Title: SiteManager Review
1SiteManager Review Update
- In service since May 1, 2005
- 1692 projects active in system
- 453 finals paid for 1,053,664.31
- 761 Change Orders approved
- 465 Conversion Estimates Processed
- 9308 Progress Estimates for payments of
1,406,522,955.23
2SiteManager
- Key Dates
- Project Engineer / Project Manager
- Federal or State?
- Change Orders
- DWR
- Diary
- Payments
3SiteManager Key Dates
- If making payment generally should have Begin
Work Date entered! - If called complete by project engineer should
have Work Complete date entered! - Put in Projected Work Complete date and update as
needed! - You get the idea, if you complete inspection,
send report, etc. put in the date!!! Also put in
projected dates as needed.
4SiteManager Key Dates
Remove KEY DATES not needed. If no Structures ie
HMA project, you can remove this date. It can be
re-added if bridge added to contract.
5SiteManager NEW Key Date
KPDES NOI Notice of Intent date sent from
District Office KPDES Coverage Letter with Permit
Number date received back from KPDES with permit
Number, put Permit in Message KPDES NOT Notice
of Termination date sent to KPDES
6SiteManagerChecklist Events Put them in system!
Need dates updated as events occur. Erosion, at
least once a week or rain event Contractor
Evaluation, 12/31 and/or at completion of
project Materials Cert date PR47 if applicable
at end of project
7SiteManagerProject Engineer / Project Manager
- Keep this updated. As Resident change, keep
current in Sitemanager. It is helpful to know
most current person responsible. District
Construction Office Manager (DCOM can update this
field).
8SiteManager Federal Project ?
- If Function is FD52 or FD51, then Federal funds.
FD52 is FHWA, FD51 is FEMA. Also if Fed State
Project Number begins with BRZ, BRO, IM, NH, ADP,
IR it is Federal Funds
9SiteManager Federal Project ? continued
- If Function is FD52 or FD51, then Federal funds.
FD52 is FHWA, FD51 is FEMA. Also if Fed State
Project Number begins with BRZ, BRO, IM, NH, ADP,
IR it is Federal Funds. Report cattext will show
funding.
10SiteManager Change Orders
- To create a copy from SiteManager for review,
create report, open file, save as HTM, open HTM
file in browser and send that via e-mail. The
HTM can be viewed from e-mail. No need to scan
or paste into WORD, use the HTM file.
11SiteManagerChange Orders continued
- Keep current on submittals
- Send for Review to RE, District (TEBM or DCE), CO
Construction (bcombs), Div of Construction
(Director and DO liaison), DSHE (Jim Rummage)
and if applicable the CO Review Committee (Bob
Lewis, David Kratt or Shari Greenwell). May need
to add userID to Contract Authority. - If over 250,000 or total change orders over 25
of Bid Price, change order should be sent to
Change Order Review Committee - If changed during Draft Review, make sure all
parties are sent new copy. Money for Review copy
needs to match submitted copy.
12SiteManager
- Change Order Review. reminder
- Be sure to include Beth Combs (bcombs) in your
list of reviewers. She gets funding from Program
Management and give hard copy to District Liaison
and Director. A most important person! She got
married two years ago and her last name in COMBS
13SiteManager Change order
- If in Pending but need to change, put back into
DRAFT, make corrections send for review before
putting back into PEND. RE should NOT deny in
PENDING STATUS.
14SiteManagerChange Orders continued
- Put in Pending only after reviews completed by
RE, District (TEBM or DCE), CO Construction
(bcombs), Div of Construction (Director or DO
liaison), DSHE (Jim Rummage) and if applicable
the CO Review Committee (Bob Lewis, David Kratt
or Shari Greenwell).
15SiteManagerChange Orders Pending approvals
- Approval Levels are
- Level 1 Contractor- (Project Engineer) this
indicates when change order mailed to Contractor - Level 2 Deputy State Highway Engineer (linman)
Once date inserted, indicates Change Order from
Contractor received in Central Office. - Level 3 Commissioner of Highways (jrummage)
Once date inserted, indicates approved by
Commissioner of Highways and passed to Div of
Accounts for uploading into system - Level 4 Final Approval e-Mars Change Order
(bcombs) Once date inserted, received from
Accounts and ready for use in SiteManager,
should be fully funded.
16SiteManagerChange Orders continued
- Put a standard reason code on items in change
order
17SiteManager DWR
- DWR abbreviated records available on internet
file can be used in excel to summarize quantities - http//transportation.ky.gov/construction/sm/dwr/
- Put location of work or Station Number of where
work performed - Be sure Items for Fuel Adjustments paid on DWR in
Month and Year work performed. Corrections need
to made on DWR in Month Year of work. - Put applicable comments on DWR. Issues resolved,
visitors, etc.
18SiteManager Diary
- For Work Day Projects need Diary entry for each
day from April 1 to November 30 and whether or
not a charge day. Be sure to add controlling
operation. - Put comments and issues resolved in Diary.
Needed to document project activities.
19SiteManager Payments
- Check balances in Doc-Viewer especially when near
end of project. - Be aware of projects with Mulitiple PO2 lines
20SiteManager Payments
From DOC-VIEWER Line Records. Open Amt is amount
remaining. Make sure your payments are under
this amount!!!
Current Estimategtgt Next Estimate do not exceed
64,836 for Total Line 1 or 1,634 for Total
Line 2
21Question?