Project Estimation - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

Project Estimation

Description:

An estimate is the most optimistic prediction that has a non-zero ... All we want to know is time and effort, dominating cost factors, ... anything's better ... – PowerPoint PPT presentation

Number of Views:117
Avg rating:3.0/5.0
Slides: 18
Provided by: Robert9
Category:

less

Transcript and Presenter's Notes

Title: Project Estimation


1
Project Estimation
  • CS4320
  • Fall 2003

2
Estimation
Estimate Definition An estimate is the most
optimistic prediction that has a non-zero
probability of coming true. -- Tom Demarco
What is the earliest date that you cant prove
you wont be finished?
3
Estimation The motivation
  • All we want to know is time and effort,
    dominating cost factors, risk factors?
  • A survey of 598 development organizations
  • 35 dont make an estimate
  • 50 record no data on ongoing projects
  • 57 do not use cost accounting
  • 80 had overruns in cost/budget and schedule
  • Mean overrun is 50

4
Estimationthe problems
  • Lack of historical data
  • Estimates done hurriedly
  • Complete specifications not available
  • Characteristics of software development
  • Rapid changes in methodologies
  • Lack of experience (how many projects do you
    actually manage?)
  • Optimism of developers
  • Difference in experience levels (who are you
    estimating for?)
  • No linear relation in development (if 1 developer
    takes 1 year, 2 developers must only take 6 mo)
  • Estimate modification for low bid

5
Cost Estimation Process
6
Categories (Jones)
  • Project-Level using rules of thumb, Math Models
  • Phase-Level using ratio/percent,
  • Activity-Based using WBS

7
Categories (Boehm)
  • Algorithmic (Estimate to math model)
  • Expert Judgment (Estimate to experience)
  • Analogy (Estimate to similar systems)
  • Parkinsons Law (Estimate to resources)
  • Price to win (Estimate to customer budget)
  • Top-Down (Estimate via functionality)
  • Bottom-up (Estimate via modules)

8
Rules of Thumb
  • LOC (RD Table 8-10)
  • Previous Experience, Analogy
  • Putnam Models (Rayleigh Curve)
  • C Technology Constant (Tools, Languages, etc)
  • Poor 2000, Good 8000, Excellent 11000
  • T Required Development Time (Years)
  • S Size in LOC
  • B Total Lifetime Effort (staff-months)
  • E Total Development Effort
  • B(1/T4)(S/C)3
  • E .3945B

9
Activity-Based
  • Wide Band Delphi
  • Group of developers meets for estimate
  • Facilitator runs meetings
  • Data submitted anonymously by individual
  • Each individual submits estimates by activity
  • Facilitator posts and then tries to get
    convergence through multiple rounds of estimation
  • CPM/PERT
  • Draw Activity Network
  • Assign resource estimates per activity
  • Sum for totals

10
Function Points
Compute Unmodified Function Points
Total UFP
11
Function Points
0 Not present 3 Average 1
Insignificant 4 Significant 2 Moderate
5 Essential
Adjust for Technical Complexity (TCF) Rate each
item 0-5 and sum
E1 Reliable data backup E8 Online Update
E2 Data Communications E9
Interface Complexity E3 Distributed Functions
E10 Reusability E4 Performance
E11 Process Complexity E5
Operational Environment E12 Installation
Ease E6 Online Data Entry E13
Multiple Sites E7 Multiple Input Screens E14
Ease of Use
FP UFP (0.65 0.1 TCF)
12
Function Points
Use this table to convert FP into
LOC. Documentation pages FP1.15 Test Cases
FP1.2 Defects FP1.25 Months
FP.4 PeopleFP/150 Maint PeopleFP/750
People also do project tracking via FP Errors
per FP per FP FP per person-month
13
Some Historical FP Numbers
  • APPLICATION Size KLOC Size FP
  • MS Office 1,250 10,000
  • WMCCS 18,000 175,000
  • MS Project 375 3,000
  • Windows95 11,000 85,000
  • 5ESS 1,500 12,000

14
Function Points and Use Cases
  • Actors
  • Simple Machine API 1 point
  • Average Human Cmd Line, Machine protocol 2
    points
  • Complex Human GUI 3 points
  • Use Cases
  • Simple lt4 key scenarios 5 points
  • Average gt4 lt8 scenarios 10 points
  • Complex gt8 scenarios 15 points
  • Adjust With FP Technical Adjustments as with FP
  • Each UCP requires 20-30 hours of effort

15
Regression Models
  • Constructive Cost Model (COCOMO II)
  • Development Effort E a sizeb C
  • Where a and b are constants determined by project
    and C is a cost factor adjustment

16
COCOMO II Cost Drivers
  • Software reliability 
  • Size of application database 
  • Complexity 
  • Analyst capability 
  • Software engineering capability 
  • Applications experience 
  • Virtual machine experience 
  • Programming language expertise 
  • Performance requirements 
  • Memory constraints 
  • Volatility of virtual machine 
  • Environment 
  • Turnaround time 
  • Use of software tools 
  • Application of software engineering methods 
  • Required development schedule 
  • Values are assigned by the manager.

17
Estimation
  • Only as good as our initial estimate
  • No one great technique
  • Almost anythings better than a SWAG
  • If we work at it, and capture data about our
    company, we can improve our estimation
  • What does INFOSYS use?
Write a Comment
User Comments (0)
About PowerShow.com