ENGINEERING 100W Energy Conservation at SJSU - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

ENGINEERING 100W Energy Conservation at SJSU

Description:

Energy efficiency measures implemented by the UC and the CSU ... MBCx activities will seek to tune and calibrate boxes and eliminate pneumatics where feasible. ... – PowerPoint PPT presentation

Number of Views:76
Avg rating:3.0/5.0
Slides: 14
Provided by: sjsu
Category:

less

Transcript and Presenter's Notes

Title: ENGINEERING 100W Energy Conservation at SJSU


1
ENGINEERING 100WEnergy Conservation at SJSU
  • 02/15/08
  • Jared Isaacson
  • Energy Analyst
  • FDO/EUE

2
Content
  • SJSU Energy Use
  • UC/CSU/IOU Partnership
  • Monitoring Based Commissioning (MBCx)
  • Background
  • MBCx completed at SJSU
  • Current Energy Program
  • Labs21/Green Campus programs

3
Energy Delivered to Campus by Central Plant in
2007
4
Engineering Building Energy Use
5
Student Union Energy Use
  • Example of metered data
  • Chart
  • EXCEL file

6
UC/CSU/IOU
Energy efficiency measures implemented by the UC
and the CSU systems, in collaboration with CAs 4
IOUs PGE, SCE, SoCal Gas, SDGE 04/05
savings 32 million kilowatt hours 1.5
million therms of gas This is the most
successful energy efficiency program serving the
higher education sector. In fact, the program was
designed and implemented to not only achieve
sustained energy savings, but also influence
energy policy in education institutions
nationwide, said Len Pettis, CSUs Chief of
Plant, Energy and Utilities. Funded by CA
utility customers and administered by CAs IOUs
under the auspices of the CPUC. Ex Gas PPP
surcharge on PGE bill

7
MBCx
  • Monitoring Based Commissioning (MBCx)
  • Element of UC/CSU/IOU Program
  • Commissioning Process
  • Ensure optimal building performance
  • Reduce Energy Use
  • Improve Indoor Air Quality
  • Improve occupant comfort productivity

8
MBCx Process
  • Combines expertise of Facilities FDO
    management staff, Utility and Contractors
  • Components
  • Energy Information Systems/Building Diagnostics
  • CEMCS/HVAC and Metering
  • Facility Retro-Commissioning
  • Commissioning of existing building for efficiency
  • Continuous Commissioning
  • M V, Training/Education lasting savings

9
Completed SJSU MBCx
10
SJSU Energy Program
  • Engineering Building Improvements
  • MBCx Potential Savings
  • 12,111 therms of steam
  • 930,170 kWh
  • Valued at 161,786 Annually
  • The Engineering Building is a four-story building
    situated in the North-East Quadrant of campus,
    fronting San Fernando Street. The 334,000 ft2
    facility was constructed in two phases, the
    initial phase (Engineering Phase 1) was
    constructed in 1962, and an expansion phase
    (Engineering Phase 2) was constructed in 1989.
    Phase 1 contains classrooms, lecture halls and
    civil engineering labs with wave tanks and
    materials testing areas. Phase 2 has classrooms
    and mechanical and electrical engineering labs
    including a large semi-conductor lab, and
    multiple, large computer labs on the 3rd floor,
    the building also has numerous computer rooms and
    process cooling equipment throughout. The
    building is provided with major facilities
    related to unknown lab use including (3) 100 HP
    air compressors dedicated to lab services, 12MVA
    of installed transformer capacity, a wet chemical
    exhaust scrubber serving a clean-lab with known
    general exhaust connections to the scrubber, a
    process cooling loop with a 250 ton crossflow
    cooling tower serving marginal lab process water
    in Phase 2.
  • Building energy usage was developed as part of
    the several utility system master planning
    projects. The baseyear energy use of the building
    is fiscal year 05/06, and is 4,716,716 kWh/yr,
    1,016,240 Ton-Hr/yr, and 176,144 Therms/yr.
    Because of the incomplete information at this
    time it's not feasible to apply the Labs21
    Benchmark tool therefore, the early benchmark
    shall be the CalArch benchmarking tool which
    indicates the Energy Intensive Units (EIU) are
    138 kBtu/ft2-yr. The buildings EIU's as
    benchmarked against "Educational", and
    "Industrial Processing/Manufacturing" are 67,
    and 50 higher then the facilities registering
    with the database.

11
Engineering MBCx
  • VAV boxes
  • Tune and calibrate
  • Variable Air Volume
  • Pumps are constant speed
  • Propose installing VFD's
  • Variable Frequency Drives adjustable speed for
    pumps electric motors

12
ENG HVAC description
  • Building is dual duct VAV with 300 mixing boxes
    and DDC thermostats and (3) 100 hp air
    compressors for lab air. Building has Process
    Cooling loop with BAC VNT 500 ton cooling tower
    running 24/7 without control. Building has 12 MVA
    of 4.16 and 12 KV transformers, all energized
    with no way to tie busses together and a maximum
    demand of 500 kW measured over the last 3 years.
    Building originally housed 2000 tons of chillers
    that have since been moved to central plant.
    Building has lighting controls that have been
    defeated due to occupant complaints of lamps
    being "out". MBCx activities will seek to tune
    and calibrate boxes and eliminate pneumatics
    where feasible. Building has process cooling
    towers with minimal lab usage. Pumps are constant
    speed, propose installing VFD's.

13
Labs 21
  • Goal development of sustainable, high
    performance, and low-energy laboratories
  • Set measurable energy and environmental
    performance goals
  • Benchmark the energy and environmental
    performance of your facility
  • Share energy and environmental performance
    results
  • Report project results
Write a Comment
User Comments (0)
About PowerShow.com