Title: WFMOS Status Report
1WFMOS Status Report
- Doug Simons
- Gemini Observatory
- January 2008
2Presentation Topics
- WFMOS in Geminis Aspen Instrument Program
Context - WFMOS Conceptual Design Study Status
- What has happened since my presentation at the
Subaru Users Meeting a year ago - Future Key Steps
- UK Withdrawal Impact
- Subaru/Gemini WFMOS Science Conference
3Aspen Instrument Program
Gemini Planet Imager
Precision Radial Velocity Spectrometer
Wide Field Multi- Object Spectrometer
Ground Layer Adaptive Optics
4Gemini Planet Imager Remains On Track
- All GPI institutions are making excellent
progress toward CDR this year - Deployment planned for 2010 at Gemini-S
- UK withdrawal from Gemini has little/no effect on
GPI as we made firm contractual commitments
already to build GPI
5WFMOS Status
- Wide Field MOS
- Conceptual design studies are about to begin -
details later - HSC
- CoDR scheduled for April 2008
- Important that results of HSC design trades get
fed into WFMOS design studies
Wide Field Multi- Object Spectrometer
- Together HSC WFMOS will provide unique wide
field imaging and spectroscopy capabilities that
no other observatory will match on similar
timescales
6Ground Layer AO Status
- University of Hawaii under contract to gather
Gemini-N site data using LOLAS and SLODAR - Expect to complete data collection phase by mid
2008 - Full analysis, including GLAO performance
prediction will be completed by the end of 2008
which will feed into a decision about building a
GLAO system for Gemini-N
Ground Layer Adaptive Optics
7Precision Radial Velocity Spectrometer
- Conceptual design studies completed and contract
negotiated with ATC led team - Contract submitted for Board approval in Nov.
2007 but UK announced intention to withdraw at
that time - Gemini Board did not approve the PRVS contract
due to Aspen funding uncertainties, firm
commitments already made to GPI, and the need to
protect WFMOS
Precision Radial Velocity Spectrometer
8Aspen Program Development Sequence
Jan 2008
GPI
PDR
CDR
CoDR
Mauna Kea Site Tests
Feasibility Study
Perf. Modeling
GLAO
CoDR?
PDR?
HRNIRS Studies
PRVS
CoDR
PDR
CDR?
Feasibility Study
CoDR
PDR?
WFMOS
2005
2006
2007
2008
2009
2010
2011
9Some WFMOS QA
10What has happened to the WFMOS design studies
since the last Subaru Users Meeting?
- Lots, but the main progress is that 2 teams have
submitted proposals to prepare conceptual design
studies for WFMOS. These two teams have just been
placed under contract to complete these studies
and Gemini will fund them for a cost of
3,500,000.
11Who will be working on the WFMOS design studies?
- Two teams will work on separate competitive
studies - One is led by the Jet Propulsion Lab in
California, the other by the Anglo Australian
Observatory - These teams include other institutions in the US,
UK, and Brazil - The studies yield competitive bids to build
WFMOS, likely at the major subassembly level - Studies will require close technical exchange
with HSC team to ensure compatibility with WFC
and telescope - Would like to explore in 2008 involvement of
Japanese institutions to potential build WFMOS
components in the future
12Why did Gemini sponsor these design studies?
- These studies are intended to -
- Provide much better estimates of the cost and
time needed to build WFMOS than we have now - Generate conceptual level approaches to the
design of WFMOS and analyses of the science that
is likely possible with WFMOS - This basic information is required before Gemini
or Subaru could decide to build WFMOS, an
instrument of unprecedented scale
13Has a commitment been made at Gemini or Subaru to
build WFMOS?
- No much needs to be done before such a
commitment is possible, including - Completing the WFMOS design studies to provide us
all with much more information than we have had
in the past - Gemini and Subaru must reach an agreement about
how we will share the cost, technical
development, scientific use of the instrument,
and exchange of telescope time as part of this
program - Funding needs to be secured at Gemini and Subaru
- Funding the HSC corrector and telescope
modifications would represent significant Subaru
contributions already.
14What is the priority for WFMOS compared to other
instruments being developed at Gemini?
- WFMOS has broad support within the Gemini
partners and remains the highest priority element
in Geminis instrument program - The willingness of the Gemini Board to
unilaterally fund these studies, at Geminis
risk, reflects the interest level at Gemini in
WFMOS
15What is the impact of the UKs recent withdrawal
from Gemini on WFMOS?
- Near term -
- Not much as the Board decided that we should
proceed with the WFMOS studies as originally
planned (which includes UK institutions) since
that is in the best scientific interests of
Gemini compared to starting over with new teams. - Long term -
- The lack of UK Aspen contributions to help fund
WFMOS could be an issue and this must be
addressed as the remaining Gemini partners
reformulate the partnership.
16Is the Gemini Board still committed to WFMOS
given the UK withdrawal from Gemini?
- The Board resolves to maintain the continuity of
operations and the enhanced scientific
opportunities of the Gemini Observatory by the
remaining Gemini Parties during this period of
transition. Furthermore, the Board wishes to
convey its continued goal of realizing our shared
future science aspirations that are advanced
through the Aspen program.
17When will the WFMOS studies be done and what
happens after they are done?
- A conceptual design review will be held in early
2009 to recommend how we proceed with WFMOS,
based upon the results of the 2 studies - Subaru and Gemini will be represented on the
review committee - The results of this review will be reported to
Subaru and Gemini management - By this time a draft Subaru/Gemini WFMOS
agreement for the joint development and use of
WFMOS needs to be in place as well so we have a
complete understanding of all the
challenges/issues - With all of this information in place, I expect
that a decision will be made in 2009 about
building WFMOS, either in its entirety or
incrementally
18How can Subaru and Gemini develop a sense of
joint ownership, scientifically and technically,
for a major new instrument like WFMOS?
- Telescope time exchange -
- Our current time exchange program is the seed
for our future time exchange program once WFMOS
is deployed. It needs to be developed further to
ensure the capabilities Gemini and Subaru offer
through this program are meeting the needs of our
respective communities - Technology -
- Organizations in Japan that are interested in
potentially building components of WFMOS need to
be identified - Science -
- The Subaru and Gemini science communities need to
develop broader collaborations in support of
future major joint Subaru/Gemini science
campaigns with WFMOS as well as PI science.
Speaking of which
19Subaru/Gemini WFMOS Science Conference
- To be held at the Waikoloa Marriott on the Big
Island - 19-21 May 2008
- Intended to bring together scientists from the
WFMOS study teams as well as the Subaru and
Gemini communities to explore science
opportunities with WFMOS and foster future
collaborations
Waikoloa Marriott
20I Look Forward to Your Questions