Title: HKIS
1HKIS PQSL TALK DISRUPTION CLAIM RECORD
KEEPING
Presented by C Y Fung
2(No Transcript)
3(No Transcript)
4Disruption vs. Prolongation Due to Delay
5Prolongation Claims
63. Disruption Claims
7Definition of Disruption
- Disruption (as distinct from delay) is
disturbance, hindrance or interruption to a
Contractors normal working methods, resulting in
lower efficiency. If caused by the Employer, it
may give rise to a right to compensation either
under the contractor or as a breach of contract.
- SCL EOT Protocol
8DISRUPTION CLAIMS
- Disruption in its simplest sense is a loss of
productivity a reduction in the output of
construction resources, those being, primarily,
labour and plant. - A disruption claim is not a claim for
prolongation of the Works. - Disruption can also be caused by a delay but the
delay may or may not occur on the critical path.
9(No Transcript)
10Sample Project 1 - Original Working Programme
11Planned progress by trades
12Sample Project 1 As-Built Programme
13Actual progress by trades
14Comparison planned actual Actual progress by
trades
15CVIs by room affected
16Issues From Sample Project 1
- Late Possession late start and delay in
completion. - Piece-meal possession delay in completion and
loss of productivity. - Water leakage by MC Abortive works and impact
on progress delay. - Late verbal instructions Belated ordering of
variation works delay. - What records do we have to substantiate our
entitlements ?
17DISRUPTION CLAIMS
- How Engineering Services Ltd v Linder Ceilings,
Floors and Partitions plc (1999) 64 CLR 67 - Demonstrated that on parts of the works where a
similar activity was not subject to the
disruption claimed, the contractor achieved his
planned output, thereby demonstrating that, but
for the events notified, the additional cost of
performing the activity would not have arisen.
18Whittal Builders Company Ltd v Chester-Le-Street
District Council (1985) 11 CLR 40
DISRUPTION CLAIMS
- Evaluation of disruption was carried out on the
basis of a comparison of productivity prior to
the disruptive events taking place, compared with
that achieved during the period of disruption.
In this case the comparison of outputs was made
by assessment of sums certified within interim
payment certificates.
19DISRUPTION CLAIMS
- The greatest problem with disruption claims is
to prove that Employer caused the disruption,
and that it was not due to the Contractors own
inefficiencies or delays.
20Disruption Claims
21Sample Project 2 Disruption to Progress But No
Delay
1. Identify events causing the productivity loss
produce proof/records
2. Show productivity level at undisrupted period
22Measured Mile Approach
- The most appropriate way to establish disruption
is to apply a technique known as the Measured
Mile. This compares the productivity achieved
on un-impacted part of the contract with that
achieved on the impacted part. Such a comparison
factors out issues concerning unrealistic
programmes and inefficient working - Identical
to Duncan Wallaces approach
234. Record Keeping Strategy
24Brief the Team Members
- Detailed handover of risk schedule and tender
philosophy. - Clear concise commercial strategy.
- Commercial awareness meetings / workshops.
- Involve the complete team.
- Build relationships.
25Importance of working as an integrated team the
3 Cs
- Communication
- Regular meetings / Site Walks
- Levels of communication
- Coordination
- Responsibility for Commercial and Operations
- Consistency
- Knowledge and understanding of the basic Contract
requirements / Forms / Record sets will allow for
a consistent approach by the entire Project Team.
26Records / Forms
- Different record sets / forms that are both
required under the Contract and form the basis of
applications for payment, measurement and
valuation of variations and preparation of
claims. - Fulfill the Contract
- Manage Costs
- Achieve Maximum Value
27Records / Forms (contd)
28WORKING TOGETHER
Operations Team
Commercial Team
29 THE END