NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE

Description:

Cable Technology Pipe-Type Cable, Over 200 miles in Greater Boston Area ... Pipe-type Cable, Proven Reliable Technology at 345 kV. New Switchyard at Origin-Stoughton ... – PowerPoint PPT presentation

Number of Views:107
Avg rating:3.0/5.0
Slides: 13
Provided by: nst59
Category:

less

Transcript and Presenter's Notes

Title: NSTAR TRANSMISSION RELIABILITY PROJECT ENVIRONMENTAL BUSINESS COUNCIL UPDATE


1
NSTARTRANSMISSION RELIABILITY
PROJECTENVIRONMENTAL BUSINESS COUNCIL UPDATE
APRIL 21, 2005
2
PROJECT NEED DRIVEN BY INCREASING GROWTH WITH
DECLINING GENERATION
  • Load Growth over Past 6 Years Exceeded Historic
    Average In Greater Boston Area Communities
  • Area Older Some Newer Generation Stations Have
    Retired or Announced Plans to Retire
  • By June 2006, System Overloads Are Experienced
    throughout the System without Relief
  • Overloads Get Worse with Time, Lead to Outages

3
GOAL WAS TO FIND MOST COST-EFFECTIVE
ALTERNATIVE TO MINIMIZE IMPACT ON NATURAL HUMAN
ENVIRONMENT
  • Type of Transmission LineUnderground
  • Cable TechnologyPipe-Type Cable, Over 200 miles
    in Greater Boston Area
  • Route Selected to be Most Direct with Least
    Impact to People Environment
  • Construction Impact Tried to Minimize
    Interferences

4
FINAL DESIGN
  • Three 345 kV Underground Transmission Lines
    Located in One Trench Up to Route Split
  • Pipe-type Cable, Proven Reliable Technology at
    345 kV
  • New Switchyard at Origin-Stoughton
  • Expand Two Termination Substations-Hyde Park K
    Street
  • Heat Exchangers at Baker Street Hyde Park
    Substations (Reverse Power Flow to W. Roxbury to
    Reinforce Area)

5
(No Transcript)
6
SUMMARY OF BENEFITS
  • Increases Import Capability into Greater Boston
    Surrounding Communities by 1200-1800MW
  • Mitigates All Known Reliability Issues for More
    than 10 Years
  • Reduces Dependence on Older Local Generation
    Stations that Plan to Retire
  • Opens Corridor for Economic Generating Sources
    from SEMA/RI into Greater Boston Area

7
PROJECT SCHEDULE OVERVIEW
Mar 2004
Planning Design
Apr 2005
Permitting Engineering
Jun 2006
Station Construction
Feb 2006
Street Construction
June 2006 In-Service

Install Splice Cable
Dec 2007 In-Service
Phase 1
Install Splice Cable
Phase 2
8
PROJECT STATUS
  • Major Permits Secured-MEPA, Siting Board, Con
    Coms
  • Most Follow-on Permits Completed, Some Still in
    Process
  • Chapter 91 License for K Street Station-DEP
  • Stoughton Conservation Commission Appeal to DEP
  • MOUs with Boston, Towns, DCR bound Mitigation
    Risk, Define Extended Works Hours
  • ISO-NE System Technical Issues Resolved (System
    Switching)
  • Major Equipment, Property, and Easements
    Acquisition Complete

9
PROJECT STATUS
  • Major Equipment Purchases Complete ISO
    Administered RFPs for high dollar items including
    Pipe-type cable and GIS Equipment
  • NSTAR/ISO issued Construction Contract RFP in Nov
    2004
  • Bid as Single GC for Entire Project or Separately
    for Lines Stations
  • Transmission Line Contract Awarded Station
    Contract in Final Negotiation

10
PERMITING PROCESS WAS INTENSE
  • EENF Filed 12/15/03 EFSB Petition Filed 1/16/04
  • MEPA Public Meetings Feb 04 EFSB Public Meetings
    Mar 04
  • NSTAR met with Boston Supplemented EFSB
    Petition with Additional Route Alternatives Mar
    04
  • Additional EFSB Public Meeting on New
    Alternatives April 04
  • 2 EFSB Interveners FiledISO-NE City of Boston
  • Siting Board Discovery followed by Intervener
    Discovery May 04
  • Submitted Single EIR to MEPA May 04
  • Unrest in Stoughton Led to Selectmens Meeting
    May 04
  • Stoughton Filed as Late EFSB Intervener June 04
    Hired Counsel
  • EFSB Accepted Stoughton as Intervener Stoughton
    Discovery Jul 04
  • Received MEPA Certificate July 16, 2004
  • EFSB Hearings began late July 04

11
PERMITING CONTINUED ON
  • EFSB Hearings Covered Each Section of Petition in
    Order
  • Initial Cross-Examination by Boston Stoughton
    Tapered Off as Hearings Progressed
  • NSTAR worked with Stoughton Counsel to Negotiate
    Agreement
  • Town Selectmen Rejected Proposed Agreement
  • NSTAR Testimony Concluded in Late Aug 04
  • Stoughton Presented Direct Case with
    Witnesses-Technical Environmental
  • Second Proposed Agreement with Town Approved
    Stoughton withdrew from Proceedings
  • Hearings Concluded Sept 04
  • Con Com Petitions filed Oct 04
  • Con Com Orders Received Dec 04 except Stoughton
    Jan 05
  • EFSB Tentative Decision Dec 04 Final Jan 14, 2005

12
NEXT STEPS
  • Final Permits/Licenses needed to Complete DEP
    is lengthy resource limited
  • Construction Contract in Place Shovels in the
    Ground
  • Community Relations Plan Developed, Ready for
    Implementation
  • Environmental Plan Ready for Implementation
  • Target Completion June 2006
Write a Comment
User Comments (0)
About PowerShow.com