Intra Girder Assembly and Alignment Robert Ruland - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

Intra Girder Assembly and Alignment Robert Ruland

Description:

Internal LCLS Undulator Alignment and Motion Review. 2. Alignment Tolerances ... All quadrupoles need to be aligned to within 2 m to a common reference line. ... – PowerPoint PPT presentation

Number of Views:67
Avg rating:3.0/5.0
Slides: 11
Provided by: hel85
Category:

less

Transcript and Presenter's Notes

Title: Intra Girder Assembly and Alignment Robert Ruland


1
Intra Girder Assembly and Alignment Robert Ruland
  • Alignment Philosophy
  • Assembly and Alignment

2
Alignment Tolerances
  • Two primary alignment tolerances
  • All quadrupoles need to be aligned to within 2
    µm to a common reference line.
  • All undulator segments need to be aligned to this
    reference line within 80 µm vertical and 140 µm
    horizontal.
  • BPM and vacuum chamber need to be aligned to the
    reference line within
  • the following tolerances
  • BPM horizontal 200 microns
  • BPM vertical 200 microns
  • Vacuum Chamber horizontal 200 microns
  • Vacuum Chamber vertical 200 microns
  • Quadrupole alignment tolerance will be achieved
    using Beam-based-alignment (BBA).
  • For BBA to converge the quadrupoles need to be
    aligned using conventional alignment methods to
    100 µm uncorrelated and 200 µm correlated

3
Undulator to Quad AlignmentTolerance Budget
Individual contributions are added in quadrature
4
Alignment and Support Philosophy
  • Global alignment of undulator segments over
    entire length to 80 (60) µm is very tough,
    instead will use BBAligned quads as local
    alignment references for undulator segments
  • 60 µm tolerance is reduced from global (130 m
    length) to relative (girder), i.e. one undulator
    segment to its adjacent quadrupole
  • To avoid having to perform the critical relative
    alignment under tunnel conditions, all components
    are mounted onto a common girder. The common
    platform retains the relative alignment when
    moving the quadrupole in the BBA process
  • Alignment Sequence
  • Fiducialization of Components
  • Intra Girder Alignment
  • Conventional Installation Alignment
  • Beam-based-alignment (Quadrupole and loose end)

5
Girder Alignment Concept
  • All components will be available as complete
    sub-assemblies
  • Girder
  • Motion systems
  • Manually adjustable supports
  • Beam steering / detecting components undulator
    segment, quad, BPM, BFW
  • Vacuum components undulator vacuum chamber,
    misc. components
  • All components will have been fiducialized
  • Undulator segments, quadrupoles and BFW will have
    fiducials in each of the principle planes
  • RF-BPM is referenced by precision surfaces
  • Girder Coordinate System
  • Undulator segment in nominal position determines
    the girder axis
  • All 33 undulator segments will have identical
    axis offsets variation in location of magnetic
    centerline wrt mounting feet is taken out by
    individual shims during fiducialization
  • All other components are aligned to this axis

6
Girder Assembly Alignment
  • Carried out in two steps
  • Assembly in girder factory (Bldg 650?) No
    temperature control
  • Mechanical installation of components
  • Rough alignment sufficient for vacuum
    connections
  • Vacuum connections
  • Plumbing Wiring
  • Alignment in MMF ( 1º K temp. control)
  • Pre-alignment (Optical Tooling, Faro Arm)
  • Final alignment (CMM Zeiss or Faro)

7
Girder Assembly Alignment Sequence (1)
  • Girder Assembly in Bldg 650
  • Station 1 Prepare Girder
  • Mount cam wedges underneath girder
  • Station 2 Component Installation
  • roll-away slides
  • component supports
  • HLS WPM components
  • undulator vacuum chamber
  • rough-align vacuum chamber
  • Station 3 Vacuum
  • install, pre-align and connect quad with
    inserted chamber
  • same for BFW and BPM
  • same for misc. vacuum components
  • Station 4 Wiring / Plumbing

8
Girder Assembly Alignment Sequence (2)
  • Girder Alignment in MMF (temperature controlled)
  • Station 1 Optical Alignment Faro Arm
  • align vacuum chamber
  • install undulator
  • check undulator to vacuum chamber clearance
  • align undulator to X0
  • pre-align girder components wrt undulator
  • remove undulator
  • Station 2 CMM (Faro Arm or Zeiss)
  • install undulator
  • align all components wrt undulator
  • align undulator to Xi
  • remove undulator
  • If test measurements prove that the combination
    of optical alignment and Faro arm can provide the
    required final alignment accuracy, all girder
    alignment will be performed at Station 1. The
    Zeiss CMM is already fully loaded by
    fiducialization measurements.

9
In Situ Intra-girder Alignment Verification
  • We will be able to verify the relative component
    alignment in situ
  • Horizontal component alignment tolerance (125 µm)
    can be achieved with standard methods e.g.
    optical tooling, ecartometer (CERN developed wire
    offset meter)
  • Vertical component alignment tolerance (60 µm) is
    marginally within optical leveling range. To be
    safe, we are planning to build a portable HLS
    based on the existing ultrasound sensors

10
END of Presentation
Write a Comment
User Comments (0)
About PowerShow.com