Transparency 1

1 / 35
About This Presentation
Title:

Transparency 1

Description:

The PPP Acceleration Act reduces re-quirements in the fields of procurement ... Remanent costs (the guidance calls for allocation. of remanent costs to the PPP model) ... – PowerPoint PPT presentation

Number of Views:34
Avg rating:3.0/5.0
Slides: 36
Provided by: brh7

less

Transcript and Presenter's Notes

Title: Transparency 1


1
PPP in Germany
  • Political framework

Coalition agreement of 11 November 2005
Component of the Federal Governments innovation
initiative
2
Objectives
  • Key objective
  • Deliver public services more efficiently

3
Subordinate objectives
  • Improve legal framework
  • The PPP Acceleration Act reduces re-quirements
    in the fields of procurement law, tax law, law
    on public fees and budgetary law and the
    Investment Act.
  • The PPP Simplification Act is being prepared to
    further simplify the legal framework.

4
Subordinate objectives
  • Meet quantitative targetsincrease the portion
    of PPP in the total of public investments to 15
    in the medium term
  • Provide central guidancee.g. in the form of
    manuals and specimen contracts (cf. transparency
    5)
  • Setting up centres of competence (cf.
    transparency 6)

5
Guidance and manuals
  • Guidance on PPP in the construction of public
    buildings with manual
  • Guidance on PPP and the law on government
    grants with manual
  • Manual on investment appraisals
  • Manual on procurement law

6
Centres of competence
7
Number of projects
  • 46 PPP projects in public building
    construction Total capital expenditure of
    about 1.4 billion
  • A further 120 projects for the construction of
    public buildings are being prepared Total
    capital expenditure of about 6 billion
  • Majority of PPP projects at local government
    level Currently 39 projects for the
    construction of buildings at local authority
    level, 7 at federal state level

8
Examples at federal level
  • Federal Ministry of Defence
  • HERKULES (IT project)Military barracks in
    Munich
  • Federal Ministry of Transport, Building and
    Urban Development Build-Operate-Transfer
    contracts for the construction of buildings and
    roads

9
Facts from the German Institute of Urban
Affairs
  • Number of contracts in 2005 increased by 50
    compared to previous year due to expectations of
    enhanced efficiency and speeding-up effects
  • At local government level, average efficiency
    yields of 10 are achieved
  • Average capital expenditure at local government
    level 13-16 million per project
  • Average capital expenditure at federal/state
    level 70 million per project

10
Requirements of the external audit institutions
regarding PPP
  • Requirements of external audit institutions at
    federal and state levels (10 findings)
  • 1. In the case of PPP projects, debt-service
    expenditure (interest and debt repayment)
    are replaced by other re- curring expenditure
    and place a similar burden on future
    budgets. Only efficiency gains that impact the
    budget are capable of reducing the burden
    on the budget.
  • 2. Where the public sector cannot afford a
    project under conventional funding, it must
    not go through with such projects under
    alternative funding arrangements.

11
Requirements of the external audit institutions
regarding PPP
  • Only once the need for a project has been
    established, officials in charge may consider
    whether the project is suitable for PPP.
  • The efficiency of a project must have been proven
    in each individual case and over entire project
    duration (life-cycle approach).
  • Risks must be shared by the public sector and the
    private partner in a reasonable and efficient
    way.

12
Requirements of the external audit institutions
regarding PPP
  • The public sector must not circumvent procurement
    law by pursuing PPP projects.
  • The complexity of PPP projects requires
    particular focus on contractual arrangements.
    Inadequate contracts have a direct negative
    impact on project efficiency.
  • 8. The cost impact of PPP projects must be
    clearly presented in budgets for the entire
    contract duration. The burden on future budgets
    must be transparent.

13
Requirements of the external audit institutions
regarding PPP
  • Audit access by external audit institutions must
    be ensured.
  • At local government level, PPP projects are often
    similar to borrowing, which requires approval by
    the supervisory authorities in almost all German
    states. Federal and state governments should
    impose minimum standards for PPP projects.

14
Audit access rights and PPP
  • The public partners
  • Extensive audit access
  • The private partners
  • Audit access only where public budget funds are
    used
  • Therefore
  • Stipulate full audit access in the contract

15
Audit activities
  • Currently, the Bundesrechungshofs audit work
    focuses on defence and road construction
    issues.
  • However, most projects have not been underway
    long enough to evaluate effectively the
    lessons learnt or conclude on the potential
    efficiency and risks of the projects.
  • Any statements of principle have been derived
    from the risks identified in the cases audited

16
Audit results
  • Based on the lessons learnt with the HERKULES
    IT project, the Bundesrechnungshof has developed
    general recommendations on investment appraisals
    in connection with PPP projects
  • Investment appraisals for PPP projects must be
    carried out before committing funds and
    commencing contract-award procedures.
  • Any decisions about PPP projects must be preceded
    by a comprehensive evaluation of the Federal
    Governments relevant options. This evaluation
    must not be restricted by the annual expenditure
    ceilings.

17
Audit results
  • The valuation of the benefits of PPP must be
    designed so that the chosen priorities reflect
    the objectives of the PPP fully and
    transparently.
  • The risks of any alternative options have to be
    examined in detail and quantified where possible.
    Their impact on the decision-making process needs
    to be illustrated.

18
Audit results
  • Further lessons learnt from auditing the PPP
    sector can be found in the cross-boundary annual
    report item on investment appraisals / efficiency
    studies in the federal administration
  • Sometimes, the authorities responsible for
    planning the PPP projects have
  • based their decisions on assumptions and
    forecasts going
  • beyond a realistic conservative estimate of
    future
  • development
  • subsequent costs, especially personnel costs
    that cannot
  • be cut immediately, were taken into account
    inadequately or
  • not at all

19
Audit results
  • used incomplete data, especially in evaluating
    optimised purely public-sector solutions
  • focused on intended benefits to the detriment of
    the quantitative results of the investment
    appraisal
  • in their appraisals stated the impact of
    potential risks in qualitative terms only
  • during the operational phase of project, failed
    to adapt their investment appraisals to changing
    conditions.

20
Findings of the Bavarian State Court of Audit
  • No cost benefits found for road works PPPs
    compared to conventional procurement!

21
Consequence
  • Decisive justification for PPP from the point of
    view of external audit institutions obtaining
    efficiency yields
  • For each individual project, an
    efficiency yield must be proven by means
    of a transparent, full and appropriate
    investment appraisal.

22
Efforts to achieve nation-wide uniform approach
  • ACTING PARTIES
  • Joint working group of the Federal Government
    and the
  • states
  • OBJECTIVE
  • nation-wide uniform (minimum) standards for
    investment
  • appraisals
  • setting up uniform terms and techniques and
    thereby
  • reduce the transaction costs incurred
  • continuous further development with regard to
    lessons learnt in practice

23
Principles
  • uniform project definition
  • practical procurement situation
  • figures are based on reliable estimates
  • risk assessment
  • tax impact considered
  • quantitative investment appraisal on the basis of
    discounted cash-flows

24
Stages of the PPP procurement process
Stages of PPP procurement process
Stages of the PPP-related investment appraisal
Stage I
Levels of detail and precision of the data
available increases
Stage II
Stage III
Stage IV
25
Stages of the investment appraisal
  • Stage I
  • Determining project efficiency
  • Test for PPP suitability
  • Stage II
  • Calculation of the public sector comparator
  • Estimate of PPP costs
  • Stage III
  • final comparison of the bids received with the
    PSC
  • If PSC gt present value of the PPP-solution,
    award contract to the
  • successful bidder and signing of contract.
  • Stage IV
  • project controlling

26
Project efficiency
  • Analysis of potential advantages and
    disadvantages of the planned project from a
    macro-economic perspective
  • If advantages are found to prevail
  • Identification of the procurement option that
    provides best value for money

27
Test for PPP suitability
  • QUESTION
  • Does the planned project meet pre-defined
    requirements which, based on the lessons learnt
    from previous projects, have proven essential
    for the success of a PPP solution.
  • EVALUATION CRITERIA
  • project volume
  • legal and / or project-specific restrictions
  • structure of project risks
  • remuneration mechanism
  • specifications
  • interest of market participants
  • market structure
  • DIFFICULTIES
  • little concrete information about the project is
    available at this time

28
Preliminary investment appraisal
  • Analysis of the economic benefit of the PPP
    before opening the contract-award procedure.
  • Comparison of estimated PPP cost and
    the PSC

29
Methodology
  • type of investment appraisal based on assessing
    discounted cash-flows (net-present-value
    method)
  • for projects having an overall economic impact
    cost-benefit analysis
  • qualitative aspects can be evaluated by means of
    utility analysis
  • use of nominal cash-flows (assumptions about
    expected price trends have to be stated
    explicitly )
  • for determining the applicable discount rate,
    the guidance recommends that the interest rate
    should be derived from the yield curve. In
    principle, using an average (nominal interest
    rate) is possible.
  • sensitivity and scenario analyses
  • separate assessment of individual risks
    (determination of so-called security
    equivalents and payment equivalents)

30
Public Sector Comparator
  • Sum of all risk adjusted costs of and, where
    applicable, proceeds of conventional procurement
  • Only those approaches that have already been
    implemented, or at least decided on, may be taken
    into account This requirement continues to be
    controversial.
  • The PSC needs to be adapted if framework
    conditions change e.g. if there is a change in
    risk allocation.

31
PPP Costs
  • Reliable estimates of the costs of implementing
    the PPP project as planned
  • PROBLEM
  • How do I arrive at a reliable estimate with a
    reasonable input of resources
  • Approaches used in practice include
  • Back-tracking method
  • Method of complete financial plans

32
Further discussion points
  • Remanent costs (the guidance calls for
    allocation of remanent costs to the PPP
    model).
  • However, this requirement is controversial
  • Treatment of tax effects? (The guidance says
    the project-executing agency has to decide
  • whether and to what extent direct tax effects
    are
  • taken into account).
  • appropriate remuneration for risks
    (risk-adjusted
  • cash-flow vs. risk adjusted interest rates)

33
Final investment appraisal
  • Demonstration of the efficiency of a PPP solution
    at the end of the procurement process. The PSC
    is the yardstick for evaluating the bids from the
    private sector.
  • Prerequisites for juxtaposition and
    comparability
  • uniform performance and quality standard
  • uniform project duration
  • risks are taken into account
  • Where necessary, adjustment of the PSC but
    optimisation from private sector bids must not be
    adopted into PSC!

34
Status of implementation
  • In 2006 the Federal Government and the
    German states decided to recommend using guidance
    as a non-binding minimum requirement.

35
Conclusions and Outlook
  • An important step towards standardisation has
    been taken. The guidance provides those
    responsible with methodological and substantive
    assistance enabling them to develop sound and
    reliable statements about PPP project efficiency.
  • Application of the guidance in practice ?
  • Evaluation of the lessons learnt by
    using the guidance in the course of
    an audit is planned by the German SAI for
    2009. The guidance will be the yardstick for
    the audit but it is not considered
    sacrosanct and unchangeable.
Write a Comment
User Comments (0)