Title: ENGINEERING 100W Energy Conservation at SJSU
1ENGINEERING 100WEnergy Conservation at SJSU
- 02/15/08
- Jared Isaacson
- Energy Analyst
- FDO/EUE
2Content
- SJSU Energy Use
- UC/CSU/IOU Partnership
- Monitoring Based Commissioning (MBCx)
- Background
- MBCx completed at SJSU
- Current Energy Program
- Labs21/Green Campus programs
3Energy Delivered to Campus by Central Plant in
2007
4Engineering Building Energy Use
5Student Union Energy Use
- Example of metered data
- Chart
- EXCEL file
6UC/CSU/IOU
Energy efficiency measures implemented by the UC
and the CSU systems, in collaboration with CAs 4
IOUs PGE, SCE, SoCal Gas, SDGE 04/05
savings 32 million kilowatt hours 1.5
million therms of gas This is the most
successful energy efficiency program serving the
higher education sector. In fact, the program was
designed and implemented to not only achieve
sustained energy savings, but also influence
energy policy in education institutions
nationwide, said Len Pettis, CSUs Chief of
Plant, Energy and Utilities. Funded by CA
utility customers and administered by CAs IOUs
under the auspices of the CPUC. Ex Gas PPP
surcharge on PGE bill
7MBCx
- Monitoring Based Commissioning (MBCx)
- Element of UC/CSU/IOU Program
- Commissioning Process
- Ensure optimal building performance
- Reduce Energy Use
- Improve Indoor Air Quality
- Improve occupant comfort productivity
8MBCx Process
- Combines expertise of Facilities FDO
management staff, Utility and Contractors - Components
- Energy Information Systems/Building Diagnostics
- CEMCS/HVAC and Metering
- Facility Retro-Commissioning
- Commissioning of existing building for efficiency
- Continuous Commissioning
- M V, Training/Education lasting savings
9Completed SJSU MBCx
10SJSU Energy Program
- Engineering Building Improvements
- MBCx Potential Savings
- 12,111 therms of steam
- 930,170 kWh
- Valued at 161,786 Annually
- The Engineering Building is a four-story building
situated in the North-East Quadrant of campus,
fronting San Fernando Street. The 334,000 ft2
facility was constructed in two phases, the
initial phase (Engineering Phase 1) was
constructed in 1962, and an expansion phase
(Engineering Phase 2) was constructed in 1989.
Phase 1 contains classrooms, lecture halls and
civil engineering labs with wave tanks and
materials testing areas. Phase 2 has classrooms
and mechanical and electrical engineering labs
including a large semi-conductor lab, and
multiple, large computer labs on the 3rd floor,
the building also has numerous computer rooms and
process cooling equipment throughout. The
building is provided with major facilities
related to unknown lab use including (3) 100 HP
air compressors dedicated to lab services, 12MVA
of installed transformer capacity, a wet chemical
exhaust scrubber serving a clean-lab with known
general exhaust connections to the scrubber, a
process cooling loop with a 250 ton crossflow
cooling tower serving marginal lab process water
in Phase 2. - Building energy usage was developed as part of
the several utility system master planning
projects. The baseyear energy use of the building
is fiscal year 05/06, and is 4,716,716 kWh/yr,
1,016,240 Ton-Hr/yr, and 176,144 Therms/yr.
Because of the incomplete information at this
time it's not feasible to apply the Labs21
Benchmark tool therefore, the early benchmark
shall be the CalArch benchmarking tool which
indicates the Energy Intensive Units (EIU) are
138 kBtu/ft2-yr. The buildings EIU's as
benchmarked against "Educational", and
"Industrial Processing/Manufacturing" are 67,
and 50 higher then the facilities registering
with the database.
11Engineering MBCx
- VAV boxes
- Tune and calibrate
- Variable Air Volume
- Pumps are constant speed
- Propose installing VFD's
- Variable Frequency Drives adjustable speed for
pumps electric motors
12ENG HVAC description
- Building is dual duct VAV with 300 mixing boxes
and DDC thermostats and (3) 100 hp air
compressors for lab air. Building has Process
Cooling loop with BAC VNT 500 ton cooling tower
running 24/7 without control. Building has 12 MVA
of 4.16 and 12 KV transformers, all energized
with no way to tie busses together and a maximum
demand of 500 kW measured over the last 3 years.
Building originally housed 2000 tons of chillers
that have since been moved to central plant.
Building has lighting controls that have been
defeated due to occupant complaints of lamps
being "out". MBCx activities will seek to tune
and calibrate boxes and eliminate pneumatics
where feasible. Building has process cooling
towers with minimal lab usage. Pumps are constant
speed, propose installing VFD's.
13Labs 21
- Goal development of sustainable, high
performance, and low-energy laboratories - Set measurable energy and environmental
performance goals - Benchmark the energy and environmental
performance of your facility - Share energy and environmental performance
results - Report project results