Title: TPC Meeting GSI Darmstadt, December 1011, 2001
1TPC Field Cage Review
J. Baechler, M. Hoch, T. C. Meyer, T.
Przybyla and TA2
- Project Schedule
- Field Cage Vessels
- End Plates
- Field defining system
- Pictures
2Project Phases
3FC Inner Containment Vessel
- Central Drum
- 5 mm C-fiber composite, Al coated
- Axial Al-strips outside as heating elements
- Cones
- 3 mm Al skins, soft joint
- Planning
- Tender sent out 2nd half of December 2001
- Finished by August 2002 (needed Oct. 2002)
4FC Inner Field Cage Vessel
- Construction
- All 3 circular segments finished.
- Flanges positioned and aligned.
- Gluing of segments today (10-12)
- Splicing (seam sealing), guard rings and vias
this week. - Delivery
- This vessel will be delivered in one piece
Mid-January 2002.
5FC Outer Field Cage Vessel
- Construction
- Segments (6) manufacture has started this
month, 1/week. - Flanges being finished at André/Grenoble.Quality
control by CERN (Central Workshop). - Delivery
- Flanges mid/end January 2002
- Composite segments February 2002
6FC Outer Containment Vessel
- Construction
- All (6) segments finished autoclaving.
- Aluminum coating ongoing.
- Flanges same process as OFV
- Delivery
- Same as for OFV (flanges and segments)(January/F
ebruary 2002)
7FC Manufacture
Cylinders are fabricated from segments glued
together (lashing).
8FC Segments Hand Lay-up
IFV segment on mold at Fischer ACC - Austria
9FC Segments Autoclaving
IFV segment introduced into autoclave (Fischer
ACC - Austria)
10Flanges OFV OCV
Forged and unforged rings for OFV OCV flanges
at André Constructions Mécaniques - Grenoble
-France
11FC Segments Transport
Crate will house the 12 segments of OFV OCV
12FC End Plates
- Construction Phase
- Electron beam welding finished (DCN Nantes)
checked and X-rayed very high quality work - We were last customer (!).
- Contracting for machining
- Old tender void! Lowest bidder (FCM-Spain) quoted
wrong currency (CHF-gt ) - New tender launched last month.
13FC End Plates (contd)
- Contracting
- New bids arrive December 2001 (now).
- Order to be placed January 2002.
- Tolerances relaxed where feasible.
- No ALODINE treatment (-40 kCHF).
- Schedule
- Welded plates to machine shop February 2002
- Delivery to CERN July 2002
- Definitely needed at CERN October 2002!
14End Plates E-Beam Welding
Sample electron beam weld for end plates at DCN
Nantes - France
15End Plates E-Beam Welding
10 m Ø vacuum tank for electron beam welding at
DCN Nantes - France
16FC Central Electrode
- Prototyping
- First foil of 3 parallel layers stretched on
aluminum frame. - Stretch-machine has been shipped to TA2.
- Presently 5-6 foils being glued together.
- Produce three foils for TPC.
- Central electrode available November 2002.
17Central Electrode Prototype
25 µm aluminized Mylar on aluminum frame of 10 cm
width, approximately 3 m Ø.
18Central Electrode Prototype
19FC Rods
- Four types
- Gas rods (50)
- 32 supply (10 l/min)
- 18 exhaust
- Laser rods (12)
- Resistor rods (44)
- HV rods (2)
- Makrolon chosen as rod material.
- Ongoing RD on HV resistor rod until spring
2002.
20FC Assembly Tooling
- DELPHI assembly frame ready.
- Clean house errected.
- Electrical circuits still to install (budget!)
- Additional tools (survey, alignment) in
preparation. - Construction of vessels with Fischer starts in
March 2002. - Finished July 2002 (critical path).
21Clean Room at SXL2
22FC Construction Resources
- Designers
- 2 FTE CERN 1 PT (hired)
- Technicians
- 2.5 FTE CERN 1.5 FTE (hired)
- 1.5 FTE Project Associates
- Mechanics
- 4 borrowed from Lars (t.b.c.)