Title: PROJECT MANAGEMENT ENCE7323 TO 763N
1PROJECT MANAGEMENTENCE-7323TO 763-N
- CLASS 2
- September 10, 2000
- Carl E. Edlund
- 214-665-8124
- cedlund_at_prodigy.net
edlund.carl_at_epa.gov
2PROJECT PLANNING AND SCHEDULING (PART 1)
- 1.0 Concepts in Class 1 also discuss NPDES
Outfall - 2.0 Review Homework No. 1
- 3.0 Nature/importance of Project Planning and
Scheduling - 4.0 Planning and Scheduling Tools
- 5.0 Fundamentals of the Critical Path Method
(CPM) - 6.0 Benefits/drawbacks of CPM
3PROJECT MANAGERS CONSTRAINTS
TIME
COST
PEOPLE EQPT FACIL. MTL INFO TECH
RESOURCES
PERFORMANCE / TECHNOLOGY
4EVOLUTION OF WORK1900 INDUSTRIAL MODEL
L
M
M
M
FOREMEN
T
T
T
T
T
5DIFFERENCESProduction Line vs Project
Organization
6EVOLUTION OF WORK
2000 TALENTED TEAM MODEL WORK IS HOLISTIC
K. S. As - MGMT - TASK - TEAM - L- SHIP
PROJECT TEAMS
M
L
TS
T
7HOMEWORK NO. 1CRITIQUING A PROJECT
- SCENARIO
- On October 28 of last year, John Smith, a
recently promoted project manager with the
consulting firm of Succup Druel, Inc. (SD),
received a call from Jane Doe, the Environmental
Manager for Acme Industries. Ms Doe asked Smith
to submit a proposal to conduct an initial
investigation of a suspected release from one of
the underground storage tanks (USTs) at the
company's fueling facility.
8HOMEWORK 1 CRITIQUING A PROJECT
- 10/28 Jane Doe Acme called John Smith SD
- Proposal for leaking ? UST
- Fast! TNRCC needs
- John Smith
- Limited Project Management experience
- Consulted Hoss Ritter good feedback
- Prepared proposal
9HOMEWORK 1 CRITIQUING A PROJECT
- Smiths proposal
- Consistent with regs
- Soil gas survey
- Sampling and analysis
- 4 borings developed as GW wells
- Costs
- Consistent with TNRCC requirements
- Lab and drilling contract estimates based on last
years project
10HOMEWORK 1 CRITIQUING A PROJECT
- Jane Doe Acme
- Verbal approval, contract
- Agreed with scope, budget,schedule
- December 31 deadline !!
- Project Team
- John Smith
- Gray Hare
- Carole Lumbardy
- Yan Nu
11HOMEWORK 1 CRITIQUING A PROJECT
- Project Tasks
- 1. Initial reconnaissance
- 2. Research site history
- 3. Compile data
- 4. Phase I field investigation
- 5. Evaluate Phase I data
- 6. Prepare report
12HOMEWORK 1 CRITIQUING A PROJECT
13HOMEWORK 1 CRITIQUING A PROJECT
- Planning meeting
- Hare
- Watch drilling and lab contractors .. No bids yet
- Available for Rs
- Subcontracts
- 3 Drillers
- 15 higher than estimate
- 3 Labs
- On target with estimate
14HOMEWORK 1 CRITIQUING A PROJECT
- Progress
- Tasks 1,2 on schedule
- Task 3
- TNRCC approval delay resulted in 1.5 week delay
to start drilling - PSH issue
- 8 hour standby
- additional day per diem for 3 men
- Task 4
- Delay of sample delivery and holiday conflict
- Premium for fast delivery
(only 25)
15HOMEWORK 1 CRITIQUING A PROJECT
- Task 5 done in 5 days
- Task 6
- to Hare for review Wednesday 12/20
- Friday 12/22 Tuesday 12/26
- Thursday 12/28 (all nighter?)
- Friday 12/29 hand delivered to empty Acme office
- Summation
- Doe Great work .. More to come.
- Hare You blew it by how much ?
16HOMEWORK NO. 1CRITIQUING A PROJECT
- Requirement Analyze John Smith's initial
performance as a project manager in terms of
planning, organization, staffing, direction, and
control.
17Project Life Cycle
DEFINE
CLOSE
CONTROL
PLAN
18Project Life Cycle
DEFINITION
- STATEMENT OF WORK
- RESPONSIBILITES MATRIX
- COMMUNICATION PLAN
- CHARTER
- ENLIST SPONSOR
- NAME STAKEHOLDERS
- MAKE RULES
19Project Life Cycle
PLANNING
- RISK LOG
- SCHEDULE
- BUDGET
- RESOURCE PLAN
- RISK MANAGEMENT
- DETAILED SCHEDULING
- RESOURCE ESTIMATING
20Project Life Cycle
CONTROL
- MEASURE PROGRESS
- COMMUNICATION
- CORRECTIVE ACTION
21Project Life Cycle
CLOSEOUT
- RECONCILE ACCOUNTS
- LESSONS LEARNED
- PREPARE FOR NEXT JOB
- FINAL PRODUCT
- CUSTOMER ACCEPTS
22Project Life Cycle
DEFINE
CLOSE
CONTROL
PLAN
FEEDBACK CHANGES CORRECTIONS
23PROJECT PLANNING AND SCHEDULING
- The project manager uses a planning and
scheduling process because most projects are
complex and of long duration and require
visualization of their parts, when they should
occur, and the resources needed. A planning and
scheduling process
24PROJECT PLANNING AND SCHEDULING
- Identifies project activities (tasks/steps)
- Identifies the sequence and duration of project
activities - Organizes project resources (labor, equipment,
materials, technology, facilities) - Enables monitoring of project progress
25PLANNING AND SCHEDULING TOOLS
- Bar (Gantt) charts
- Critical Path Method (CPM) and Program
Evaluation Review Technique (PERT) - Level of Effort (Manual v/s Computerized
Applications)
26BAR (GANTT) CHARTS
- Key Elements
- Activity List
- Time Line
- Activity Duration Assignments
- Example(next page)
- Strengths/Weaknesses
- Applications
- Proposals
- Status Briefings
- Work Schedules
- In-Class Practical Exercise
27EXAMPLE
2001
Sep
October
November
Task Name
29
13
20
27
3
17
24
6
10
PROJECT KICKOFF MEETING
PROJECT COORD. EQUIP. MOB.
FIELD WORK
LAB TESTING DATA VALIDITY
DATA REVIEW REPORT PREP.
DRAFT REPORT COMPLETION
28PRACTICAL EXERCISE
- On September 1 Horace Kantwate, a seasoned
project manager for SD, received a call from
ERU's Bob Jones. Jones asked Kantwate for a
rough schedule of work that would needed to
submit a permit application for a new solid waste
landfill that ERU planned. SD was to assume a
January 2002 start date for beginning the
permitting project e.g. submit draft permit to
SEA. After getting preliminary information on
the type, size, and location for the landfill,
Kantwate
29PRACTICAL EXERCISE
- prepared a schedule. The tasks and estimated
durations were as shown below - Activity Estimated
Duration(days) - Preliminary Investigation and
- Feasibility Study
50 - Field Investigation
60 - Engineering Analysis and Design
40 - Permit Preparation
80 - Requirement Prepare a Bar (Gantt) chart schedule
for the proposed landfill permitting project
CAN the permit be submitted before the end of
January?
30FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- Critical Path Method (CPM)
- As a Planning and Scheduling Tool
- It is a formal, graphic means of determining the
relationship between the activities (tasks) in a
project. - It enables systematic isolation of activities
comprising the critical elements that set the
duration of a project.
31FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- It helps the project manager analyze a project
before, during, and after operations. - The greatest asset of CPM is its portrayal of
critical activities, giving the project manager
forewarning of where he or she might expect
schedule problems.
32FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- About CPM
- The core of CPM is a network diagram that
represents the manager's best effort at efficient
planning and scheduling of project activities. - The network diagram consists of arrows
(activities) and circles (events). Activities
represent work and consume resources and time
events do not, rather they mark points in time
when activities begin or finish. The length of
an arrow has no relevance.
33FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- The CPM network has one starting event and one
ending event. - Each activity is bounded by two events, one at
the tail (starting point) and one at the head
(ending point).
Activity
Event
Event
Mobilize
Drill Borings
1
3
2
2
3
i
i
j
j
Duration (Days)
34FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- The event circles bounding an activity are
numbered, the number of the tail event is that
activity's "i" designation the number of the
head event is that activity's "j" designation.
By convention, j is numerically higher than i,
portraying left to right movement through the
network diagram. The j designation of a
preceding activity is the i designation of the
succeeding activity.
35FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- Dummy arrows (dashed lines) may be needed in a
network diagram to show logic or achieve unique
i-j designation for activities dummy arrows do
not consume resources or time.
DUMMY ARROW
A
2
A
3
0
3
1
1
3
3
B
B
2
2
36FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- Network diagrams flow from left to right with
horizontal or vertical numbering of events. See
illustration on next page. - Analysis of the network diagram will disclose the
float time (schedule flexibility) available for
each activity. An activity's Total Float time
represents the delay that can occur in starting
the activity without delaying the overall
project an activity's Free Float time is the
delay the activity can sustain without delaying a
subsequent activity.
37VERTICAL HORIZONTAL NUMBERING
2
6
VERTICAL
3
7
10
13
1
11
8
4
2
3
12
9
5
4
5
6
13
1
9
8
7
HORIZONTAL
12
11
10
38FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- Eight Steps to Using CPM to Manage a Project
- ? Identify the activities (tasks) in the project
and their durations. - ? Determine for each activity the logic that
governs when it can occur, i.e., what must
precede the activity, what can occur at the same
time, and what must follow (precedence,
concurrence, succession).
39FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- ? Draw a network diagram that reflects the best
progression of the project (i.e., order
activities in a logical sequence that minimizes
project duration). For each activity, place the
name of the activity above the arrow and the
duration of the activity below the arrow. - ? Determine the earliest event times (EETs) and
latest event times (LETs) for each event in the
network diagram. -
40FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- Compute EETs
- The EET for Event 1 is 0 (representing the end of
day 0 or the beginning of day 1). - Trace each activity and add that activity's
duration to the preceding EET. The sum will be
the EET for the next event, unless two or more
activities enter that event. IF two or more
activities enter an event, the EET for that event
will be the largest of the computed
41FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- EETs, SINCE activities leaving that event cannot
begin until all activities entering the event are
complete. Place the EET in a box symbol adjacent
to the event symbol. - Continue the procedure from left to right until
reaching the end of the diagram. - The EET for the last event is the earliest
possible time the entire project can be
completed, given the network as drawn and the
activity durations assigned.
42FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- of the activity. The result will be the LET at
the tail of the activity, unless the tails of two
or more activities converge at the event. If the
tails of two or more activities converge, the LET
at the tail event will be the smallest computed
time. To select a larger LET would delay
(extend) the time of the project. Place the LET
in a triangle symbol adjacent to the event
symbol. - Continue from right to left to the beginning of
the diagram.
43FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- ? Determine and highlight the critical path
(those critical activities that define the
duration of the project). Activities are
critical if - The EET and LET at the tail of the activity are
equal. - The EET and LET at the head of the activity are
equal. - The difference between the EET (or LET) at the
head and the EET (or LET) at the tail equals the
activity duration.
44FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- There will be at least one critical path
extending from the beginning to the end of the
project. - ? Tabulate activity times (early start, early
finish, late start, late finish, total float, and
free float) that can help you schedule resources
and identify schedule flexibility. - Early Start (ES) The EET (entered in the box
symbol) at the tail of the activity arrow
45FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- Early Finish (EF) ES Activity Duration
- Late Start (LS) LF - Activity Duration
- Late Finish (LF) The LET (entered in the
triangle symbol) at the head of the activity
arrow - Total Float (TF) LS - ES LF EF
- Free Float (FF) EET (at the head) - EF
46FUNDAMENTALS OF THE CRITICAL PATH METHOD (CPM)
- Interfering float (that which delays a
subsequent activity, but not the total project)
equals TF - FF for a given activity, it is also
equal to the difference between the LET and EET
at the head of that activity's arrow. - ? Schedule activities and allocate resources to
maximize efficiencies and minimize project time. - ? During the project, measure progress taking
action where necessary and modifying the network
diagram as needed.
47SUMMARY OF BENEFITS OF THE CRITICAL PATH METHOD
- Provides graphic representation of the sequence
and interdependency of activities - Enables prediction of project duration
- Highlights critical path activities and project
float time - Enables detailed planning/scheduling prior to
starting the project
48BENEFITS OF THE CRITICAL PATH METHOD (CPM)
- Enables tracking of project activities and timely
response to changed conditions - Can be used for alternatives analysis
- Aids in estimating/allocating resources and costs
and visualizing constraints
49LOOSE CANNONSNO. 3
- Susan Queue, SD project manager, wrestled with
the enormity of the project. There were so many
tasks to accomplish. She wondered what was the
best arrangement of the tasks and how long the
project would take. She knew some tasks could
not start until others were finished, while
others were unconstrained. She wondered how much
flexibility she had in the project, how critical
task start and stop times were, and how to
allocate resources.