The NAPOCOR - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

The NAPOCOR

Description:

The public sector debt stood at P 5.39 trillion during the third quarter of 2003. ... Source: Pascual, 'Contracted Power Failure', 2000. OBVIOUSLY ONEROUS ... – PowerPoint PPT presentation

Number of Views:159
Avg rating:3.0/5.0
Slides: 19
Provided by: dinoaesub
Category:
Tags: napocor | pascual

less

Transcript and Presenter's Notes

Title: The NAPOCOR


1
The NAPOCOR the Bataan Nuclear Power Plant
DebtsOdious Legacies of Power
  • Ana Maria R. Nemenzo
  • President, FDC

Freedom from Debt Coalition
2
Topic Outline
  • NAPOCOR the Public Debt Burden
  • Then The Bataan Nuclear Power Plant A Legacy
    of Fraud, Corruption and Odious Debt
  • Now The NAPOCOR and Onerous IPP Contracts -- A
    continuation of BNPP legacy

3
The NAPOCOR Debt
  • The public sector debt stood at P 5.39 trillion
    during the third quarter of 2003.
  • A significant portion of this debt comes from the
    National Power Corporation NPC. At end 2003,
    its audited financial statement showed P 1.17
    trillion in long-term debts and lease obligations
    to independent power producers IPPs. Current
    estimates put these debts and obligations at P1.4
    trillion, equivalent to about 20 of the
    consolidated public sector debt.
  • Of all of NAPOCORs debts, the Bataan Nuclear
    Power Plant loan assumed by the Aquino
    Government in 1986 and current contracts with
    Independent Power Producers are the most
    burdensome and onerous. And so our story begins...

4
Corruption fraud taint the BNPP debt project
  • The deal between Westinghouse and the Marcos
    government involved bribery, overpricing and
    subcontracting awards to Disini-Marcos companies
    during the plant construction I.e., Power
    Contractors, Inc. Summa Insurance Corp.,
    Technosphere
  • From 2 Feb. 1979 7 Sept. 1981 Westinghouse
    payments flowed into Disini holdings Herdis
    Management Interbank to the tune of
    5,949,580.16.
  • Originally quoted at 500 million each for two
    power plants, the project price would eventually
    be jacked up to 1.1 billion for one plant. When
    construction was completed in 1985, total project
    cost reached 2.2 billion because of escalating
    cost adjustments and additional costs due to
    safety corrections.

5
BNPP Public Assumption of Private Debts
  • The BNPP case is an early example of government
    assumption of what were clearly loans and
    obligations tainted with corruption and fraud.
  • In 1986, Marcos falls and flees. President
    Corazon Aquino mothballs the BNPP in April 30
    through a unanimous Cabinet decision.
  • However, in October of that year, she issues
    Executive Order 55 transferring BNPP foreign loan
    obligations assets from Napocor to the national
    government.
  • Finally, on October 15, 1995, the Ramos
    government finally agrees to settle with
    Westinghouse out of court.

6
The Public is still Paying the Assumed BNPP Loans
Today
  • The original BNPP loan was 1.084 billion.
  • By December 1988, the loan amounted to 2.67
    billion, accumulating interests and other
    add-ons.
  • Today, 28 years after construction began, the
    Filipino people are still paying the BNPP debt.
    Interest payments amounted to P496 million in
    2003, while principal payments amounted to P1.78
    billion for the same year. Source Bureau of the
    Treasury
  • The Filipino people will continue paying until
    year 2018 for the outstanding BNPP debt amounting
    to P6. 26 billion as of end-2003.

7
BNPP Creditor Complicity Irresponsible Lending
  • The U.S. Export Import EXIM Bank financed the
    project fully aware of Westinghouses overpricing
    and questions about the health, safety and
    environmental problems of the plant. It released
    project funds despite these questions, even when
    Westinghouse still had no license to export the
    nuclear plant to the Philippines.
  • March 1975 Westinghouse quoted 1.2 billion for
    one reactor. Then-EXIMBANK president William
    Casey later CIA director estimated the price
    for the reactor at over 1.6 billion.
  • September 1975 RP government applied for a loan
    with US EXIMBANK for one reactor costing 1.1
    billion 722 million 387 million for interest
    and escalating costs

8
Now Onerous IPP ContractsThe Story Begins
Again...
  • In 1986, Pres. Corazon Aquino abolishes the
    Ministry of Energy. Afterward, no government
    support is given to rehabilitate existing power
    plants and build new plants due to lack of fund
    to address the looming power shortage, Aquino
    signs EO 215 in 1987, opening power generation to
    the private sector that has the needed capital.
  • In the beginning of the 1990s, the country is hit
    by power shortages and frequent brown outs. This
    grew into a power crisis under Pres. Ramos who
    succeeded Aquino.
  • To address the power crisis, Ramos asked for and
    was given emergency powers. Under his
    Administration, NAPOCOR enters into expensive 10
    to 25-year contracts with independent power
    producers IPPs, most of which were signed
    during 1992-94.
  • NAPOCOR currently has 46 IPP contracts 13 were
    signed from May 1990 - April 1992 31 from
    September 1992 - November 1997 and, 2 in July
    November 1998. To date, 35 of these contracts are
    active while the rest were already expired or
    terminated.

9
OBVIOUSLY ONEROUS
  • Guaranteed income for IPPs, burden to the
    government and the consumers
  • Take or Pay Agreement Napocor promised to buy
    70-90 power (whether actually generated /
    utilized or not) of the total capacity of IPP
    plant. (Only 20-40 is actually generated).
  • Fuel Cost Guarantee Napocor will supply fuel to
    the IPP, and subsequently absorb any fluctuations
    in the cost of fuel.
  • Foreign Exchange Rate Guarantee All IPP
    contracts are in US dollars. NPC absorbs any
    dollar fluctuation.
  • Overpriced Power In 1996 average IPP generation
    cost was US76 per MWh, compared with US57 MWh
    for NPC.

Source Pascual, Contracted Power Failure, 2000.
10
Onerous IPP contracts the Magellan Cogeneration
Inc. case
  • MCI operated a coal-fired power plant and
    entered into power supply contract with the
    Cavite Export Processing Zone Authority (CEPZA)
    in June 1993. It also entered into an energy
    conversion agreement with NPC in September 1993.
    This last contract contained a take or pay
    provision.
  • CEPZA cancelled its contract with MCI in 2001 as
    the power plant no longer generated electricity.
    Instead of generating electricity, MCI was only
    buying cheaper power from NPC and delivering this
    to CEPZA. (MCI became a power trader, instead of
    power generator). The company is financially and
    technically incapable of delivering power. Its
    mother company in the United States meanwhile has
    filed for bankruptcy in April 2002.

11
Onerous IPP contracts the Casecnan Irrigation
and Power Project (year 2000-2020)
  • An unsolicited proposal in May 1994 from US
    company, CalEnergy (main project proponent), the
    project was able to obtain government guarantees.
  • Expensive Power US0.165/kwh equivalent to
    almost P9/kWh compared to NPCs hydropower
    costing less than P2 / kWh.
  • Expensive Water Delivery Fee The National
    Government through NIA pays more than P2 billion
    annually (as contingent liabilities, that become
    actual liabilities under NIA)
  • Government Guarantees / Risk Absorption The
    project proponents will receive at least 72.7
    million a year from the NIA and S36.4 million a
    year in energy fees from NPC, whether the project
    delivers the contracted volume of water or
    whether its power plant operates and generates
    electricity.

12
Onerous IPP contract Caliraya-Botocan-Kalayaan
- IMPSA
  • Although an unsolicited project, CBK-IMPSA was
    given government guarantee
  • IMPSA was never technically and financially
    qualified to undertake the CBK power project. It
    disregarded NEDA rules on government bidding.
  • The contract contains onerous provisions grossly
    disadvantageous to the government
  • Under the original agreement, the project should
    have started in 2004. But due to the supplemental
    agreement forged in 1998, the operation started
    earlier than scheduled. In 2002, NPC started
    shelling out US2 million.

13
Initial Results of Interagency Review Committee
for IPP Contracts
  • Of the 35 IPP contracts reviewed by the
    inter-agency review committee
  • Five 5 contain onerous terms i.e. Binga
    hydroelectric, MCI, Sual coal-fired, Casecnan,
    San Roque multipurpose project
  • Only six had no legal or financial issues
  • 24 had financial, remedial policy remedial
    financial issues and need to undergo further
    scrutiny by the departments of Justice and
    Energy, PSALM, and NEDA

14
Impact of NAPOCORS Onerous IPP Contracts
  • As consumers, Filipinos have to pay higher power
    rates.
  • NAPOCORs debts and guarantees to these IPPs add
    to the public sector debt, which we pay for as
    taxpayers.
  • The government sells bonds in behalf of NPC. In
    effect, government assumes NPC liabilities/maturin
    g obligations. The government is also the one
    paying for the interest of these bonds and other
    loans.
  • From 1999-2003, NG took over P44.5 billion of NPC
    debt (source The Deepening Crisis, a white
    paper by 11 UP Econ. Professors)

15
  • According to Manasan, in 2003-2004, the bulk of
    the public sector deficit was traced to NAPOCOR
    77 - 78
  • According to Rep. Andaya, NG-assumed debts by
    NAPOCOR will increase the targeted deficit of P
    197 billion by P 36 billion this year.

16
Thank you . . .
AUDIT ALL PUBLIC SECTOR DEBTS
17
Main Sources References
  • Republic of the Philippines National Power
    Corporation NPC v. Westinghouse Electric
    Corporation, Westinghouse International Projects
    Company and Burns and Roe Enterprises, Inc.,
    Affidavits in Support of Plaintiffs Memorandum
    of Points and Authorities, Volume I-II, CA No.
    88-5150 (US District Court New Jersey, 1988).
  • ______________ Complaint for Money Damages and
    Equitable Relief and Demand for July Trial, CA
    No. 88-5150 (US District Court New Jersey,
    1988). 
  • ______________ Plaintiffs Memorandum of Points
    and Authorities in Opposition to Defendants
    Motion to Stay Pending Arbitration, CA No.
    88-5150 (US District Court New Jersey, 1988). 

18
Main Sources References
  • ______________ Republic of the Philippines
    Answers and Objections to Defendant
    Westinghouses First Set of Interrogatories, CA
    No. 88-5150 (US District Court New Jersey,
    1988).
  • Freedom from Debt Coalition, Briefer on the
    Campaign on IPPs in the Philippines, September,
    2001.
  • Freedom from Debt Coalition, Power Sector
    Privatization in the Philippines Struggles and
    Challenges, 2003.
  • Rosario Manasan, Fiscal Reform Agenda Getting
    Ready for the Bumpy Ride Ahead, PIDS Discussion
    Paper Series No. 2004-26.
Write a Comment
User Comments (0)
About PowerShow.com