
Kalana Mine 1,000,000 oz Mineral Resource
MI 428,000 oz Reserve (PP)
Kalanako 70,000 oz Russian Geological
Resource
22Phase 3 Significant drill resultsMarch- June 2005
- Two main gold-bearing zones identified new gold
discovery on Grid 8 - Significant assay results including
- Djirila Main zone 5.4g/t over 36 m including
73.6g/t over 2m 45.9g/t over 4m - Djirila South zone 4.1g/t over 6m 8.3g/t over
22m - 6 holes ended in mineralisation
- One RAB hole intersected 8.0g/t over 4m on the
Badani zone, NE of Djirila
23Djirila Main South Zone
24Phase 4 Significant Drill ResultsNovember 2005-
February 2006
- 15 diamond drill holes at Djirila Main and South
- Significant assay results include
- 11.14g/t over 24m from 68-92m in DDH02
- 4.81g/t over 10m from 136-146m in DDH02
- 14.57g/t over 3m from 98-101m in DDH06
- 19.3g/t over 2m from 46-48m in DDH11
- 12.55g/t over 19m from 80-99m in DDH11
- 5.72g/t over 2m from 120-122m in DDH11
- 3,04g/t over 7m from 120-122m in DDH12
- 3.74g/t over 14m from 98-112m in DDH13
- 3.14g/t over 3m from 113-116m in DDH14
25(No Transcript)
26(No Transcript)
27Djirila Main Zone
- Djirila Main has been identified by RC and DDH
programs. It is a fault controlled,
quartz-vein-stockwork zone characterised by high
grade mineralisation between surface and 100m - Zone is 225m long on a NNE strike and artisinal
workings extend 150m beyond this zone - Vertical to steep easterly dip
- 3m to 50m width
- Open at depth and along strike
28W-E Section Djirila Main
29 Phase 4 February- July 2006
- RC drill program to build a resource base and
test the continuity of Djirila Main Zone - RC Drill gold anomaly targets on Grid 7, one of
the 8 other gold anomaly targets on the permit - 54 RC holes (5100m) are proposed
- Current drilling budget US388,000
- Extensive soil sampling programme over at least 3
areas budget US150,000
30Phase 4 Geochemical Sampling Grids
31Management
- Executive Chairman Howard Miller
- CEO Roy Meade Mining Engineer
- CFO Andrew Herbert
- Mine General Manager Koos Grove
- Exploration Consultants Jack Hamilton Michel
Mercier - In Country Director Ibrahim Kantao (ex DG of
DNGM)
32Current Capital Structure
- Shares Issued
- Public IPO 12,393,065
- Promoters 35,000,000
- Private Placement 7,936,000
- Issued for interest on loan 390,139
- Total issued 55,719,744
- Shares Reserved Can
- Warrants (5 year listed) 6,196,801 _at_ 1.06
- Warrants (2 year unlisted) 7,936,000 _at_ 1.30
- IPO Agents warrants (2 years)
419,499 _at_ 0.76 - Private Placement Brokers warrants (2 years)
1,117,200 _at_ 1.00 - Minority shareholder warrants 1,050,000 _at_
US0.275 - Minority shareholder warrants 435,400
_at_ 0.95 - Convertible loan note (5 years)
13,427,476 _at_ 0.95 - CEO Compensation Options 2,500,000 _at_
US0.275 - Stock Options 1,850,000 _at_ 0.76
- Total warrants/options 34,932,376
33Pre-Offering Capital Structure
- Elliott and Associates (fund management group)
Fern Trust (family of Howard Miller, Chairman)
equally invested 21 million to end of 2004 - 21.88 million capitalised 5050 into 35 million
common shares and a 5-year convertible note - 2.8 million bridging loan converted into a Term
Loan due 31 December 2007 - Management and associates own 40 of company
- US7.6m (pre expenses) raised in June 2005 8
institutions/high worth individuals
34Private PlacementNovember 2005
- Issued 7,936,000 units at C1.00 per unit
- Unit consists of 1 common share and one share
purchase warrant - Warrants exercisable for 2 years at C1.30
- 4 European and North American institutions
35Avnel Gold Mining Limited