Welded plates to machine shop February 2002. Delivery to CERN: ... End Plates: E-Beam Welding. Sample electron beam weld for end plates at DCN Nantes - France ... – PowerPoint PPT presentation

Number of Views:67
Avg rating:3.0/5.0
Slides: 23
Provided by: ITD101
Category:

less

Transcript and Presenter's Notes

Title: TPC Meeting GSI Darmstadt, December 1011, 2001


1
TPC Field Cage Review
J. Baechler, M. Hoch, T. C. Meyer, T.
Przybyla and TA2
  • Project Schedule
  • Field Cage Vessels
  • End Plates
  • Field defining system
  • Pictures

2
Project Phases
3
FC Inner Containment Vessel
  • Central Drum
  • 5 mm C-fiber composite, Al coated
  • Axial Al-strips outside as heating elements
  • Cones
  • 3 mm Al skins, soft joint
  • Planning
  • Tender sent out 2nd half of December 2001
  • Finished by August 2002 (needed Oct. 2002)

4
FC Inner Field Cage Vessel
  • Construction
  • All 3 circular segments finished.
  • Flanges positioned and aligned.
  • Gluing of segments today (10-12)
  • Splicing (seam sealing), guard rings and vias
    this week.
  • Delivery
  • This vessel will be delivered in one piece
    Mid-January 2002.

5
FC Outer Field Cage Vessel
  • Construction
  • Segments (6) manufacture has started this
    month, 1/week.
  • Flanges being finished at André/Grenoble.Quality
    control by CERN (Central Workshop).
  • Delivery
  • Flanges mid/end January 2002
  • Composite segments February 2002

6
FC Outer Containment Vessel
  • Construction
  • All (6) segments finished autoclaving.
  • Aluminum coating ongoing.
  • Flanges same process as OFV
  • Delivery
  • Same as for OFV (flanges and segments)(January/F
    ebruary 2002)

7
FC Manufacture
Cylinders are fabricated from segments glued
together (lashing).
8
FC Segments Hand Lay-up
IFV segment on mold at Fischer ACC - Austria
9
FC Segments Autoclaving
IFV segment introduced into autoclave (Fischer
ACC - Austria)
10
Flanges OFV OCV
Forged and unforged rings for OFV OCV flanges
at André Constructions Mécaniques - Grenoble
-France
11
FC Segments Transport
Crate will house the 12 segments of OFV OCV
12
FC End Plates
  • Construction Phase
  • Electron beam welding finished (DCN Nantes)
    checked and X-rayed very high quality work
  • We were last customer (!).
  • Contracting for machining
  • Old tender void! Lowest bidder (FCM-Spain) quoted
    wrong currency (CHF-gt )
  • New tender launched last month.

13
FC End Plates (contd)
  • Contracting
  • New bids arrive December 2001 (now).
  • Order to be placed January 2002.
  • Tolerances relaxed where feasible.
  • No ALODINE treatment (-40 kCHF).
  • Schedule
  • Welded plates to machine shop February 2002
  • Delivery to CERN July 2002
  • Definitely needed at CERN October 2002!

14
End Plates E-Beam Welding
Sample electron beam weld for end plates at DCN
Nantes - France
15
End Plates E-Beam Welding
10 m Ø vacuum tank for electron beam welding at
DCN Nantes - France
16
FC Central Electrode
  • Prototyping
  • First foil of 3 parallel layers stretched on
    aluminum frame.
  • Stretch-machine has been shipped to TA2.
  • Presently 5-6 foils being glued together.
  • Produce three foils for TPC.
  • Central electrode available November 2002.

17
Central Electrode Prototype
25 µm aluminized Mylar on aluminum frame of 10 cm
width, approximately 3 m Ø.
18
Central Electrode Prototype
19
FC Rods
  • Four types
  • Gas rods (50)
  • 32 supply (10 l/min)
  • 18 exhaust
  • Laser rods (12)
  • Resistor rods (44)
  • HV rods (2)
  • Makrolon chosen as rod material.
  • Ongoing RD on HV resistor rod until spring
    2002.

20
FC Assembly Tooling
  • DELPHI assembly frame ready.
  • Clean house errected.
  • Electrical circuits still to install (budget!)
  • Additional tools (survey, alignment) in
    preparation.
  • Construction of vessels with Fischer starts in
    March 2002.
  • Finished July 2002 (critical path).

21
Clean Room at SXL2
22
FC Construction Resources
  • Designers
  • 2 FTE CERN 1 PT (hired)
  • Technicians
  • 2.5 FTE CERN 1.5 FTE (hired)
  • 1.5 FTE Project Associates
  • Mechanics
  • 4 borrowed from Lars (t.b.c.)