Title: National eCrime Programme Structure


1
National e-Crime Programme Structure
2
Programme structure
Strands within the e-Crime Portfolio
ACPO e-Crime Portfolio DAC Janet Williams
Strands
Strands
ACPO e-Crime Committee
Training, Recruitment Retention
Central / Regional e-Crime Structure
Forensics
Research Development
Prevention
Regional e-Crime Units
Olympics
Legal Issues
Increasing Knowledge for Action (SOCA Programme 7)
3
Programme structure
Programme structure
ACPO e-Crime Portfolio DAC Janet Williams
ACPO e-Crime Committee
Training, Recruitment Retention
Central / Regional e-Crime Structure
Forensics
Research Development
Prevention
Regional e-Crime Units
Olympics
Legal Issues
Increasing Knowledge for Action (SOCA Programme 7)
4
Strategic Group
  • The Programme Board assists the Programme Sponsor
    in periodically reviewing the progress the
    programme (and its constituent projects) is
    making to meet its objectives.
  • The Programme Board is not a committee controlled
    by voting, as the Sponsor is ultimately
    responsible for the success of the programme.
  • The Programme Board supports her in achieving
    this, and provides a forum for the principal
    stakeholders to discuss and resolve strategic
    issues.

5
Roles Responsibilities
Programme Governance National e-Crime Programme
Board
Sponsor / SRO DAC Janet Williams
  • Take overall responsibility for ensuring that the
    programme achieves its objectives / benefits
  • Provide leadership throughout the life of the
    programme
  • Monitor and control business change at a
    strategic level
  • Top-level stakeholder endorsement of the
    rationale and objectives of the programme
  • Oversight on budget decisions
  • Review progress towards achieving the Vision
  • Review strategic risks and issues, and assist the
    SRO in addressing these

Project Team Leaders / Project Managers
  • Take individual responsibility for leading a
    Strand of work within the Programme
  • Develop Strand strategy and plans
  • Identify projects required within the Strand
  • Gain approval and funding for projects from the
    Programme SRO and Programme Board
  • Initiate, monitor and control approved projects
  • Leading, directing and motivating the project
    team on a day-to-day basis
  • Planning and monitoring progress
  • Identifying and managing risks and issues
  • Liasing with related projects to ensure alignment
  • Reporting progress to the Strand Lead and SRO