Title: Transparency 1
1PPP in Germany
Coalition agreement of 11 November 2005
Component of the Federal Governments innovation
initiative
2Objectives
-
- Key objective
- Deliver public services more efficiently
-
3Subordinate objectives
- Improve legal framework
- The PPP Acceleration Act reduces re-quirements
in the fields of procurement law, tax law, law
on public fees and budgetary law and the
Investment Act. - The PPP Simplification Act is being prepared to
further simplify the legal framework.
4Subordinate objectives
- Meet quantitative targetsincrease the portion
of PPP in the total of public investments to 15
in the medium term - Provide central guidancee.g. in the form of
manuals and specimen contracts (cf. transparency
5) - Setting up centres of competence (cf.
transparency 6)
5Guidance and manuals
- Guidance on PPP in the construction of public
buildings with manual - Guidance on PPP and the law on government
grants with manual - Manual on investment appraisals
- Manual on procurement law
6Centres of competence
7Number of projects
- 46 PPP projects in public building
construction Total capital expenditure of
about 1.4 billion - A further 120 projects for the construction of
public buildings are being prepared Total
capital expenditure of about 6 billion - Majority of PPP projects at local government
level Currently 39 projects for the
construction of buildings at local authority
level, 7 at federal state level
8Examples at federal level
- Federal Ministry of Defence
- HERKULES (IT project)Military barracks in
Munich - Federal Ministry of Transport, Building and
Urban Development Build-Operate-Transfer
contracts for the construction of buildings and
roads
9 Facts from the German Institute of Urban
Affairs
- Number of contracts in 2005 increased by 50
compared to previous year due to expectations of
enhanced efficiency and speeding-up effects - At local government level, average efficiency
yields of 10 are achieved - Average capital expenditure at local government
level 13-16 million per project - Average capital expenditure at federal/state
level 70 million per project
10 Requirements of the external audit institutions
regarding PPP
- Requirements of external audit institutions at
federal and state levels (10 findings) - 1. In the case of PPP projects, debt-service
expenditure (interest and debt repayment)
are replaced by other re- curring expenditure
and place a similar burden on future
budgets. Only efficiency gains that impact the
budget are capable of reducing the burden
on the budget. - 2. Where the public sector cannot afford a
project under conventional funding, it must
not go through with such projects under
alternative funding arrangements.
11 Requirements of the external audit institutions
regarding PPP
- Only once the need for a project has been
established, officials in charge may consider
whether the project is suitable for PPP. - The efficiency of a project must have been proven
in each individual case and over entire project
duration (life-cycle approach). - Risks must be shared by the public sector and the
private partner in a reasonable and efficient
way.
12 Requirements of the external audit institutions
regarding PPP
- The public sector must not circumvent procurement
law by pursuing PPP projects. - The complexity of PPP projects requires
particular focus on contractual arrangements.
Inadequate contracts have a direct negative
impact on project efficiency. - 8. The cost impact of PPP projects must be
clearly presented in budgets for the entire
contract duration. The burden on future budgets
must be transparent.
13 Requirements of the external audit institutions
regarding PPP
- Audit access by external audit institutions must
be ensured. - At local government level, PPP projects are often
similar to borrowing, which requires approval by
the supervisory authorities in almost all German
states. Federal and state governments should
impose minimum standards for PPP projects.
14Audit access rights and PPP
- The public partners
- Extensive audit access
- The private partners
- Audit access only where public budget funds are
used - Therefore
- Stipulate full audit access in the contract
15Audit activities
- Currently, the Bundesrechungshofs audit work
focuses on defence and road construction
issues. - However, most projects have not been underway
long enough to evaluate effectively the
lessons learnt or conclude on the potential
efficiency and risks of the projects. - Any statements of principle have been derived
from the risks identified in the cases audited
16Audit results
- Based on the lessons learnt with the HERKULES
IT project, the Bundesrechnungshof has developed
general recommendations on investment appraisals
in connection with PPP projects - Investment appraisals for PPP projects must be
carried out before committing funds and
commencing contract-award procedures. - Any decisions about PPP projects must be preceded
by a comprehensive evaluation of the Federal
Governments relevant options. This evaluation
must not be restricted by the annual expenditure
ceilings.
17Audit results
- The valuation of the benefits of PPP must be
designed so that the chosen priorities reflect
the objectives of the PPP fully and
transparently. - The risks of any alternative options have to be
examined in detail and quantified where possible.
Their impact on the decision-making process needs
to be illustrated.
18 Audit results
- Further lessons learnt from auditing the PPP
sector can be found in the cross-boundary annual
report item on investment appraisals / efficiency
studies in the federal administration - Sometimes, the authorities responsible for
planning the PPP projects have - based their decisions on assumptions and
forecasts going - beyond a realistic conservative estimate of
future - development
- subsequent costs, especially personnel costs
that cannot - be cut immediately, were taken into account
inadequately or - not at all
19Audit results
- used incomplete data, especially in evaluating
optimised purely public-sector solutions - focused on intended benefits to the detriment of
the quantitative results of the investment
appraisal - in their appraisals stated the impact of
potential risks in qualitative terms only - during the operational phase of project, failed
to adapt their investment appraisals to changing
conditions.
20 Findings of the Bavarian State Court of Audit
- No cost benefits found for road works PPPs
compared to conventional procurement!
21Consequence
- Decisive justification for PPP from the point of
view of external audit institutions obtaining
efficiency yields - For each individual project, an
efficiency yield must be proven by means
of a transparent, full and appropriate
investment appraisal.
22Efforts to achieve nation-wide uniform approach
- ACTING PARTIES
- Joint working group of the Federal Government
and the - states
- OBJECTIVE
- nation-wide uniform (minimum) standards for
investment - appraisals
- setting up uniform terms and techniques and
thereby - reduce the transaction costs incurred
- continuous further development with regard to
lessons learnt in practice
23Principles
- uniform project definition
- practical procurement situation
- figures are based on reliable estimates
- risk assessment
- tax impact considered
- quantitative investment appraisal on the basis of
discounted cash-flows
24Stages of the PPP procurement process
Stages of PPP procurement process
Stages of the PPP-related investment appraisal
Stage I
Levels of detail and precision of the data
available increases
Stage II
Stage III
Stage IV
25 Stages of the investment appraisal
- Stage I
- Determining project efficiency
- Test for PPP suitability
- Stage II
- Calculation of the public sector comparator
- Estimate of PPP costs
-
- Stage III
- final comparison of the bids received with the
PSC - If PSC gt present value of the PPP-solution,
award contract to the - successful bidder and signing of contract.
- Stage IV
- project controlling
26Project efficiency
- Analysis of potential advantages and
disadvantages of the planned project from a
macro-economic perspective - If advantages are found to prevail
- Identification of the procurement option that
provides best value for money
27Test for PPP suitability
- QUESTION
- Does the planned project meet pre-defined
requirements which, based on the lessons learnt
from previous projects, have proven essential
for the success of a PPP solution. - EVALUATION CRITERIA
- project volume
- legal and / or project-specific restrictions
- structure of project risks
- remuneration mechanism
- specifications
- interest of market participants
- market structure
- DIFFICULTIES
- little concrete information about the project is
available at this time
28 Preliminary investment appraisal
- Analysis of the economic benefit of the PPP
before opening the contract-award procedure. - Comparison of estimated PPP cost and
the PSC
29Methodology
- type of investment appraisal based on assessing
discounted cash-flows (net-present-value
method) - for projects having an overall economic impact
cost-benefit analysis - qualitative aspects can be evaluated by means of
utility analysis - use of nominal cash-flows (assumptions about
expected price trends have to be stated
explicitly ) - for determining the applicable discount rate,
the guidance recommends that the interest rate
should be derived from the yield curve. In
principle, using an average (nominal interest
rate) is possible. - sensitivity and scenario analyses
- separate assessment of individual risks
(determination of so-called security
equivalents and payment equivalents)
30Public Sector Comparator
- Sum of all risk adjusted costs of and, where
applicable, proceeds of conventional procurement - Only those approaches that have already been
implemented, or at least decided on, may be taken
into account This requirement continues to be
controversial. - The PSC needs to be adapted if framework
conditions change e.g. if there is a change in
risk allocation.
31PPP Costs
- Reliable estimates of the costs of implementing
the PPP project as planned - PROBLEM
- How do I arrive at a reliable estimate with a
reasonable input of resources - Approaches used in practice include
- Back-tracking method
- Method of complete financial plans
32Further discussion points
- Remanent costs (the guidance calls for
allocation of remanent costs to the PPP
model). - However, this requirement is controversial
- Treatment of tax effects? (The guidance says
the project-executing agency has to decide - whether and to what extent direct tax effects
are - taken into account).
- appropriate remuneration for risks
(risk-adjusted - cash-flow vs. risk adjusted interest rates)
33 Final investment appraisal
- Demonstration of the efficiency of a PPP solution
at the end of the procurement process. The PSC
is the yardstick for evaluating the bids from the
private sector. - Prerequisites for juxtaposition and
comparability - uniform performance and quality standard
- uniform project duration
- risks are taken into account
- Where necessary, adjustment of the PSC but
optimisation from private sector bids must not be
adopted into PSC!
34Status of implementation
-
- In 2006 the Federal Government and the
German states decided to recommend using guidance
as a non-binding minimum requirement. -
-
35Conclusions and Outlook
- An important step towards standardisation has
been taken. The guidance provides those
responsible with methodological and substantive
assistance enabling them to develop sound and
reliable statements about PPP project efficiency. - Application of the guidance in practice ?
- Evaluation of the lessons learnt by
using the guidance in the course of
an audit is planned by the German SAI for
2009. The guidance will be the yardstick for
the audit but it is not considered
sacrosanct and unchangeable.