A Practical Solution for Turfway Road - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

A Practical Solution for Turfway Road

Description:

A Practical Solution for Turfway Road – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 20
Provided by: Burg154
Category:

less

Transcript and Presenter's Notes

Title: A Practical Solution for Turfway Road


1
A Practical Solution for Turfway Road
2
Project Summary
  • Turfway Road is a 1.9 mile improvement project
    through a heavily developed urban corridor. It
    widened a congested two-lane rural typical
    section to five-lanes in order to accommodate a
    2020 design year average daily traffic of 34,900.

3
Project Summary
  • The scope included improvements to the I-71 /
    I-75 interchange. A conventional solution called
    for replacing the 3-span interstate overpass
    bridge to make room for the widening of Turfway
    Road which occupied the center span of the bridge.

4
Project Summary
  • We proposed soil nail walls to excavate the
    abutment fill slopes under the flanking spans to
    make room for more traffic lanes. To verify the
    solution, we proposed using what was then called
    TRAF-NETSIM (now CORSIM).
  • Once we were selected, we had to make it work.

5
Project History
  • Selected in late 1996
  • Plans submitted (after several budgetary stops
    and starts) in the Summer of 2002
  • Construction began in the Summer of 2005, and was
    completed late in 2007.

6
Project Innovation
  • The proposed soil nail walls saved considerable
    time, money and headache.
  • Replacing the existing bridge to make room to
    widening Turfway Road would have cost about 10
    million.
  • Replacement of the bridge also would have imposed
    severe maintenance-of-traffic constrictions and
    inconvenience on the 150,000 vehicles per day
    traveling the interstate during construction.

7
Project Innovation
  • Verifying proposed traffic related solutions,
    (number of lanes, turning movement lane location
    and storage length, proposed geometrics and
    design speeds) fell to the use of a relatively
    new tool, CORSIM.
  • CORSIM is a traffic simulation program that
    simulates the flow of the design traffic volumes
    and directions through the proposed solutions.

8
Project Innovation
  • Like a pipe network program simulating the water
    flow, CORSIM simulates traffic flow through a
    roadway network.

9
Project Innovation
  • CORSIM allowed the team to propose only enough
    pavement to meet project needs, avoiding costs
    and disturbance to adjacent properties.

10
Project Implementation
  • Implementing the soil nail wall to accommodate
    the solutions verified through CORSIM meant

seeing if this
could be turned into this.
11
Project Implementation
  • Soil nail walls were proposed because they allow
    top-down excavation and construction of a
    soil-retaining structure.
  • This allowed opening the flanking spans of the
    bridge for the additional lanes while maintaining
    the embankment under live traffic above.

12
Project Implementation
  • Soil nail wall specification is an outcome-based
    process.
  • The drawings define the geometry (height, length,
    slope, etc.) and provide the soil properties.
  • The vendors employ that information to design the
    walls and submit drawings and calculations for
    review and approval.

13
Project Implementation
14
Project Implementation
  • However, use of the soil nail wall was not a
    panacea. A number of issues had to be addressed
  • Safety of traffic split around the existing
    piers.

15
Project Implementation
  • Feasibility lane configuration around the piers
    under the bridge was verified compliant with
    design speed and interchange capacity.

16
Project Implementation
  • Compatibility of typical section, including
    elevated walks, with the variation and geometry
    of abutment types was confirmed.

17
Project Summary
  • The Turfway Road widening has now been completed
    and has been well received by KYTC District 6,
    the City of Florence, KY and the traveling
    public.
  • The project was widened from 2-lanes to as many
    as 7-lanes without the need to take a single
    building along this heavily developed corridor.

18
Project Summary
  • From preconstruction to the final plan
    implementation only eight parking places were
    lost to the commercial developments along the
    project, and a large park and ride facility was
    created in the process.
  • We think this project demonstrates the successful
    use of new technologies, in both design and
    construction that can lead to practical and cost
    effective solutions of our transportation
    problems.

19
  • Please hold questions
  • until end of
  • both presentations.
Write a Comment
User Comments (0)
About PowerShow.com