Goose Creek Consolidated Independent School
District 2005 BOND PROGRAM
JACOBS CONTRIBUTION TO DATE
May 2006
2
Program Planning Management Services
  • Safety Security
  • Added a comprehensive Article 10 Protection of
    Persons and Property to the Contract Documents.
  • Added Security and Badging language to the
    Specifications.
  • Reviewed, evaluated, and scored all Contractor
    Safety Programs, EMRs, Resumes of Safety
    Personnel, and Drug and Alcohol programs
  • Identified Owners overall objectives prepared
    program policies needed to obtain objectives.
  • Developed a Program organization chart including
    PM roles responsibilities.
  • Completed Review, coordination implementation
    of Front End Documents required by district for
    CSP CM at Risk process for
  • Review of contract documents,
  • General conditions,
  • Architectural specifications,
  • District standards and specifications.
  • Established Project Management protocol
    procedures for effective communication between
    Owner, Architects, Engineers Consultants.
  • Recommended project delivery method including the
    implementation of the CSP review worksheet -
    effective tool used to evaluate select a
    General Contractor.

3
Commissioning Activities
  • HIGHLANDS JR HIGH SCHOOL
  • reviewed design documents and submitted CxA
    comments
  • attended design team for 99, and final
    design docs
  • HORACE MANN JR HIGH SCHOOL
  • reviewed design documents and submitted CxA
    comments
  • attended design team meetings for 50 and 100
    design docs
  • HOPPER ELEMENTARY SCHOOL
  • reviewed design documents and submitted CxA
    comments
  • attended design team meetings for 100 design
    docs
  • NEW HIGH SCHOOL 3
  • reviewed design documents and submitted CxA
    comments
  • attended design team for 50, 75, 100, and
    final design docs
  • GENTRY JR HIGH SCHOOL
  • reviewed design documents and submitted CxA
    comments
  • attended design team meetings for 100 design
    docs
  • ELEMENTARY 14 BOWIE ELEMENTARY SCHOOLS
  • reviewed design documents and submitted CxA
    comments
  • attended design team meetings for 50 and 100
    design docs

4
Master Program Schedule
  • Implemented Overall Master Program Schedule in
    Primavera based on the needs of design
    construction community including
  • phasing,
  • sequencing packaging of design,
  • consulting equipment/construction contracts
  • Prepared monthly

    updates for

    Bond Program.
  • Developed

    prepared

    monthly updated

    schedules for

    specific individual

    projects

5
Design Review Comments
  • Facilitate document weekly design coordination
    meetings with Architects, Engineers Consultants
    to discuss review progress.
  • Performed design review helped to come up with
    possible project cost savings
  • Design Review Estimate Status on Specific
    Projects
  • Bowie ES ES 14
  • Completed design reviews of 50 and 100 CDs
  • Completed review of 50 and 100 CD cost
    estimates
  • Gentry JHS Hopper PS
  • Completed design reviews of 100 DDs and 100 CDs
  • Completed review of 100 DD cost estimate
  • Prepared detailed 100 CD cost estimate
  • Horace Mann JHS
  • Completed design reviews of 50, 75 and 100 CDs
  • Completed review of 100 DD cost estimate
  • Prepared detailed 50 CD cost estimate
  • Agricultural Science Facility
  • Completed schematic design of new facility
  • High School 3
  • Received and reviewed the 50 CD submission,
    including front end documents, specifications and
    drawings.
  • Received and reviewed the 75 CD submission
    including front end documents, specifications and
    drawings.

6
Project Management Information Control System
  • Project Management Control System
  • Developed customized GCCISD Database with 41
    projects
  • Created customized reports for Project Controls
    (Cost Control, Doc Control etc)
  • Loaded expenditures into Jacob's PMCS to
    calculate projected over/under.
  • Lawson Integration
  • Identifying and resolving account

    category
    discrepancies in

    Lawson
    accounting system.
  • Developed a Cost Code


    structure in PMCS to


    interface with the


    Lawson Accounting System
  • Document Control
  • PMCS is updated with all contacts, meeting
    minutes, companies contact information.
  • Aided in integration of a document control plan
    for all bond related correspondence
    documentation.

7
Program Budgeting Cost Management
  • Prepared a program budget to account for project
    expenses.
  • Implemented a cost management program that will
    interface with the Owners cost reporting system.
  • Reconciled District's 2005 Bond expenditures from
    June 2005 to current.
  • Cross-referenced project encumbrances for
    accuracy.
  • Upon receipt of the over budget estimates, Jacobs
    researched the major portions of the projects
    with subcontractors to verify the prices being
    proposed were within reason.
  • Jacobs/GCCISD worked with the GCs to get cost
    savings.
  • Along with the Architect recommended that the
    existing proposals not be accepted due to the
    accelerated costs.
  • Facilitated numerous cost savings meetings with
    Owner, Architect and Contractor in an effort to
    bring project within budget.
  • Worked with Architect and Owner to offer cost
    savings suggestions that would be acceptable to
    the district.

8
Miscellaneous
  • Communication
  • Monthly Reports
  • Meeting Minutes
  • Mobilization Session
  • Client Expectation Survey
  • Administrative
  • Established administrative procedures for
    pre-design, design, procurement, construction and
    post construction.
  • Established an effective filing system and
    procedures by developing paper electronic file
    for all 34 projects to maintain all documents
    correspondence
  • Developed a Construction Calendar for
    coordination between GCCISD and Jacobs.
  • Administered the advertisement for bid and
    participated in the bidding process, reviewed and
    evaluated proposals.
  • Prepared the CSP review worksheet which evaluates
    each Contractor.

9
  • Questions??