Title: SiteManager Review


1
SiteManager Review Update
  • In service since May 1, 2005
  • 1692 projects active in system
  • 453 finals paid for 1,053,664.31
  • 761 Change Orders approved
  • 465 Conversion Estimates Processed
  • 9308 Progress Estimates for payments of
    1,406,522,955.23

2
SiteManager
  • Key Dates
  • Project Engineer / Project Manager
  • Federal or State?
  • Change Orders
  • DWR
  • Diary
  • Payments

3
SiteManager Key Dates
  • If making payment generally should have Begin
    Work Date entered!
  • If called complete by project engineer should
    have Work Complete date entered!
  • Put in Projected Work Complete date and update as
    needed!
  • You get the idea, if you complete inspection,
    send report, etc. put in the date!!! Also put in
    projected dates as needed.

4
SiteManager Key Dates
Remove KEY DATES not needed. If no Structures ie
HMA project, you can remove this date. It can be
re-added if bridge added to contract.
5
SiteManager NEW Key Date
KPDES NOI Notice of Intent date sent from
District Office KPDES Coverage Letter with Permit
Number date received back from KPDES with permit
Number, put Permit in Message KPDES NOT Notice
of Termination date sent to KPDES
6
SiteManagerChecklist Events Put them in system!
Need dates updated as events occur. Erosion, at
least once a week or rain event Contractor
Evaluation, 12/31 and/or at completion of
project Materials Cert date PR47 if applicable
at end of project
7
SiteManagerProject Engineer / Project Manager
  • Keep this updated. As Resident change, keep
    current in Sitemanager. It is helpful to know
    most current person responsible. District
    Construction Office Manager (DCOM can update this
    field).

8
SiteManager Federal Project ?
  • If Function is FD52 or FD51, then Federal funds.
    FD52 is FHWA, FD51 is FEMA. Also if Fed State
    Project Number begins with BRZ, BRO, IM, NH, ADP,
    IR it is Federal Funds

9
SiteManager Federal Project ? continued
  • If Function is FD52 or FD51, then Federal funds.
    FD52 is FHWA, FD51 is FEMA. Also if Fed State
    Project Number begins with BRZ, BRO, IM, NH, ADP,
    IR it is Federal Funds. Report cattext will show
    funding.

10
SiteManager Change Orders
  • To create a copy from SiteManager for review,
    create report, open file, save as HTM, open HTM
    file in browser and send that via e-mail. The
    HTM can be viewed from e-mail. No need to scan
    or paste into WORD, use the HTM file.

11
SiteManagerChange Orders continued
  • Keep current on submittals
  • Send for Review to RE, District (TEBM or DCE), CO
    Construction (bcombs), Div of Construction
    (Director and DO liaison), DSHE (Jim Rummage)
    and if applicable the CO Review Committee (Bob
    Lewis, David Kratt or Shari Greenwell). May need
    to add userID to Contract Authority.
  • If over 250,000 or total change orders over 25
    of Bid Price, change order should be sent to
    Change Order Review Committee
  • If changed during Draft Review, make sure all
    parties are sent new copy. Money for Review copy
    needs to match submitted copy.

12
SiteManager
  • Change Order Review. reminder
  • Be sure to include Beth Combs (bcombs) in your
    list of reviewers. She gets funding from Program
    Management and give hard copy to District Liaison
    and Director. A most important person! She got
    married two years ago and her last name in COMBS

13
SiteManager Change order
  • If in Pending but need to change, put back into
    DRAFT, make corrections send for review before
    putting back into PEND. RE should NOT deny in
    PENDING STATUS.

14
SiteManagerChange Orders continued
  • Put in Pending only after reviews completed by
    RE, District (TEBM or DCE), CO Construction
    (bcombs), Div of Construction (Director or DO
    liaison), DSHE (Jim Rummage) and if applicable
    the CO Review Committee (Bob Lewis, David Kratt
    or Shari Greenwell).

15
SiteManagerChange Orders Pending approvals
  • Approval Levels are
  • Level 1 Contractor- (Project Engineer) this
    indicates when change order mailed to Contractor
  • Level 2 Deputy State Highway Engineer (linman)
    Once date inserted, indicates Change Order from
    Contractor received in Central Office.
  • Level 3 Commissioner of Highways (jrummage)
    Once date inserted, indicates approved by
    Commissioner of Highways and passed to Div of
    Accounts for uploading into system
  • Level 4 Final Approval e-Mars Change Order
    (bcombs) Once date inserted, received from
    Accounts and ready for use in SiteManager,
    should be fully funded.

16
SiteManagerChange Orders continued
  • Put a standard reason code on items in change
    order

17
SiteManager DWR
  • DWR abbreviated records available on internet
    file can be used in excel to summarize quantities
  • http//transportation.ky.gov/construction/sm/dwr/
  • Put location of work or Station Number of where
    work performed
  • Be sure Items for Fuel Adjustments paid on DWR in
    Month and Year work performed. Corrections need
    to made on DWR in Month Year of work.
  • Put applicable comments on DWR. Issues resolved,
    visitors, etc.

18
SiteManager Diary
  • For Work Day Projects need Diary entry for each
    day from April 1 to November 30 and whether or
    not a charge day. Be sure to add controlling
    operation.
  • Put comments and issues resolved in Diary.
    Needed to document project activities.

19
SiteManager Payments
  • Check balances in Doc-Viewer especially when near
    end of project.
  • Be aware of projects with Mulitiple PO2 lines

20
SiteManager Payments
From DOC-VIEWER Line Records. Open Amt is amount
remaining. Make sure your payments are under
this amount!!!
Current Estimategtgt Next Estimate do not exceed
64,836 for Total Line 1 or 1,634 for Total
Line 2
21
Question?
22
Robert C. Lewis, PE Assistant State Highway
Engineer 200 Mero Street W6-17-02 Frankfort, KY
40622 E-mail Bob.lewis_at_ky.gov Cell
502-330-3470 Office 502-564-3730 ext 3084
Write a Comment
User Comments (0)
About PowerShow.com