Title: SHOUAIBA PHASE III
1SHOUAIBA PHASE III Shouaiba Independent power
and power project (IWPP) CEM 525 PROJECT
DELIVERY SYSTEMS MOHAMMED JALALUDDIN
2DETAILS OF WEC IWPPs LOCATIONS
3SHOUAIBA PHASE III
Worlds largest new-build IPP / IWPP (by debt
finance) Shuaibah project has been jointly
awarded the Desalination Deal of the Year 2006
by the Global Water Intelligence Shuaibah IWPP
wins prestigious Award Power and Water Deal of
the Year 2005 by (Euromoney, GWI)
4Introduction SHOUAIBA PHASE III IWPP
- Shoaiba project is the first of four IWPPs under
development in Saudi Arabia - The Project is to be located adjacent to the
existing Shoaiba power and desalination complex
110 km south of Jeddah, on the western coast of
Saudi Arabia - The Project will be developed as a Greenfield
crude oil-fired power and seawater desalination
plant and associated facilities located on land
owned by SWCC at Shoaiba, approximately 110 km
south of Jeddah, on the Red Sea coast. - The proposed Plant site is located next to the
existing Shoaiba phase 1 (300 MW and 50 MIGD) and
phase 2 (550 MW and 100 MIGD) plants owned and
operated by SWCC.
5(No Transcript)
6 PRE-QUALIFIED COMPANIES/CONSORTIUMS FOR
SHOAIBA (PHASE 3) IWPP
7Introduction SHOUAIBA PHASE III IWPP
- A Saudi-Malaysian consortium was selected as the
first-ranked bidder to build the SR9 billion
Shuaiba Independent Water and Power Project
(IWPP). - Shuaiba is the first of the four IWPP projects
that will be implemented by the private sector,
following from the Supreme Economic Council's
resolution 5/23 issued on June 3, 2002. - The other three projects include Shuqaiq, Raz
Azzour and Jubail. - The Saudi-Malaysian consortium will build, own
and operate the 900 MW and 880,000 m3/d Shuaiba
IWPP. - The credit support is to be provided by the
ministry of finance. 60 per cent of the share
capital will be owned by the consortium 32 per
cent will be owned by Public Investment Fund
(PIF) and the remaining 8 per cent will be owned
by the SEC. - WEC will enter into contractual negotiations with
the consortium and the Power Water Purchase
Agreement (PWPA) will be signed between the two
parties in for a period of (20) years.
8Introduction SHOUAIBA PHASE III IWPP
- Shuaibah Plant will export 194 million gallon of
water per day (880,000 cubic meters per day) and
900 megawatt of power. - This water export will serve the cities of
Makkah, Jeddah, Al-Taif and Al-Baha, while power
will be exported to the Western Electricity grid.
The combined export capacity of the four projects
will reach 492 million gallons of water per day,
(2.236 million cubic meters per day) and 4,500
megawatt of power. - Consortium of Tanaga Nasional Berhad, Khazanah
Nasional Berhad and Malakoff Berhad, of Malaysia,
- and Arabian Company for Water and Power
Development and Mada Company for Industrial
Commercial Investment Limited, of Saudi Arabia,
own indirectly the other 60. - The project companys construction contractor is
a consortium of Siemens (power) and Doosan Heavy
Industries (desalination) and the operator will
be Sogex. - NEW COMPANY NAMED
- Shuaibah Water Electricity Company"
9Financing SHOUAIBA PHASE III IWPP
- The Saudi-Malaysian Consortium has the support of
international and Saudi Finance Parties including
- ABN Amro,
- Arab Bank PLC,
- Export-Import Bank of Korea,
- Riyad Bank and
- Saudi Hollandi Bank.
- out of the projects total cost of US2.5
billion, more than US1.9 billion was financed
through senior, project finance, credit
facilities. - Commercial bank funding was arranged by Riyad
Bank, Saudi Hollandi Bank, ABN Amro and Arab
Bank. - The two export credit agencies are the
Export-Import Bank of Korea (Kexim) and Euler
Hermes of Germany (Hermes). - The Islamic tranche was led by Al Rajhi Banking
Investment Corp. of Saudi Arabia.
10PROJECT CONTRACTUAL RELATIONSHIPS
11Project Agreements
-
- The Project will be built, owned and operated by
the Project Company. - In order to expedite the incorporation of the
Project Company, PIF and SEC are in the process
of forming the Project Company as a Saudi joint
stock company of which PIF will initially own 80
and SEC 20. - The Successful Bidder will enter into the SSPA
with PIF and SEC to acquire 60 of the shares in
the Project Company (at par value). The
Successful Bidder will also enter into the
Shareholders Agreement with PIF and SEC.
12SHUQAIQ IWPP PHASE 2 Case Study 2
Independent power and power project (IWPP) CEM
525 PROJECT DELIVERY SYSTEMS MOHAMMED
JALALUDDIN
13DETAILS
- Shuqaiq Phase 2 IWPP
- Water 212,000 m³/day
- Power 700 MW
- Fuel Liquid Fuel (Crude Oil)
- Estimated
- Capital Cost SR 3,800 Million
- total SR 23,000 Millions for 4 initial projects)
14 ongoing Project RFQ ISSUED
- (RFQ) to 53 companies for Shuqaiq IWPP
- SOQ Received from 24 companies
- Prequalification 12 companies
15(No Transcript)
16(No Transcript)
17References
- WEC ( Water Electricity Company)
- SWCC
- MARAFIQ