Tritium Recycle from Gaseous Illumination Devices - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

Tritium Recycle from Gaseous Illumination Devices

Description:

Tritium Recycle from Gaseous Illumination Devices – PowerPoint PPT presentation

Number of Views:209
Avg rating:3.0/5.0
Slides: 23
Provided by: LLN956
Category:

less

Transcript and Presenter's Notes

Title: Tritium Recycle from Gaseous Illumination Devices


1
Tritium Recycle from Gaseous Illumination Devices
Official Use Only
UCRL-PRES-234471
Robert J. Vellinger and J. Mark Mintz Lawrence
Livermore National Laboratory September 20, 2007
OFFICIAL USE ONLY This document contains
Circumvention of Statute Information. Further
dissemination authorized to U. S. Government
agencies and their contractors other requests
shall be approved by the Innovative Business and
Information Department, Lawrence Livermore
National Laboratory or higher DOE programmatic
authority.
LIMITED DISTRIBUTION NOT FOR PUBLIC
DISSEMINATION OR RELEASE UNTIL REVIEWED BY THE
LLNL OFFICE OF CLASSIFICATION AND EXPORT CONTROL
This work was performed under the auspices of the
U.S. Department of Energy by the University of
California Lawrence Livermore National
Laboratory under Contract No. W-7405-Eng-48. Lawre
nce Livermore National Laboratory, P.O. Box 808,
Livermore, CA 94551
Official Use Only
2
Facility History
  • Opened in 1958
  • Tritium RD major
  • focus until 1992
  • 1992 - 2002
    Downsizing, DD,
  • tritium recycle, limited RD, addition of
    actinide operations
  • 2002 present
  • Renewed emphasis on tritium operations (NIF
    support) and tritium recycle opportunities

LLNL Tritium Facility (B331)
3
B331 Interior
Offices
RMA Increment 1
RMA Increment 2
Walls Removed
Tritium recovery operations
131
143
134
Gas cart
Stacks Bldg.
Auxiliary Building
North
MBA 420
4
New Tritium Recycle Project Brings Increased
Recycle Capabilities to B331
  • Requestor Waste Management Technology Limited,
    initially AEA Technology, plc
  • U.K. company
  • Requested our assistance in tritium recovery from
    obsolete telephone dials
  • Technical parameters
  • 1.8 x 106 thin glass circular tubes mounted on
    plastic backing plates (GTLDs, see example)
  • 2 5 mCi/tube tritium (in gas phase)
  • Recovery methodology
  • Vacuum processing environment
  • GTLDs are crushed in a grinder operation
  • Released tritium pumped to storage u-bed
  • Contaminated residuals enter B331 LLW waste
    stream

5
Project Scope
  • Install 480V and 208 3-phase electrical utilities
  • Install gas piping and reroute drain and
    sprinkler lines
  • Install grinder unit and steel plate on floor
  • Install two gate valves on grinder unit (6 and
    20)
  • Install abort volume
  • Install HK HEPA filters for capture of grinder
    particulates
  • Install/connect vac pumps and gas
    clean-up/recovery cart
  • Install electronics racks for monitoring/control
    of grinder
  • Install instrumentation control wiring and
    equipment
  • Conduct Management Self Assessment and RA
  • Begin operational use of improved tritium
    recycling capability

6
GTLDs in Storage
7
GTLD Baskets
8
GTLDs in Storage in the B331
9
Gas Recovery Process Schematic
10
Commercial Grinder Unit
11
(No Transcript)
12
Abort Volume Line Drawing
13
(No Transcript)
14
(No Transcript)
15
(No Transcript)
16
(No Transcript)
17
Hazards and Controls
  • Gravity Mass Sources
  • Lifting
  • Motion Sources
  • Mass-in-motion
  • Chemical Sources
  • Radioactive materials - tritium

18
Safety Basis Documentation
  • WFO Contract conditionally approved on September
    14, 2005
  • NEPA approved on November 4, 2005
  • Contract was approved, funded and project kickoff
    meeting was held on March 9, 2006
  • USQ Status
  • 14 point letter approved by LSO on August 25,
    2006 (LSOAMTS 060100)

19
B331 Facility Interfaces
  • Tritium monitors will be installed in each room
    where dials are stored or processed
  • Electrical power will be provided to run
    equipment
  • Ventilation will be maintained negative to the
    hallway in rooms where dials are stored
  • TESA locks may be put on doors to rooms to limit
    access
  • RMA yard area gate access will be maintained
    through TFM construction activity to allow
    moving/opening boxes in the yard

20
Drawings and Documents
  • Tritium inventory will be updated upon arrival of
    dials and then again as items are sent to LLW
  • Engineering drawings will be prepared for gas
    recovery system
  • B331 Work Permit will be prepared to approve this
    activity under B331 work control process
  • Procedures will be written for operation of the
    grinder unit
  • Activity will be added to B331 WAL
  • FORR will be prepared documenting authorization
    to begin process
  • OSP may be prepared to support ongoing operations

21
Project Schedule
  • Schedule
  • We are currently installing equipment for our new
    capability in the tritium facility
  • Once installation and set-up of equipment is
    completed we will conduct an internal Facility
    Operational Readiness Review (FORR)
  • We expect to begin tritium recycling operations
    by 12/1/07
  • We plan to complete WMT tritium recycling
    operations by 3/30/09

22
Interested in Tritium Recycle/Recovery?
  • Please contact us
  • Rob Vellinger at vellinger1_at_llnl.gov, (925)
    422-7382, or
  • Mark Mintz at mintz1_at_llnl.gov, (925) 422-8394
Write a Comment
User Comments (0)
About PowerShow.com