Title: NordStream Presentation
1Nord Stream Current Status And Progress
Achieved So Far
Russian Economic and Financial Forum in
Switzerland Paul Corcoran, Financial Director,
Nord Stream AG Zurich, 17 March 2008
2A NEW NATURAL GAS SUPPLY ROUTE FOR EUROPE
- 1,220-kilometre-long offshore natural gas
pipeline across the Baltic Sea - Two parallel pipelines with a total capacity of
55 bcm per year - Connecting Western European natural gas network
with Russian gas reserves - From Germany, natural gas can be transported to
Denmark, the UK, the Netherlands, Belgium, France
and other countries
3SIGNIFICANT CONTRIBUTION TO SECURITY OF SUPPLY
Additional gas imports needed
712 bcm
Import gap? 230 bcm
175
530 bcm
55
75
59
Imports
EU domestic gas production
2015
2005
4THE NEW SHAREHOLDER STRUCTURE
- Advantages of the new structure
- Operational and technical expertise of Gasunie in
the construction and operation of pipelines - Strengthening of wider European character of Nord
Stream
51 51
24,5 20
- 9
24,5 20
Current
Future
4
5COMPLIANCE WITH INTERNATIONAL LEGAL FRAME
- United Nations Convention on the Law of the Sea
(freedom of the high seas includes freedom to lay
submarine cables and pipelines) - Espoo Convention (international consultation
process), Council Directive 97/11/EC of 3/3 1997 - European Directive on Environmental Impact
Assessment - Cooperation with the Helsinki Commission HELCOM
6STATUS OF INTERNATIONAL CONSULTION PROCESS
INVOLVING ALL BALTIC SEA STATES
- Consultation process started in April 2006
-
- Formal inter-governmental Notification in
November 2006 - Regular meetings within the Espoo framework
- Updated status documentation delivered in October
2007 - Distribution of draft transboundary EIA report to
involved country authorities in December 2007 - Final transboundary EIA report currently being
finalised
7NATIONAL APPROVAL PROCESSES
- Nord Stream is subject to national legislation in
each of the countries through which it passes
Finland, Sweden, Denmark and Germany (Parties of
origin) and Russia - Example of Sweden
- Submission of application documents to Swedish
government on 21 December 2007 - First official response of Swedish government on
12 February 2008 requesting additional
information - Submission of applications in Russia, Denmark,
Germany and Finland to follow
8PIPELINE DESIGN
- Two pipelines, almost in parallel, with an inner
diameter of 1,153 mm, and a design pressure of
up to 220 bar - Steel wall thickness in the range of 26.8 mm to
41.0 mm - Concrete coating with a thickness ranging between
60 mm and 110 mm to give added weight sufficient
to stabilize the pipeline on the seabed - Midway service platform to facilitate pipeline
maintenance and inspection by intelligent
pigging
9ECONOMIC IMPACT FOR EUROPEAN SUBCONTRACTORS
- A great volume of business generated for various
supplier companies all over Europe - All contractors selected on the basis of
competitive tenders - Subcontractors for environmental studies and
technical design - Environmental Impact Assessment (EIA) prepared by
Rambøll, Denmark - Environmental studies carried out by Marin
Mättinek (MMT), Sweden, and Institut für
Angewandte Ökologie (IfAÖ), Germany - Technical engineering conducted by Snamprogetti,
Italy
9
10MAJOR SUPPLY CONTRACTS CONCLUDED
- Conclusion of supply contracts and Letters of
Intent important steps towards efficient and
timely project implementation - Supply agreements are concluded for the first
pipeline one million tons of steel pipes are
ordered - Europipe (Germany) to supply 75 order value
1.2 bn EUR - OMK (Russia) to supply 25 order value 0.4 bn
EUR - Further tender will be issued for 2nd pipeline
- Letter of intent has been signed with SAIPEM
(Italy) for pipe-laying contract - Letter of Intent for logistics (concrete coating,
pipe storage, transport) due to be signed with
EUPEC in March - Locations Mukran (D), Kotka, Hanko (FIN), Slite
and Karlshamn (SW) - Order value ca. 650 mio EUR
10
11STRUCTURE OF FINANCING
- Financing structure
- 30 per cent of project costs by equity
contributions from shareholders - 70 per cent financed externally through limited
recourse finance (lenders to be determined in the
near future) - Financial advisors chosen
- Société Générale
- ABN Amro
- Dresdner Kleinwort
- Currently, framework of bank participation is
being prepared - Support of export credit agencies also an option
11
12TIMEFRAME MEETS EUS NEEDS FOR GAS
- Key issues in 2008
- Detailed technical planning for construction work
- Completion of Environmental Impact Assessment
- Finalization of contracts for key investments
(pipes, logistics, pipe lay) - Determination of external project financing
- Ongoing dialogue with authorities in the Baltic
Sea region
Commiss-ioning Line 1
Commiss-ioning Line 2
Feasibility Study
Conceptual Design
Detailed Design
Laying Line 1
Laying Line 2
EIA Approvals
12
13Contacts
- Nord Stream AG
- Grafenauweg 2
- 6304 Zug / Switzerland
- Phone 41 (0) 41 766 91 91
- www.nord-stream.com
- Paul Corcoran
- Financial Director
- paul.corcoran_at_nord-stream.com
13