Title: Initial Results Eight Distribution Planning Opportunities
1Initial ResultsEight Distribution Planning
Opportunities
- Discussion Document
- Distribution Planning Working Group
- Massachusetts Distributed Generation
Collaborative - October 19, 2005
2Agenda
- Introduction
- Preliminary Conclusions
- Status Quo/Customer Ownership
- Active Case/Utility Ownership
- Active Case/Customer Ownership
- Next Steps
3Agenda
- Introduction
- Preliminary Conclusions
- Status Quo/Customer Ownership
- Active Case/Utility Ownership
- Active Case/Customer Ownership
- Next Steps
4The major purpose of the analysis of the eight
opportunities is to test the DG/Distribution
Planning hypothesis.
Introduction
- Hypothesis DG contributes value to
distribution planning and meets customer needs - There are three conditions that must be met for
the hypothesis to be correct - There must be enough DG capacity to meet the
distribution system shortfall (forecasted load
2005 distribution system capacity). - The DG reliability must meet distribution
planning needs - The economics for DG customers/owners and
utilities must be favorable.
5Our analysis will consider a status quo and
active scenarios for each of the eight DG and
distribution planning opportunities.
Introduction
Status Quo
Active
DG grows without tight integration with
distribution planning
DG is tightly integrated with distribution and is
relied upon to meet demand
Customer Ownership
Utility Ownership
Customer Ownership
Distribution Deferral Value Included Customer
Case - Similar to passive analysis but will also
include distribution deferral payment and
customer recruitment.
Distribution Deferral Value Included Utility
ownership and control of DG
- Status Quo Analysis Include only DG values that
can be captured today - Assumptions
- DG penetrates the customer base on the eight
distribution planning opportunity areas based on
the savings that DG will provide customers. - Current customer incentives are included in
economic analysis. - DG penetration is based on customer payback.
- No new incentives (e.g. value of distribution
deferral).
- Other values included
- Customer case add additional values and
associated costs
- Other values included
- Utility case add additional values and
associated costs
6Agenda
- Introduction
- Preliminary Conclusions
- Status Quo/Customer Ownership
- Active Case/Utility Ownership
- Active Case/Customer Ownership
- Next Steps
7Without an active program DG is not likely to
meet the capacity shortfalls.
Preliminary Conclusions Capacity
? DG alone meets capacity requirements ? DG is
part of a portfolio that meets capacity
requirements ? DG does not meet capacity
requirements
8DG could provide adequate reliability in some
cases.
Preliminary Conclusions Capacity
- Status Quo/Customer Ownership DG doesnt meet
the reliability requirements in most cases since
it will not provide enough capacity. - Active/Customer Ownership Under certain
circumstances, DG could meet the reliability
requirements if there is enough diversity of
resources and other resources (energy efficiency
and demand response) are used to firm DG
capacity. - Active/Utility Ownership The analysis assumed
that the utilities would add enough DG capacity
to meet their needs for reliability.
9In some cases DG provide positive NPVs for
utilities.
Preliminary Conclusions Economics
Customer Ownership
Active Utility Ownership
Active Utility DG Ownership
Status Quo and Active Utility DG Ownership
- Customer Perspective An underlying assumption
for the analysis is that a customer will not
install DG unless it meets their requirements for
savings. - Utility Perspective The impact on utility
economics has not been evaluated.
Results have not been optimized, NPVs may improve
10Agenda
- Introduction
- Preliminary Conclusions
- Status Quo/Customer Ownership
- Active Case/Utility Ownership
- Active Case/Customer Ownership
- Next Steps
11Preliminary Conclusions
Status Quo/Customer Ownership Preliminary
Conclusions
- In most cases, DG alone is not enough to meet the
capacity shortfalls. Energy efficiency combined
with DG can meet shortfalls in some cases
however, the deferral period is short. - Small recip engines are the most attractive
technologies PV can beat recip engines in some
cases. - Characteristics of a good opportunity for DG in
distribution planning - System near capacity, but need is still several
years out - Large customers with thermal demand
- Slow growth
- Shortfall is small relative to the load
12Assumptions
Status Quo/Customer Ownership Assumptions
- Distributed Generation
- Customer maximum demand and annual energy use are
provided by the electric distribution companies - Electric and gas prices for Jan 1, 2005 to Dec
31, 2005 (For some utilities the Nov Dec cost
of gas and electric generation are estimated) - DG performance parameters, installation and
operating costs as provided in the NREL report,
Gas-Fired Distributed Energy Resource Technology
Characterizations, October 2003 - Cumulative market penetration determined from the
curve -- Average of Kastovich and ADL - Linear market adoption, with 100 occurring in
year 10 - Energy Efficiency
- The amount of energy efficiency that can be
achieved is 10 of all customers' maximum demand - The payback for all customers is 5 years
- Cumulative market penetration determined from the
curve -- Average of Kastovich and ADL - Linear market adoption, with 100 occurring in
year 5
13In the Norwell Opportunity, DG and Energy
Efficiency could provide a one-yr deferral.
Status Quo/Customer Ownership National Grid
14In the Lunenberg Opportunity, DG and Energy
Efficiency could provide a one-yr deferral.
Status Quo/Customer Ownership FGE
15For the Framingham Opportunity, DG alone may meet
the capacity shortfall.
Status Quo/Customer Ownership NStar
16In the WMECO opportunities, DG and Energy
Efficiency could provide one-yr deferrals.
Status Quo/Customer Ownership WMECO
17The DG opportunity may be understated, since the
analysis doesnt address growth and is limited to
the 2004 customer loads.
Status Quo/Customer Ownership Missing
Opportunities?
Targeted Customer Load as a Percentage of
Forecasted Load
18Agenda
- Introduction
- Preliminary Conclusions
- Status Quo/Customer Ownership
- Active Case/Utility Ownership
- Active Case/Customer Ownership
- Next Steps
19Preliminary Conclusions
Active/Utility Ownership Preliminary
Conclusions
- In most cases, DG was not an economic solution
- Despite the higher capital costs, several smaller
units are more attractive than one large unit in
meeting reliability requirements. - The characteristics of the best opportunities
- Shortfall is small relative to the forecasted
load - High cost distribution solution relative to the
need - Deferral value per kW is much higher in the
earlier years - The amount of DG needed to meet the reliability
threshold is significantly higher than the
shortfall. - The number of hours that DG needs to run is short
(most cases capacity factor 1-3) - The results of this analysis have not been
optimized. - For example, improving diversity by using smaller
units could improve NPV, since fewer MWs are
required to meet the reliability limits.
20Assumptions
Active/Utility Ownership Assumptions
- Utility Model
- Utilities are allowed to own small, distributed
generation - DG can be moved when it no longer can meet
reliability criteria (i.e., TD Solution is
implemented) - Last year of NPV analysis is 2015 (to coincide
with prior utility economic case studies) Note
that shorter (or longer) timeframes could alter
results - Discount rate based on utility weighted cost of
capital - Have assumed sufficient DG must be installed to
meet a peak load reliability threshold of 0.999 - We assume the existing system is 100 reliable in
setting the 0.999 threshold - DG only operates when loads exceed equipment
ratings - Most utility ownership cases include installation
of diesels w/o emission control systems (Range
400 - 600/kW) - DG units operate independently a forced outage
of one unit does not influence the likelihood of
an outage of other units - The utility can receive capacity and energy
benefits for DG based on market rates - Used the same load profile (LDC) and load factor
for all cases - Revenue requirements model used to calculate NPV
- DG costs include cost of capital (rate base),
working capital, depreciation, property taxes,
state and federal taxes, fuel and OM - DG asset life and depreciation schedule set at
approximately 35 years depreciation is
straight-line - Property taxes assumed to be 2 for all cases
- 2) Customer and Deferral Savings Model
21The deferral savings are calculated using a
revenue requirements approach.
Active/Utility Ownership Assumptions
WMECO Substation Opportunity
22Explain how cost module works
Active/Utility Ownership Assumptions
WMECO Substation Opportunity
23In the Norwell opportunity, 6 MW of DG would be
added over a 7-yr period to meet the capacity
shortfall and reliability requirements.
Active/Utility Ownership National Grid Norwell
24The Norwell Opportunity would have a negative
NPV.
Active/Utility Ownership National Grid Norwell
25In the Worcester opportunity, 12 MW of DG would
be added over a 10-year period to meet the
shortfall and reliability requirements.
Active/Utility Ownership National Grid
Worcester
26The Worcester Opportunity would have a negative
NPV.
Active/Utility Ownership National Grid
Worcester
27In the Lunenberg Opportunity, 6 MW of DG would be
added to meet the capacity shortfall and
reliability requirements.
Active/Utility Ownership FGE Lunenberg
28The Lunenberg Opportunity would have a negative
NPV.
Active/Utility Ownership FGE Lunenberg
29In the Leominster Opportunity, 225 kW of DG would
be added to meet the capacity shortfall and
reliability requirements.
Active/Utility Ownership FGE Leominster
30The Leominster Opportunity would have a positive
NPV.
Active/Utility Ownership FGE Leominster
31In the Woburn Opportunity, 500 kW of DG would be
added to meet the capacity shortfall and
reliability requirements.
Active/Utility Ownership NSTAR Woburn
32The Woburn Opportunity would have a negative NPV.
Active/Utility Ownership NSTAR Woburn
33In the Framingham Opportunity, 4.5 MW of DG would
be added to meet the capacity shortfall and
reliability requirements.
Active/Utility Ownership NSTAR Framingham
34The Framingham Opportunity would have a negative
NPV.
Active/Utility Ownership NSTAR Framingham
35In the WMECO Substation Opportunity, 4 MW of DG
would be added to meet the capacity shortfall and
reliability requirements.
Active/Utility Ownership WMECO Substation
36The WMECO Substation Opportunity would have a
positive NPV.
Active/Utility Ownership WMECO Substation
37In the WMECO Circuit Opportunity, 5 MW of DG
would be added to meet the capacity shortfall and
reliability requirements.
Active/Utility Ownership WMECO Circuit
38The WMECO Circuit Opportunity would have a
negative NPV.
Active/Utility Ownership WMECO Circuit
39Alternatively, by adding fewer DG units, the
WMECO Circuit Opportunity would have a shorter
deferral period.
Active/Utility Ownership WMECO Circuit
40Active/Utility Ownership WMECO Circuit
A shorter deferral period would provide a
positive NPV.
41The reliability module calculates the peak load
availability for each year.
Active/Utility Ownership Reliability
42For the WMECO Substation case enough DG is added
to provide gt99.9 peak load availability.
Active/Utility Ownership Reliability
Set at gt99.9
43Agenda
- Introduction
- Preliminary Conclusions
- Status Quo/Customer Ownership
- Active Case/Utility Ownership
- Active Case/Customer Ownership
- Next Steps
44Preliminary Conclusions
Active/Customer Ownership Preliminary
Conclusions
- Including incentives makes DG, EE and DR more
attractive (e.g. extends deferral 1-3 years). - An Active/Customer Ownership program is not
likely to provide 10-yr deferrals in most cases. - A program could be developed for a 1-3 year
deferral. - Small recip engines are the most attractive
technologies PV can beat recip engines in some
cases. - Characteristics of a good opportunity for DG in
distribution planning - System near capacity, but need is still several
years out - Large customers with thermal demand
- Slow growth
- Shortfall is small relative to the load
45Assumptions
Active/Customer Ownership Assumptions
- Active Distributed Generation
- Same conditions as in Status Quo case, except
there is now a one-time incentive payment in year
1 corresponding to - Annual deferral savings were determined from the
utility DG module - The NPV of the savings from 2006 to 2015 was
determined for each opportunity - This was then divided by the capacity shortfall
in 2015 to determine the value of the one-time
incentive payment, /kW - Cumulative market penetration determined from the
curve -- Average of Kastovich and ADL market
penetration curves - Linear market adoption, with 100 occurring in
year 5
46Assumptions (continued)
Active/Customer Ownership Assumptions
- Active Energy Efficiency
- The amount of energy efficiency that can be
achieved is 10 of all customers' maximum demand - The payback for customers is adjusted based on
the incentive, assumes EE measures to achieve 10
reduction cost 3,000 per kW - Cumulative market penetration determined from the
curve -- Average of Kastovich and ADL market
penetration curves - Linear market adoption, with 100 occurring in
year 2 - Active Demand Response
- Customer reduction must be at least 50 kW (same
as Brockton Pilot) - The achievable demand response is 5 of a
customer's maximum demand - Same payback as energy efficiency case
- Cumulative market penetration determined from the
curve -- Average of Kastovich and ADL market
penetration curves - Linear market adoption, with 100 occurring in
year 2
47With incentives for DG, DR and EE, the Norwell
Opportunity could have a 2-yr deferral.
Active/Customer Ownership National Grid
48With incentives for DG, DR and EE, the Lunenberg
Opportunity could have a 2-yr deferral.
Active/Customer Ownership FGE
49With incentives for DG, the Framingham
Opportunity could have a 10-yr deferral.
Active/Customer Ownership NStar
50With incentives for DG, DR and EE, the WMECO
Opportunities could have 1-3 year deferrals.
Active/Customer Ownership WMECO
51Reliability
52Agenda
- Introduction
- Preliminary Conclusions
- Status Quo/Customer Ownership
- Active Case/Utility Ownership
- Active Case/Customer Ownership
- Next Steps