Title: 450 GeV Preliminary Commissioning: Measurement Programme
1450 GeV Preliminary Commissioning Measurement
Programme
- polarities
- apertures
- basic optics checks
thanks to Rhodri Jones, Stefano Redaelli,
Ralph Steinhagen
2additional aims on LHC-commissioning web page
https//lhc-commissioning.web.cern.ch/lhc-commiss
ioning/
- measurement program with pilots
- low intensity, polarities aperture (1st pass)
- linear optics checks
- trajectory vs. kick, phase advance,
- BPM corrector polarity, dispersion
- tunes, orbit, chromaticity, coupling
time estimate (lhc-commissioning web) 4 days per
ring ? 8 days with beam in total
3flow chart from Mike Lamont
4 from lhc-commissioning web site
Q
? coupling correction 1st pass
Q
orbit
corrector BPM polarity
linear optics check
? coupling correction 2nd pass
aperture scan
5expected static errors
6BPM resolution
- Nominal resolution (5 µm) for
- single bunch intensity gt 2-3x1010 charges per
bunch - global orbit 43 pilot bunches
E.B. Holzer, J.-J. Gras, O.R. Jones, Chamonix XV
workshop
7initial adjustments
- set tunes to nominal or alternative WP
- (0.28/0.31) or (0.285/0.385)
- nominal WP requires coupling correction
- - from tune response to two orthogonal skew-quad
families - - or using multi-turn BPM readings
- if we use alternative WP need to switch later
- correct chromaticity
- - maximize decoherence time (fast)
- - radial steering
- smoothen orbit IR3, IR7 (cleaning), IR6 (dump)
and injection region critical
S. Fartoukh, LCC 23/10/2002
8tune measurement raw data
Q50
Q-50
x
turns
Q20
Q2
HEADTAIL, coupling k0.05, broadband impedance,
detuning w. ampl., space charge, Nb 3x1010
9tune measurement spectrum
Q50
Q-50
Q20
Q2
peak yields same tune value 0.2813/-0.0003 in
all 4 cases
10BPM corrector polarities
- already partially checked during threading
- (Jorg Wenninger)
- 530 x 2 orbit correctors per ring excite each to
Dx,y 500 mm (qcor5 mrad ltlt 1.2 mrad (max.)) - 1056 x 2 BPMs per ring
- time required 10-30 s per corrector
- ? estimate 4-9 h per ring for polarity,
calibration, side-benefit redundant data for
linear optics check - in addition
- 3 interlock BPMs in IP6 for MP (bump to check BPM
position w.r.t. TCDQ) - BPMs at TDI
Ralph Steinhagen
11what is a bad BPM?
- wrong polarity
- wrong plane
- large noise (spray?)
- wrong location
- nonlinearity?
- large orbit offset?
- calibration error
- other
discussion triggered by Peter Limon Oliver
Bruning in Chamonix_at_Divonne
12basic optics checks
- process orbit-response data from corrector tests
(5-20 mm resolution) to get b coupling - take multi-turn BPM data for harmonic analysis
(50-200 mm resolution, fast) to get f, b
coupling - possibly K modulation at a few critical locations
(wire scanners, SL monitor, IP6,) - radial steering for measuring dispersion (expect
few cm or resolution) Q off-momentum b
(multi-turn BPMs) - coupling correction
- change of working point?
- estimated minimum time 3-5 h / ring
13finding local sources of b beat
- fit against model / inversion of quadrupole
response matrix - e.g., from measured phase beating
- may not be trivial, especially for distributed
errors - simultaneous fit of data from both rings
constraints
in short
14Example 1, SPS comparing measurement prediction
phase beating induced by a single quadrupole
QE604 in the SPS red measurement, blue model
prediction (J. Klem, 2000)
from phase of harmonic analysis
15Example 2, SPS result of fit using SVD
pseudo-inversion
SPS test with quadrupole QE603, DQ0.05, varying
weight l for DK in SVD solution
weight low many quadrupoles excited to get
perfect fit
reasonable weight
correct quadrupole is identified for proper
weight l
C. Carli, G. Arduini, F.Z., EPAC04
weight high all quadrupole changes a small
16aperture
- determine global transverse aperture using pairs
of orthogonal correctors (minimum 8 measurements
with beam loss, per ring) center beam inside
aperture for each corrector - momentum aperture by radial steering until beam
loss (2 measurements) - determine center frequency? (radial steering
sextupoles) important to compare both rings - in case of problem local closed bumps or sliding
bumps across IRs or arcs - estimated minimum time 2-3 hours / ring
17(No Transcript)
18y aperture 14s limited at VMAJI/B in IR2, 3, 7
(8)
x aperture 14s limited at VSSB VMAII/B in
all SSS
apertures for ideal optics
d aperture 0.008 limited at VSSB VMAII/B in
IR2, 3, 7 (8)
from mixture of MAD-X optics database and
aperture model setup for collimation studies
(Stefano Redaelli)
19conclusions
- initial measurements can be done in 8 days (2
rings) - readiness of procedures software critical
- up-to-date MAD-X or SIXTRACK model for flight
simulations? - measured field errors, apertures, realistic
relative misalignments (including spool-pieces
etc.)
20appendix
21apertures for ideal optics role of dispersion
horizontal aperture / total beam size
correlation between xb d aperture
similar to picture of Ax/sx,b on slide 18