Title: Claytor Hydroelectric Project Water Quality Study
1Claytor Hydroelectric ProjectWater Quality Study
Mark Hutchins, Project Manager January 25, 2007
2About Normandeau Associates, Inc.
- New Hampshire-based natural resources consulting
firm founded in 1970 - Employee-owned since 2001
- 13 fully-staffed offices nationwide
- Known for managing complex field and impact
assessment projects - Recognized as one of the largest natural resource
management companies in the U.S. (EBJ)
3Hydro Relicensing Services
- FERC Relicensing and Compliance
- Fish Passage
- Wetlands, Endangered Species Wildlife
- Water Quality Monitoring and Mitigation
- Instream Flow Studies
4Representative HydroPower Projects
- Dozens of Hydro projects throughout the U.S.
- Yadkin Relicensing (NC)
- Tapoco Relicensing (NC/TN)
- Santee Cooper Relicensing (SC)
- TVA Reservoir Operations Study EIS (35 dams, 6
states)
5(No Transcript)
6Claytor Lake Water Quality Study
- Study Goals
- Evaluate WQ within and downstream of Claytor Lake
- Determine how hydroelectric operations affect WQ
- Determine how hydroelectric operations could be
modified to improve WQ, if necessary - Study Methods
- Collect existing WQ data
- Collect new WQ data
- Characterize existing WQ conditions
- Recommend measures to enhance WQ, as appropriate
7Specific Study Objectives
- Objective 1 Assemble and Review Existing Data
- All recent (last 15 years) data immediately
upstream, within and downstream of Claytor Lake
will be retrieved. - Know data sources are state agencies, colleges
and universities and non-governmental agencies - QA/QC data
- VDEQ will determine data acceptability
8Specific Study Objectives
- Objective 8 Assess Adequacy of Existing Upriver
and Downriver Temperature Data - Evaluate existing VDGIF continuous temp data to
determine completeness, deficiencies and
additional data needs. - Modify field collection study plan, if
appropriate, to fill data gaps
9Specific Study Objectives
- Objective 4 Collect Additional WQ Data
- Sampling period generally, once weekly, June 15
to September 15 - Four locations inflow to Claytor Lake, lower
Claytor Lake, Claytor Dam tailrace and select
downriver locations - At an upriver mussel bed
- Temperature only
- Within Claytor Lake at three transects (forebay,
1km, 2km) - Sampling will occur at 4 equi-spaced locations
per transect - DO, temp, pH and conductivity by 1-meter vertical
profile - Chlorophyll a by field meter at one center
location per transect by 1-meter vertical profile - In Project tailrace continuous monitoring
- Sampling will occur at one well-mixed location
- DO, temp, pH and conductivity
- 3 downriver transects (Rt 11 bridge, upriver of
Plum Creek, Pembroke area) - Sampling will occur at each quarter point on each
transect in pre-dawn/early dawn hours - DO, temp, pH and conductivity by 1-meter profile,
if appropriate
10Specific Study Objectives
- Objective 2 Characterize Existing Study Area WQ
- Use existing and new collected WQ data
- Focus will be DO/temp, but other WQ parameters
will be included - Characterization will be 4 dimensional
longitudinal (Allisonia to Glen Lyn), horizontal,
vertical and temporal - Temporal focus will be spring, summer, early fall
11Specific Study Objectives
- Objective 7 Identify Impact of Project
Operations on Claytor Lake and Downriver WQ - Identify, where possible how peaking operations,
water level fluctuations, water residence times
and turbine intake zones affect reservoir and New
River WQ
12Specific Study Objectives
- Objective 3 Identify Measures that could Enhance
Downriver DO under Normal and Drought River Flow
Conditions - Determine the magnitude, frequency and duration
of low DO events downriver of the Project - Conduct a literature survey of methods used to
improve DO at hydroelectric facilities - Assess applicability to Claytor Lake
13Specific Study Objectives
- Objective 6 Determine Effects of Sediments on
Claytor Lake WQ - Conduct a literature review of activities that
may affect sediment/water/fish interactions - Review VDEQ fish tissue and sediment analyses
data - Assess relevance to Claytor Lake
14Specific Study Objectives
- Objective 5 Develop Protocols for Future WQ
Monitoring, as Appropriate - Identify remaining WQ data deficiencies
- Detail how future sampling efforts should be
undertaken, spatially and temporally, to
eliminate these deficiencies
15Project Deliverables
- Periodic Progress Reports
- Draft Information Report
- Final Information Report
- Weekly spreadsheets of new data to VDEQ
- Draft Final Report
- Final Report
16Schedule
- Progress Reports May, August and November 2007
- Draft Informational Report May 2007
- Final Informational Report June 2007
- Stakeholders Meeting May 2007
- WQ Sampling Program June 15-September 15, 2007
- Draft Final Report January 2008
- Stakeholders Meeting February 2008
- Final Report by May 30, 2008