Initial Results Eight Distribution Planning Opportunities

1 / 52
About This Presentation
Title:

Initial Results Eight Distribution Planning Opportunities

Description:

Active/Utility Ownership National Grid Worcester. In the Worcester opportunity, 12 MW of DG would be ... The Worcester Opportunity would have a negative NPV. ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 53
Provided by: nci379

less

Transcript and Presenter's Notes

Title: Initial Results Eight Distribution Planning Opportunities


1
Initial ResultsEight Distribution Planning
Opportunities
  • Discussion Document
  • Distribution Planning Working Group
  • Massachusetts Distributed Generation
    Collaborative
  • October 19, 2005

2
Agenda
  • Introduction
  • Preliminary Conclusions
  • Status Quo/Customer Ownership
  • Active Case/Utility Ownership
  • Active Case/Customer Ownership
  • Next Steps

3
Agenda
  • Introduction
  • Preliminary Conclusions
  • Status Quo/Customer Ownership
  • Active Case/Utility Ownership
  • Active Case/Customer Ownership
  • Next Steps

4
The major purpose of the analysis of the eight
opportunities is to test the DG/Distribution
Planning hypothesis.
Introduction
  • Hypothesis DG contributes value to
    distribution planning and meets customer needs
  • There are three conditions that must be met for
    the hypothesis to be correct
  • There must be enough DG capacity to meet the
    distribution system shortfall (forecasted load
    2005 distribution system capacity).
  • The DG reliability must meet distribution
    planning needs
  • The economics for DG customers/owners and
    utilities must be favorable.

5
Our analysis will consider a status quo and
active scenarios for each of the eight DG and
distribution planning opportunities.
Introduction
Status Quo
Active
DG grows without tight integration with
distribution planning
DG is tightly integrated with distribution and is
relied upon to meet demand
Customer Ownership
Utility Ownership
Customer Ownership
Distribution Deferral Value Included Customer
Case - Similar to passive analysis but will also
include distribution deferral payment and
customer recruitment.
Distribution Deferral Value Included Utility
ownership and control of DG
  • Status Quo Analysis Include only DG values that
    can be captured today
  • Assumptions
  • DG penetrates the customer base on the eight
    distribution planning opportunity areas based on
    the savings that DG will provide customers.
  • Current customer incentives are included in
    economic analysis.
  • DG penetration is based on customer payback.
  • No new incentives (e.g. value of distribution
    deferral).
  • Other values included
  • Customer case add additional values and
    associated costs
  • Other values included
  • Utility case add additional values and
    associated costs

6
Agenda
  • Introduction
  • Preliminary Conclusions
  • Status Quo/Customer Ownership
  • Active Case/Utility Ownership
  • Active Case/Customer Ownership
  • Next Steps

7
Without an active program DG is not likely to
meet the capacity shortfalls.
Preliminary Conclusions Capacity
? DG alone meets capacity requirements ? DG is
part of a portfolio that meets capacity
requirements ? DG does not meet capacity
requirements
8
DG could provide adequate reliability in some
cases.
Preliminary Conclusions Capacity
  • Status Quo/Customer Ownership DG doesnt meet
    the reliability requirements in most cases since
    it will not provide enough capacity.
  • Active/Customer Ownership Under certain
    circumstances, DG could meet the reliability
    requirements if there is enough diversity of
    resources and other resources (energy efficiency
    and demand response) are used to firm DG
    capacity.
  • Active/Utility Ownership The analysis assumed
    that the utilities would add enough DG capacity
    to meet their needs for reliability.

9
In some cases DG provide positive NPVs for
utilities.
Preliminary Conclusions Economics
Customer Ownership
Active Utility Ownership
Active Utility DG Ownership
Status Quo and Active Utility DG Ownership
  • Customer Perspective An underlying assumption
    for the analysis is that a customer will not
    install DG unless it meets their requirements for
    savings.
  • Utility Perspective The impact on utility
    economics has not been evaluated.

Results have not been optimized, NPVs may improve
10
Agenda
  • Introduction
  • Preliminary Conclusions
  • Status Quo/Customer Ownership
  • Active Case/Utility Ownership
  • Active Case/Customer Ownership
  • Next Steps

11
Preliminary Conclusions
Status Quo/Customer Ownership Preliminary
Conclusions
  • In most cases, DG alone is not enough to meet the
    capacity shortfalls. Energy efficiency combined
    with DG can meet shortfalls in some cases
    however, the deferral period is short.
  • Small recip engines are the most attractive
    technologies PV can beat recip engines in some
    cases.
  • Characteristics of a good opportunity for DG in
    distribution planning
  • System near capacity, but need is still several
    years out
  • Large customers with thermal demand
  • Slow growth
  • Shortfall is small relative to the load

12
Assumptions
Status Quo/Customer Ownership Assumptions
  • Distributed Generation
  • Customer maximum demand and annual energy use are
    provided by the electric distribution companies
  • Electric and gas prices for Jan 1, 2005 to Dec
    31, 2005 (For some utilities the Nov Dec cost
    of gas and electric generation are estimated)
  • DG performance parameters, installation and
    operating costs as provided in the NREL report,
    Gas-Fired Distributed Energy Resource Technology
    Characterizations, October 2003
  • Cumulative market penetration determined from the
    curve -- Average of Kastovich and ADL
  • Linear market adoption, with 100 occurring in
    year 10
  • Energy Efficiency
  • The amount of energy efficiency that can be
    achieved is 10 of all customers' maximum demand
  • The payback for all customers is 5 years
  • Cumulative market penetration determined from the
    curve -- Average of Kastovich and ADL
  • Linear market adoption, with 100 occurring in
    year 5

13
In the Norwell Opportunity, DG and Energy
Efficiency could provide a one-yr deferral.
Status Quo/Customer Ownership National Grid
14
In the Lunenberg Opportunity, DG and Energy
Efficiency could provide a one-yr deferral.
Status Quo/Customer Ownership FGE
15
For the Framingham Opportunity, DG alone may meet
the capacity shortfall.
Status Quo/Customer Ownership NStar
16
In the WMECO opportunities, DG and Energy
Efficiency could provide one-yr deferrals.
Status Quo/Customer Ownership WMECO
17
The DG opportunity may be understated, since the
analysis doesnt address growth and is limited to
the 2004 customer loads.
Status Quo/Customer Ownership Missing
Opportunities?
Targeted Customer Load as a Percentage of
Forecasted Load
18
Agenda
  • Introduction
  • Preliminary Conclusions
  • Status Quo/Customer Ownership
  • Active Case/Utility Ownership
  • Active Case/Customer Ownership
  • Next Steps

19
Preliminary Conclusions
Active/Utility Ownership Preliminary
Conclusions
  • In most cases, DG was not an economic solution
  • Despite the higher capital costs, several smaller
    units are more attractive than one large unit in
    meeting reliability requirements.
  • The characteristics of the best opportunities
  • Shortfall is small relative to the forecasted
    load
  • High cost distribution solution relative to the
    need
  • Deferral value per kW is much higher in the
    earlier years
  • The amount of DG needed to meet the reliability
    threshold is significantly higher than the
    shortfall.
  • The number of hours that DG needs to run is short
    (most cases capacity factor 1-3)
  • The results of this analysis have not been
    optimized.
  • For example, improving diversity by using smaller
    units could improve NPV, since fewer MWs are
    required to meet the reliability limits.

20
Assumptions
Active/Utility Ownership Assumptions
  • Utility Model
  • Utilities are allowed to own small, distributed
    generation
  • DG can be moved when it no longer can meet
    reliability criteria (i.e., TD Solution is
    implemented)
  • Last year of NPV analysis is 2015 (to coincide
    with prior utility economic case studies) Note
    that shorter (or longer) timeframes could alter
    results
  • Discount rate based on utility weighted cost of
    capital
  • Have assumed sufficient DG must be installed to
    meet a peak load reliability threshold of 0.999
  • We assume the existing system is 100 reliable in
    setting the 0.999 threshold
  • DG only operates when loads exceed equipment
    ratings
  • Most utility ownership cases include installation
    of diesels w/o emission control systems (Range
    400 - 600/kW)
  • DG units operate independently a forced outage
    of one unit does not influence the likelihood of
    an outage of other units
  • The utility can receive capacity and energy
    benefits for DG based on market rates
  • Used the same load profile (LDC) and load factor
    for all cases
  • Revenue requirements model used to calculate NPV
  • DG costs include cost of capital (rate base),
    working capital, depreciation, property taxes,
    state and federal taxes, fuel and OM
  • DG asset life and depreciation schedule set at
    approximately 35 years depreciation is
    straight-line
  • Property taxes assumed to be 2 for all cases
  • 2) Customer and Deferral Savings Model

21
The deferral savings are calculated using a
revenue requirements approach.
Active/Utility Ownership Assumptions
WMECO Substation Opportunity
22
Explain how cost module works
Active/Utility Ownership Assumptions
WMECO Substation Opportunity
23
In the Norwell opportunity, 6 MW of DG would be
added over a 7-yr period to meet the capacity
shortfall and reliability requirements.
Active/Utility Ownership National Grid Norwell
24
The Norwell Opportunity would have a negative
NPV.
Active/Utility Ownership National Grid Norwell
25
In the Worcester opportunity, 12 MW of DG would
be added over a 10-year period to meet the
shortfall and reliability requirements.
Active/Utility Ownership National Grid
Worcester
26
The Worcester Opportunity would have a negative
NPV.
Active/Utility Ownership National Grid
Worcester
27
In the Lunenberg Opportunity, 6 MW of DG would be
added to meet the capacity shortfall and
reliability requirements.
Active/Utility Ownership FGE Lunenberg
28
The Lunenberg Opportunity would have a negative
NPV.
Active/Utility Ownership FGE Lunenberg
29
In the Leominster Opportunity, 225 kW of DG would
be added to meet the capacity shortfall and
reliability requirements.
Active/Utility Ownership FGE Leominster
30
The Leominster Opportunity would have a positive
NPV.
Active/Utility Ownership FGE Leominster
31
In the Woburn Opportunity, 500 kW of DG would be
added to meet the capacity shortfall and
reliability requirements.
Active/Utility Ownership NSTAR Woburn
32
The Woburn Opportunity would have a negative NPV.
Active/Utility Ownership NSTAR Woburn
33
In the Framingham Opportunity, 4.5 MW of DG would
be added to meet the capacity shortfall and
reliability requirements.
Active/Utility Ownership NSTAR Framingham
34
The Framingham Opportunity would have a negative
NPV.
Active/Utility Ownership NSTAR Framingham
35
In the WMECO Substation Opportunity, 4 MW of DG
would be added to meet the capacity shortfall and
reliability requirements.
Active/Utility Ownership WMECO Substation
36
The WMECO Substation Opportunity would have a
positive NPV.
Active/Utility Ownership WMECO Substation
37
In the WMECO Circuit Opportunity, 5 MW of DG
would be added to meet the capacity shortfall and
reliability requirements.
Active/Utility Ownership WMECO Circuit
38
The WMECO Circuit Opportunity would have a
negative NPV.
Active/Utility Ownership WMECO Circuit
39
Alternatively, by adding fewer DG units, the
WMECO Circuit Opportunity would have a shorter
deferral period.
Active/Utility Ownership WMECO Circuit
40
Active/Utility Ownership WMECO Circuit
A shorter deferral period would provide a
positive NPV.
41
The reliability module calculates the peak load
availability for each year.
Active/Utility Ownership Reliability
42
For the WMECO Substation case enough DG is added
to provide gt99.9 peak load availability.
Active/Utility Ownership Reliability
Set at gt99.9
43
Agenda
  • Introduction
  • Preliminary Conclusions
  • Status Quo/Customer Ownership
  • Active Case/Utility Ownership
  • Active Case/Customer Ownership
  • Next Steps

44
Preliminary Conclusions
Active/Customer Ownership Preliminary
Conclusions
  • Including incentives makes DG, EE and DR more
    attractive (e.g. extends deferral 1-3 years).
  • An Active/Customer Ownership program is not
    likely to provide 10-yr deferrals in most cases.
  • A program could be developed for a 1-3 year
    deferral.
  • Small recip engines are the most attractive
    technologies PV can beat recip engines in some
    cases.
  • Characteristics of a good opportunity for DG in
    distribution planning
  • System near capacity, but need is still several
    years out
  • Large customers with thermal demand
  • Slow growth
  • Shortfall is small relative to the load

45
Assumptions
Active/Customer Ownership Assumptions
  • Active Distributed Generation
  • Same conditions as in Status Quo case, except
    there is now a one-time incentive payment in year
    1 corresponding to
  • Annual deferral savings were determined from the
    utility DG module
  • The NPV of the savings from 2006 to 2015 was
    determined for each opportunity
  • This was then divided by the capacity shortfall
    in 2015 to determine the value of the one-time
    incentive payment, /kW
  • Cumulative market penetration determined from the
    curve -- Average of Kastovich and ADL market
    penetration curves
  • Linear market adoption, with 100 occurring in
    year 5

46
Assumptions (continued)
Active/Customer Ownership Assumptions
  • Active Energy Efficiency
  • The amount of energy efficiency that can be
    achieved is 10 of all customers' maximum demand
  • The payback for customers is adjusted based on
    the incentive, assumes EE measures to achieve 10
    reduction cost 3,000 per kW
  • Cumulative market penetration determined from the
    curve -- Average of Kastovich and ADL market
    penetration curves
  • Linear market adoption, with 100 occurring in
    year 2
  • Active Demand Response
  • Customer reduction must be at least 50 kW (same
    as Brockton Pilot)
  • The achievable demand response is 5 of a
    customer's maximum demand
  • Same payback as energy efficiency case
  • Cumulative market penetration determined from the
    curve -- Average of Kastovich and ADL market
    penetration curves
  • Linear market adoption, with 100 occurring in
    year 2

47
With incentives for DG, DR and EE, the Norwell
Opportunity could have a 2-yr deferral.
Active/Customer Ownership National Grid
48
With incentives for DG, DR and EE, the Lunenberg
Opportunity could have a 2-yr deferral.
Active/Customer Ownership FGE
49
With incentives for DG, the Framingham
Opportunity could have a 10-yr deferral.
Active/Customer Ownership NStar
50
With incentives for DG, DR and EE, the WMECO
Opportunities could have 1-3 year deferrals.
Active/Customer Ownership WMECO
51
Reliability
52
Agenda
  • Introduction
  • Preliminary Conclusions
  • Status Quo/Customer Ownership
  • Active Case/Utility Ownership
  • Active Case/Customer Ownership
  • Next Steps
Write a Comment
User Comments (0)