PDO NORM Storage Facilities - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

PDO NORM Storage Facilities

Description:

The NORM storage areas must be protected with proper fencing and security so ... material prior to being placed in the storage were cemented and solidified, ... – PowerPoint PPT presentation

Number of Views:395
Avg rating:3.0/5.0
Slides: 27
Provided by: mu506
Category:

less

Transcript and Presenter's Notes

Title: PDO NORM Storage Facilities


1
PDO NORM Storage Facilities
  • Ahmed Al-Sabahi
  • Corporate Environmental Advisor

2
PDO NORM Storage Facilities
  • PDO Has two Storage facilities
  • Zualayah Storage area
  • Bahja Storage Facility

3
Storage of Radioactive Materials SP-1170
  • All NORM contaminated items or materials must be
    taken to the PDO designated storage site in
    Zauliyah as soon as reasonably practicable. The
    NORM storage area must comply with the following
  • The NORM storage areas must be protected with
    proper fencing and security so that uncontrolled
    entry is not possible.
  • There must be proper signage (pictorial and
    written in English and Arabic) around the fence
    so that the hazards are understood by everybody.
  • A contour of dose rates for the site shall be
    available through the supervisor.
  • People who are given access to the site are
    briefed on the location of hazards.
  • The key for access to the site must only be
    issued to authorised personnel and must be signed
    out and back into the custodians control.
  • The dose rate outside at the fence of the storage
    facility shall not exceed 2.5 1 ?Sv/hr.

4
Zauliyah Storage Facility
  • In 1994 a pig sample from Hasirah Zauliyah line
    was found to have radioactive reading above
    background level
  • comprehensive survey for Naturally occurring
    radioactive material (NORM) was conducted in
    Zauliyah station
  • high contamination reading were observed and
    materials.
  • This discovery lead to have a NORM storage area
    in Zauliyah.

5
What we are storing in Zualiyah
  • Tubulars
  • Contaminated Sludge ( in Drums).
  • X-Mass trees
  • Cables
  • Scrap metals
  • The NORM radioactive material prior to being
    placed in the storage were cemented and
    solidified, in thick numbered steel drums and
    transferred to an enclosed, top open wall
    (10L15W1.5H)

6
(No Transcript)
7
(No Transcript)
8
(No Transcript)
9
Some of the drums in the Storage
10
(No Transcript)
11
Contaminated tubular from Zauliyah 5
12
Present NORM Storage Facility
  • AD Hoc facility set up in Zauliya
  • Does not meet required standards or
    specifications
  • Licensed but threat of license revocation exists
    due to standards breaches.
  • Increasing quantities have increased dose rate to
    dangerous levels
  • RAC (Radiation Advisory Committee Approved
    Setting up permanent facility

13
NORM DESIGNATED AREA-PDO
NORM CONTAMINATION 0 c/s Dose rate
lt0.10mSv/h RADON in Gas 61 Bq/m3
NORM CONTAMINATION 10 c/s Dose Rate
0.11-0.29mSv/h RADON in Gas 66Bq/m3
MAF
LEKHWAIR
NORM CONTAMINATION 400 c/s Dose Rate
lt0.33-0.47mSv/h LKH-128L660 Bq/g LPS-T-2612260Bq
/g
Mazoon
DHULAIMA
NORM CONTAMINATION 60 c/s Dose Rate
0.22-0.27mSv/h RADON in Gas 435Bq/m3
NORM CONTAMINATION 20 c/s DOSE RATE
0.12-0.25mSv/h RADON IN GAS - 66
NATIH
FAHUD
YIBAL
NORM CONTAMINATION 0 c/s Dose Rate
lt0.12mSv/h RADON in Gas 407Bq/m3
NORM CONTAMINATION 0 c/s DOSE RATE lt0.12
mSv/h RADON IN GAS - 86Bq/M3
AL HUWAISAH
MUSALLIM
SAIH NUHAYDA
TAWF DAHM
NORM CONTAMINATION 60 c/s Dose Rate
0.25-0.50mSv/h RADON in Gas 107Bq/m3
G.NORTH
SAIH RAWL
NORM CONTAMINATION 18c/s DOSE RATE
0.19-0.25mSv/h RADON IN GAS 317 Bq/M3
QALN-ALARM
MABROUK

AL-GHUBARA
BARIK
NORM CONTAMINATION 2500 c/s DOSE RATE
1.99-2.40mSv/h RADON IN GAS -44Bq/M3 ZL-5 592
Bq/g
NORM CONTAMINATION 0 c/s DOSE RATE
lt0.12mSv/h RADON IN GAS 260Bq/m3
ZAULIYAH
ANZAUZ
HASIRAH
NORM CONTAMINATION 0 c/s DOSE RATE
lt0.12mSv/h RADON IN GAS 47Bq/m3
NORM CONTAMINATION 20 c/s DOSE RATE
0.15-0.20mSv/h
WAFRA
WAFRA-10 1110Bq/g
SUWAIHAT
HASIRAH- ZAULIYAH LINE-CONTAMINATED LINE 60 c/s
NORM CONTAMINATION 20 c/s DOSE RATE
0.12-0.15mSv/h RADON IN GAS 43Bq/m3
SAYYALA
BAHJA
NORM CONTAMINATION \ 15 c/s DOSE RATE
0.12mSv/h RADON IN GAS 46Bq/m3
MUKHAIZNA
NORM CONTAMINATION 60 c/s DOSE RATE
0.15-0.18mSv/h
SADAD
NORM CONTAMINATION 30 c/s Dose Rate
lt0.18-0.24mSv/h RADON in Gas 53 Bq/m3
NIMR
NORM CONTAMINATION 0 c/s DOSE RATE lt0.12
mSv/h RADON in Gas 430Bq/m3
SIMSIM
NORM CONTAMINATION 20 c/s Dose Rate
0.12-0.25mSv/h RADON in Gas - N/D
AMIN
AMAL
MARMUL
AL BURJ
RAHAB
QAHARIR
THULEILAT
LE
G
E
N
D
NORM AREA
Specifications. NORM contamination- reading 3
times the back-ground on the contamination meter
is a NORM trace or NORM suspect area.- NORM
area - Area confirmed to have materials with
quantitative radioactive level of more than 100
Bq/g Dose rate-Accepted limit is below 2.5mSv/h
PPE should be used when dose rate is above
7.5mSv/h. Contamination reading are back-ground
subtracted Note-NORM traces area,procedures must
be followed c/s-counts/seconds Bq/g -Becquerel/
grams Bq/m3-Becquel/ cubic meter Sv/h -
Sievart/hour
NORM AREA
NORM TRACES
NORM TRACES
Oil
pi
pel
in
e
Gas
pi
pe
lin
e
LAST UP DATED ON 24/02/99 - Compiled and
prepared by RASHID AL-ZAKWANI-TKL2B
Interior-Radiation-Focal-point
14
Issues Due to Lack of NORM Storage
  • Many Tanks cleaning delayed
  • Mounting Inventory of NORM materials
  • Non compliance to HSE-MS or ISO-14001
  • Potentially serious HSE risks

15
Present NORM Inventory
  • Expected drums 7000-8000
  • Down hole equipments 40 50 pieces (about 4
    meters length)
  • Tubings (3/4) 20000 pieces.
  • Pipes 50 pieces (different sizes and lengths).
  • X- Mass trees 10 pieces.
  • Cables ( down hole work) 3000m
  • Suspected NORM Sludge 1500m³

16
NORM Strategy
  • Storage Facilities in Bahja as per SP-1170
  • MRME constructing NORM disposal facility in 2
    years
  • Operation of facility to be managed by Waste
    Management Contractor

17
Storage Facility Details
  • Total Area 400m x 400m
  • All the area should be lined
  • Temporary storage for the incoming sludge
  • Toilets
  • Equipment PPE Store
  • Drummed sludge only - (50 m x 25 m x 0.4 m area)
  • Contaminated equipment (tubulars, esps) - (50 m
    x 25 m area)
  • Scrap material/metals (50 m x 25 m area)
  • Dedicated concrete pits for storage of
    liquid/bulk sludge from tanks (100m100m1m)

18
NORM facility
400 m
Entrance
Concrete pad 100 m x 50 m
Rest Room Toilet
400 m
gate
2 Pits Sludge Storage 100m10m1m depth
Source Pit
Tublars 50m x 25m
Drum storage 50m x 25m
Scrap metal 50m x 25m
Note- Not decided yet due to change in design
basis. CSM32 to advise
19
Project Phases
  • Phase 1 project started in June was completed
    in August 2004 as per agreed plan.
  • Preparation of the site
  • Fencing of the site
  • Phase 2 under construction and target completion
    Dec.04.
  • Two HDPE lined pits being built
  • Tubular Area
  • Metal Area
  • Drum Yard
  • Source Pit
  • Toilets
  • Phase3 will be mid June 2005 and it will include
  • for additional 4 pits decontamination area
  • Initiate development of decontamination facility
  • Determine and agree on long term disposal options
    for NORM
  • Tender out the design for the decontamination
    facility

20
1st PIT
21
2nd PIT
22
TUBALAR AREA
23
METAL AREA
24
DRUMS YARD
25
SOURCE PIT
26
Rest Room
Write a Comment
User Comments (0)
About PowerShow.com