Title: Magnet Resources, Cost
1Magnet Resources, Cost ScheduleandRecap of
the LARP Magnet Program Rich Stanek
Introduction Goals of the Program Planning
Methodology Resources Cost Schedule Summary Conclu
sions
2Introduction
- LARP Magnet Collaboration is centered in three
Labs LBNL, BNL FNAL - Success of the magnet program depends on
teamwork that utilizes all of the collaborations
resources while playing to the strengths of each
Lab - An important byproduct of the LARP collaboration
will be an overall stronger DOE capability to
produce high performance (Nb3Sn) magnets (one of
the enabling technologies for future
accelerators) - LARP is an RD Program not a construction project
(managed accordingly) - Each Lab has a core program that in many ways
complements LARP - Infrastructure and human resources are available
to LARP because these core programs exist - Given budget constraints, LARP needs the core
program support to establish and succeed with a
reasonable magnet program plan -
3LARP Magnet Program Goals
- LARP Magnet Program Goals
- Demonstrate by 2009, that Nb3Sn magnets are a
viable choice for an LHC IR Upgrade - gt requires stable conductor, technology choice
for a mechanical support system and scale up
capability with reproducible results - 1) Demonstrate predictable and reproducible
performance from short (1m long) model magnets
of acceptable gradient and aperture (gt200T/m,
90mm) while selecting a mechanical support system - gt FY05 through FY07 TQ series
- 2) Demonstrate scale up capability (4m long)
with same gradient (gt200T/m), aperture (90mm)
and performance (field quality and training) - gt FY08 through FY09 LQ series
- 3) Explore higher gradients (gt250T/m) and
larger apertures with short (1m long) model
magnets - gt FY08 through FY09 HQ series
4Achieving the Goals
- To be successful and achieve our goals LARP must
- Continue to develop a collaborative effort (have
a good start) - Need input from all Labs to build a strong
consensus on a chosen design - Need coordinated efforts to understand and
solve the materials issues - Need to build up common capabilities/procedures
among Labs (flexibility) - Concentrate on technical areas where issues
exist - Mechanics (preload, max stress, alignment)
- SC material (strand cable RD)
- Insulation (rad hard requirements)
- Fabrication techniques (handling, impregnating,
reacting) - Design, build and test Nb3Sn coils/magnets over
a range of options -
- Exploit the synergy between LARP and the core
programs - Utilize the strengths of each Lab (although
every Lab has full capabilities) - LBNL gt analysis and use of subscale coils to
get answers and cabling facility - BNL gt design, fabrication and testing
capabilities - FNAL gt fabrication infrastructure and test
facilities (materials magnets)
5Program Planning Methodology
- Program is defined at the annual Collaboration
Meeting, refined by the Magnet Steering Committee
and reviewed by DOE, LAPAC and LARP Executive
Committee - Individual tasks are identified that lead to
success of program goals - Task leaders are chosen
- Estimates of the required resources, costs and
schedules (including milestones) are made for
each task - Each Lab agrees on the availability of resources
and possible core program contributions to the
effort - L2 coordinators develop detailed schedules which
map out the execution of the tasks - Overall schedule/plan is established that meshes
the four parts of the magnet program together - Check that budget constraints are met or iterate
as necessary - Track progress (L2 coordinators quarterly
reports)
6Total Available Resources for LARP
- Each Lab brings a set of available labor
resources to LARP program - LARP Management (Program Leaders MSC L2) is
responsible for creating the optimum match of
budget resources to the tasks by selecting
which Labs are best suited to perform each part - Collaboration is a key ingredient in the formula
for LARP success, so some effort is dedicated to
learning, sharing and modifying procedures and
techniques between Labs to establish a common set
of working guidelines and experiences gt This
benefits LARP and the core programs - LARP budget can not/will not support all of these
people
7Current Labor Resource Usage
- FNAL plan for LARP FY05 activities calls for 3.1
FTE in salary support - In FY06 this increases to 9.3 FTE
- LBNL plan for LARP FY05 activities calls for
3.2 FTE in salary support - In FY06 this increases to 10 FTE
- BNL plan for LARP FY05 activities calls for 1.7
FTE in salary support - In FY06 this increases to 6.8 FTE
Core programs will be able to contribute
additional labor (to work on LARP related tasks)
if budgets allow. LARP will need this added
effort to be successful.
8Budget/Cost Estimation
- Initial Task Cost Estimation is done using
standard LARP rates - Scientist/Engineer 180K/yr (fully loaded)
- Designer/Tech 150K/yr (fully loaded)
- SC strand 1230/kg
- Once a task is explicitly defined, a responsible
Lab is identified, and the required resources are
understood, the specific labor rates for that
particular Lab can be input into the cost
estimate -
- MS costs are optimized by choosing the lowest
cost option for large purchases (SC strand) and
by using common parts and vendors - To minimize design and fabrication costs and
promote commonality, CAD drawings and actual
tooling/fixtures are shared among Labs - Costs (developed in Task Sheets) are input using
best estimate techniques and contingency is
held by the LARP Program Managers
9FY06 LARP Magnet Budget
- Budget distribution needs to be flexible to
respond to changing circumstances (RD Program) - Need to plan for success but prepare for
difficulties (this is a process - subject to
change) - Strategic Decision Keep all three Labs actively
engaged - Activity associated with long magnet development
cannot wait for the success of the short models
gt some questions can be answered now - LARP budget is limited lots to do
- gt LARP and the core programs need each other
10LARP Budgets
- Each Lab is represented on the Magnet Steering
Committee (MSC) and therefore has a voice in how
the program is planned and executed - gt sometimes very difficult decisions (delay of
open mid-plane dipole) - L2 coordinators are responsible for coordinating
Task Sheets for work in their areas. Using
standard times and costs for similar tasks
(helps in the planning stage) - Determining the final budget and split of funds
is an iterative process but in the end it is a
function of where the work has the best chance
for success at the least cost to the program - 2009 Goal of demonstrating a long Nb3Sn
quadrupole magnet has resulted in a more focused
approach (narrower scope and streamlined path,
not allowing for excursions to explore more of
parameter space) - gt this is where the core programs are important
- LARP funding profile is fairly flat 11M (FY06
07), 12M (FY08 09)
11Schedule
- The overall LARP schedule is intended to be used
as a tool to help plan and manage the magnet RD
program. It is not the same as a Resource
Loaded Schedule used to control a project - L2 coordinators develop detailed schedules that
include all of the important steps needed to
complete a task. This is used to track the work
at a more appropriate level and provide immediate
feedback as to the completion of tasks and
achievement of milestones - Information from these L2 schedules is rolled
up into the integrated schedule to create an
overall plan that shows interdependencies between
L2 activities and possible over commitments of
funds or resources - Overall plan can change as a result of
- budget profile changes
- results from completed tasks
- agreement with CERN management for shift of
priorities
12Overall Schedule Work in Progress
13Summary
- The LARP RD Magnet Program has a very specific
intermediate goal - gt to demonstrate the viability of Nb3Sn
magnets for the LHC quadrupole upgrade by 2009 - LARP requires an effective collaborative effort
among the three Labs (LBNL, BNL, FNAL) and a by
product of this program will be a stronger
high-field magnet capability across the DOE
complex - LARP and the Labs core programs need each other
for success - Lab/core programs provide infrastructure and
human resources - LARP provides the specific application and
focus for the technology - They are complimentary
- LARP is an RD Program not a construction project
- Change of plan is inevitable
- Diversity in approach by different Labs is
constructive - Key is to utilize all available resources to
develop a solution that meets the program goals
14Conclusions
- LARP Magnet RD Program is technically
challenging - Budget is tight and will force some aspects of
the program that could be worked on earlier to be
delayed - Schedule is aggressive and relies on
- the material vendor to develop a stable conductor
with appropriate Jc and reproducibility (CDP is a
key partner) - success of the short model magnet tasks
- LARP has access to good people (technically
competent and motivated to succeed) and good
facilities (infrastructure that Lab/core programs
already have in place) - Plan exists to achieve the Program Goals on the
required timescale