Magnet Resources, Cost - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Magnet Resources, Cost

Description:

Success of the magnet program depends on teamwork that utilizes all of the ... Exploit the synergy between LARP and the core programs ... – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 15
Provided by: tdserve
Category:

less

Transcript and Presenter's Notes

Title: Magnet Resources, Cost


1
Magnet Resources, Cost ScheduleandRecap of
the LARP Magnet Program Rich Stanek
Introduction Goals of the Program Planning
Methodology Resources Cost Schedule Summary Conclu
sions
2
Introduction
  • LARP Magnet Collaboration is centered in three
    Labs LBNL, BNL FNAL
  • Success of the magnet program depends on
    teamwork that utilizes all of the collaborations
    resources while playing to the strengths of each
    Lab
  • An important byproduct of the LARP collaboration
    will be an overall stronger DOE capability to
    produce high performance (Nb3Sn) magnets (one of
    the enabling technologies for future
    accelerators)
  • LARP is an RD Program not a construction project
    (managed accordingly)
  • Each Lab has a core program that in many ways
    complements LARP
  • Infrastructure and human resources are available
    to LARP because these core programs exist
  • Given budget constraints, LARP needs the core
    program support to establish and succeed with a
    reasonable magnet program plan

3
LARP Magnet Program Goals
  • LARP Magnet Program Goals
  • Demonstrate by 2009, that Nb3Sn magnets are a
    viable choice for an LHC IR Upgrade
  • gt requires stable conductor, technology choice
    for a mechanical support system and scale up
    capability with reproducible results
  • 1) Demonstrate predictable and reproducible
    performance from short (1m long) model magnets
    of acceptable gradient and aperture (gt200T/m,
    90mm) while selecting a mechanical support system
  • gt FY05 through FY07 TQ series
  • 2) Demonstrate scale up capability (4m long)
    with same gradient (gt200T/m), aperture (90mm)
    and performance (field quality and training)
  • gt FY08 through FY09 LQ series
  • 3) Explore higher gradients (gt250T/m) and
    larger apertures with short (1m long) model
    magnets
  • gt FY08 through FY09 HQ series

4
Achieving the Goals
  • To be successful and achieve our goals LARP must
  • Continue to develop a collaborative effort (have
    a good start)
  • Need input from all Labs to build a strong
    consensus on a chosen design
  • Need coordinated efforts to understand and
    solve the materials issues
  • Need to build up common capabilities/procedures
    among Labs (flexibility)
  • Concentrate on technical areas where issues
    exist
  • Mechanics (preload, max stress, alignment)
  • SC material (strand cable RD)
  • Insulation (rad hard requirements)
  • Fabrication techniques (handling, impregnating,
    reacting)
  • Design, build and test Nb3Sn coils/magnets over
    a range of options
  • Exploit the synergy between LARP and the core
    programs
  • Utilize the strengths of each Lab (although
    every Lab has full capabilities)
  • LBNL gt analysis and use of subscale coils to
    get answers and cabling facility
  • BNL gt design, fabrication and testing
    capabilities
  • FNAL gt fabrication infrastructure and test
    facilities (materials magnets)

5
Program Planning Methodology
  • Program is defined at the annual Collaboration
    Meeting, refined by the Magnet Steering Committee
    and reviewed by DOE, LAPAC and LARP Executive
    Committee
  • Individual tasks are identified that lead to
    success of program goals
  • Task leaders are chosen
  • Estimates of the required resources, costs and
    schedules (including milestones) are made for
    each task
  • Each Lab agrees on the availability of resources
    and possible core program contributions to the
    effort
  • L2 coordinators develop detailed schedules which
    map out the execution of the tasks
  • Overall schedule/plan is established that meshes
    the four parts of the magnet program together
  • Check that budget constraints are met or iterate
    as necessary
  • Track progress (L2 coordinators quarterly
    reports)

6
Total Available Resources for LARP
  • Each Lab brings a set of available labor
    resources to LARP program
  • LARP Management (Program Leaders MSC L2) is
    responsible for creating the optimum match of
    budget resources to the tasks by selecting
    which Labs are best suited to perform each part
  • Collaboration is a key ingredient in the formula
    for LARP success, so some effort is dedicated to
    learning, sharing and modifying procedures and
    techniques between Labs to establish a common set
    of working guidelines and experiences gt This
    benefits LARP and the core programs
  • LARP budget can not/will not support all of these
    people

7
Current Labor Resource Usage
  • FNAL plan for LARP FY05 activities calls for 3.1
    FTE in salary support
  • In FY06 this increases to 9.3 FTE
  • LBNL plan for LARP FY05 activities calls for
    3.2 FTE in salary support
  • In FY06 this increases to 10 FTE
  • BNL plan for LARP FY05 activities calls for 1.7
    FTE in salary support
  • In FY06 this increases to 6.8 FTE

Core programs will be able to contribute
additional labor (to work on LARP related tasks)
if budgets allow. LARP will need this added
effort to be successful.
8
Budget/Cost Estimation
  • Initial Task Cost Estimation is done using
    standard LARP rates
  • Scientist/Engineer 180K/yr (fully loaded)
  • Designer/Tech 150K/yr (fully loaded)
  • SC strand 1230/kg
  • Once a task is explicitly defined, a responsible
    Lab is identified, and the required resources are
    understood, the specific labor rates for that
    particular Lab can be input into the cost
    estimate
  • MS costs are optimized by choosing the lowest
    cost option for large purchases (SC strand) and
    by using common parts and vendors
  • To minimize design and fabrication costs and
    promote commonality, CAD drawings and actual
    tooling/fixtures are shared among Labs
  • Costs (developed in Task Sheets) are input using
    best estimate techniques and contingency is
    held by the LARP Program Managers

9
FY06 LARP Magnet Budget
  • Budget distribution needs to be flexible to
    respond to changing circumstances (RD Program)
  • Need to plan for success but prepare for
    difficulties (this is a process - subject to
    change)
  • Strategic Decision Keep all three Labs actively
    engaged
  • Activity associated with long magnet development
    cannot wait for the success of the short models
    gt some questions can be answered now
  • LARP budget is limited lots to do
  • gt LARP and the core programs need each other

10
LARP Budgets
  • Each Lab is represented on the Magnet Steering
    Committee (MSC) and therefore has a voice in how
    the program is planned and executed
  • gt sometimes very difficult decisions (delay of
    open mid-plane dipole)
  • L2 coordinators are responsible for coordinating
    Task Sheets for work in their areas. Using
    standard times and costs for similar tasks
    (helps in the planning stage)
  • Determining the final budget and split of funds
    is an iterative process but in the end it is a
    function of where the work has the best chance
    for success at the least cost to the program
  • 2009 Goal of demonstrating a long Nb3Sn
    quadrupole magnet has resulted in a more focused
    approach (narrower scope and streamlined path,
    not allowing for excursions to explore more of
    parameter space)
  • gt this is where the core programs are important
  • LARP funding profile is fairly flat 11M (FY06
    07), 12M (FY08 09)

11
Schedule
  • The overall LARP schedule is intended to be used
    as a tool to help plan and manage the magnet RD
    program. It is not the same as a Resource
    Loaded Schedule used to control a project
  • L2 coordinators develop detailed schedules that
    include all of the important steps needed to
    complete a task. This is used to track the work
    at a more appropriate level and provide immediate
    feedback as to the completion of tasks and
    achievement of milestones
  • Information from these L2 schedules is rolled
    up into the integrated schedule to create an
    overall plan that shows interdependencies between
    L2 activities and possible over commitments of
    funds or resources
  • Overall plan can change as a result of
  • budget profile changes
  • results from completed tasks
  • agreement with CERN management for shift of
    priorities

12
Overall Schedule Work in Progress
13
Summary
  • The LARP RD Magnet Program has a very specific
    intermediate goal
  • gt to demonstrate the viability of Nb3Sn
    magnets for the LHC quadrupole upgrade by 2009
  • LARP requires an effective collaborative effort
    among the three Labs (LBNL, BNL, FNAL) and a by
    product of this program will be a stronger
    high-field magnet capability across the DOE
    complex
  • LARP and the Labs core programs need each other
    for success
  • Lab/core programs provide infrastructure and
    human resources
  • LARP provides the specific application and
    focus for the technology
  • They are complimentary
  • LARP is an RD Program not a construction project
  • Change of plan is inevitable
  • Diversity in approach by different Labs is
    constructive
  • Key is to utilize all available resources to
    develop a solution that meets the program goals

14
Conclusions
  • LARP Magnet RD Program is technically
    challenging
  • Budget is tight and will force some aspects of
    the program that could be worked on earlier to be
    delayed
  • Schedule is aggressive and relies on
  • the material vendor to develop a stable conductor
    with appropriate Jc and reproducibility (CDP is a
    key partner)
  • success of the short model magnet tasks
  • LARP has access to good people (technically
    competent and motivated to succeed) and good
    facilities (infrastructure that Lab/core programs
    already have in place)
  • Plan exists to achieve the Program Goals on the
    required timescale
Write a Comment
User Comments (0)
About PowerShow.com