Title: A
1ORISSA ELECTRICITY REGULATORY COMMISSION
Together, let us light up our lives.
A Presentation on ARR Tariff Proposal of
SOUTHCO for FY 2007-08 Broad Suggestions/Objecti
ons Feburary 9, 2007
2Data Sources
- As stated by SOUTHCO
- The Accounts up to September 2005 have been
audited as per Companies Act - The accounts up to March 2006 have been audited
as per Income Tax Rules - It has relied upon the audited accounts upto
September 2005 as per Companies Act and accounts
upto March 2006 as per Tax Audit for preparation
of ARR
3(No Transcript)
4(No Transcript)
5Tariff Structure
- SOUTHCO has proposed
- No change in tariff structure
- No special tariff should be allowed to the
industries having own CPPs - Demand charge of Rs 200/- per KVA to be
applicable for consumers having contract demand
70 KVA and above under HT Industrial (M) and GP
category - The provisions of tariff applicable to large
industries should be made applicable to above
consumers. - Fixed charges for LT Industrial(S), LT
Industrial(M) PWW to be levied on KVA in place
of KW. - Demand charges _at_ 120 of demand charges to be
made applicable on MD recorded along with
applicable energy charges for CPPs
6Tariff Structure .. Contd..
- The minimum demand charges concept i.e. 80 of
CD should not be made applicable to CPPs - Service connection charges for single phase
Domestic / GP consumers upto 3 KW load to be
revised from Rs 500/- to Rs. 1000/-. - The rate of labour component to be taken by the
consumers equivalent to Rs. 400/-where single
phase consumers come forward and provide service
connection materials. - Monthly minimum fixed charges for consumers with
contact demand lt 100 KVA should be levied on CD
or MD whichever higher
7Tariff Structure .. Contd..
- Tariff for medium industries (LT) may be
considered at par with GP (LT)category. - The over drawl energy should be considered in
cumulative basis for all DISTCOs together instead
of considering DISTCO wise over drawl till to
Intra-State ABT is implemented. - Rebate _at_ 2 for payment of BST bills within three
working days from the date of presentation of
bill. - Delayed Payment Surcharge to be levied to LT
industrial (Small) supply category. - Bridge the Revenue Gap through combination of
increase in Retail Supply Tariff, Reduction in
Bulk supply Tariff, Government Subsidy etc.
8Reconnection Charges
9BROAD TARIFF RELATED ISSUES RAISED BY OBJECTORS (
To be addressed by the Licensees )
10Legal Issues
- The ARR application filed by the licensee is not
tenable under law due to the following defects - The licensees account has not been audited for FY
2004-05 and 2005-06. - The licensee has filed the application to confuse
the consumer public without disclosing the
purpose for such filing. - The interested persons are being kept in dark and
not able to file effective objection and as such
the purpose of such exercise has been frustrated
and contrary to law and principle of natural
justice. - The procedure/method so adopted by the Commission
be made simple and inexpensive. - The licensee has failed to provide details as
required under regulations to the Commission for
consideration of his application as such the
application may be rejected.
11Issues raised by Objectors
- Military Engineering Services
- There should be discriminatory Tariff between
consumers of general category and of the defence. - Distribution Loss
- The licensee has miserably failed to arrest high
Distribution loss on account of unauthorized use
of power. - Distribution loss should be calculated by taking
ratio of units lost in distribution system
excluding EHT sale. - Since, a large chunk of consumers are still
unmetered and having defective meters, the
declared loss by the licensee is unrealistic. - Collection Efficiency
- The consumers are not to be burdened for
in-efficiency of licensees to collect their
energy dues from consumers every year.
12Issues raised by Objectors.. Contd..
- ATC Loss
- ATC concept should not be implemented as it
hides the inefficiency of the Licensee. - Power Factor Incentive/ Power Factor Penalty
- Power Factor incentive has to be calculated upto
two decimal fraction - Power factor penalty is levied for power factor
less than 90 power factor incentive should be
given for power factors above 90 at the same
rate. - Power factor penalty for the small and medium
industry consumer may be introduced. - Cross Subsidy
- Bench Marks for gradual reduction of cross
subsidy may be fixed from this year to achieve
Zero level by 2009-10.
13Issues raised by Objectors.. Contd..
- Quality of Services
- The industries are put to financial burden for
being unable to achieve 80 Load Factor due to
the inability of the licensee to supply proper
quality power. - Due to slow up gradation of the system and
sub-station, the new industries are finding
difficult to get power connection. - Voltage/frequency fluctuation The accountability
should be fixed with the License in terms of
financial compensation for the fluctuation beyond
standard norms.
14Issues raised by Objectors.. Contd..
- Consumer Classification
- Electricity tariff for poultry may be at par with
agriculture. - The State Government has decided to classify
poultry as agriculture - Reliance Telecom Ltd. and Reliance Infocomm Ltd.
- Electricity energy may be charged at
Industrial Rates instead of General Purpose
rates to the IT ITES Industries operating in
the State - BSNL Orissa Circle, Bhubaneswar
- BSNL may be treated as an industrial undertaking
as power is substantially utilized as motive
force for Industrial purpose and without supply
of power it is not possible to run the Telecom
services. - The BSNL is coming under the purview of industry
as per the verdict of the Honble Supreme Court
in several cases. - So also as per the finance Act, 2002 w.e.f.
01.4.03, the business of providing
Telecommunication Services has been declared as
industrial undertaking.
15Issues raised by Objectors.. Contd..
- Financial Issues
- In absence of the audited balance sheet and
report of the auditors it is not possible for the
objector to make proper observation on financial
matters. - Interests attributable to bonds
- The interest attributed to bonds against arrear
of power purchases cost and capital value of
bonds are not payable by consumers.
16Issues raised by Objectors.. Contd..
- Interests towards securitization
- The interest towards securitization as well as
capital of securitization should not be passed on
to the revenue requirement for tariff proposes. - Infusing additional funds - The licensee may be
directed to infuse additional funds as may be
required to turn around the sector. - Regulatory assets - Any losses that the
distribution licensee likes to incur after
complying with the orders of the Commission, can
only be considered for the purpose of computing
the Regulatory Assets. - Employees cost - It is suggested that an increase
of about 6 over last years provision may be
allowed while fixing the employees cost for the
FY 2007-08. - Past Losses - Past losses should be paid through
tariff by consumers only if these losses have
been incurred due to reasons beyond the control
of licensee and in spite of licensee having
performed as per bench marks fixed by OERC.
17Issues raised by Objectors.. Contd..
- Computation of Load Factor
- Load factor or consumption ratio to be determined
on the basis of Maximum Demand recorded in the
meter in accordance with Regulation 2(y) of the
OERC Distribution (Conditions of Supply) Code,
2004. - It will be just and proper to calculate the load
factor on the basis of Maximum Demand or 80 of
the Contract Demand whichever is higher. - A lower load factor upto 50 may be prescribed
for the period of annual maintenance, which will
be jointly decided by the licensee and the
consumer. - The guaranteed load factor of 80 should be
determined on an annual basis. - Load factor may be computed separately for peak
and off peak hours and the overall load factor be
computed by integrating the above data. - The LF be calculated based on the actual period
of availability of unrestricted power supply
during the month. - The MD during the off peak hours should not be
considered for computing the LF.
18Issues raised by Objectors.. Contd..
- Tariff Issues
- The gap of electricity charges between high
consumption and low consumption should be reduced
to minimum level, which will discourage theft of
energy. - Contract Demand
- Time frame for reducing the contract demand may
not be imposed. - Provision for Rebate
- Seven clear days may be given from the receipt of
the bill to get the rebate on prompt payment.
19Issues raised by Objectors.. Contd..
- Emergency Supply to CPPs
- The proposal of demand charges for emergency
drawal to CPPs should be rejected. - Emergency power requirement for CPP/Generating
stations are very low and for short duration
only, it is not at all justified to propose
demand charges for emergency power to CPPs. - Rail-ways
- Adoption of single part tariff for Railway
traction. - Proper adoption of simultaneous maximum demand
for Railway traction supply. - Railway may be exempted from payment of Security
deposit. - Stipulation of penalty on power factor if it goes
below 0.85 as against 0.90. - Stipulation of incentive for improvement in power
factor above 0.85.
20Issues raised by Objectors.. Contd..
- Grant of relief to railways for power supply
interruption as well as poor quality of supply. - The tariff applicable to Railway Traction should
reflect the cost of supply without any cross
subsidy. - As far as supply to Railway Traction Sub-station
is concerned, the distribution companies are not
entitled to any wheeling charges as non of their
own asset is involved in the supply process. - Ignoring of maximum demand of TSSs during feed
extensions as Railways are constrained to extend
feed from adjacent TSS to the failed TSS zone. - The tariff clause for industrial colony
consumption should be applicable to Railway
colony.
21Issues raised by Objectors.. Contd..
- General Issues
- The additional costs actual or estimated on
account of the inefficiency/inability of licensee
should not be passed on to the consumers through
the tariff, either as a direct cost or a so
called Regulatory Asset. - Any cost due to additional power purchase, beyond
the allowable distribution loss should not be
included in the ARR of the licensee. - Increase in the reconnection charge no
justification. - The charges to the consumers should reflect the
cost to the licensee. - DPS for LT consumers no justification.
- A LT consumer loses the rebate of 10 p/kwh in a
month. Additional levy of DPS is thus unnecessary
and un reasonable.
22Issues raised by Objectors.. Contd..
- The demand charges may be calculated prorate if
the total of period of interruption (causing loss
of production due to interruptions) and the
pre-arranged shut downs availed on intimation, or
statutory power cuts, exceeds 60 hours in a moth. - The street light burning hours should be on
actual time i.e. for 10 hours a day. - The ceiling limit of 10 of total consumption for
the colony consumption should be waived - Electricity charges for the colony consumption
should be at per with domestic rate because the
electricity used in the colony is never used for
any industrial purpose. - Special tariff for running of FOUNDRY A special
tariff structure _at_50 of the existing tariff, may
be introduced for running of the furnaces.
23Issues raised by Objectors.. Contd..
- Demand charges
- The demand charges may be calculated on prorate
basis for the actual period of power
availability. - The demand charges may be exempted if there is
power interruption for more than 50 hours in a
month. - To have a uniform tariff for all consumers based
on commercial principle of cost plus benefit
basis. - Separate Tariff may be introduced for Specified
Public Purpose consumers under private sector
especially for Educational Institutions.
24Issues raised by Objectors.. Contd..
- Service Connection charges - It is suggested that
a realistic amount in place of Rs500/- may be
fixed so that the Licensee can procure quality
materials in time. - Uniform rate may be introduced for LT (domestic)
without any slab system. - Tariff Revision - The proposed tariff revision is
not at all desirable as there is no improvement
in services.
25Issues raised by Objectors.. Contd..
- OERC Regulations
- During the initial period of supply, which is
prescribed for five years, an Exit Clause should
be provided since the consumer has right to
choose its supplier. - Customers Security Deposit Consumers may be
permitted to furnish bank guarantee or to open
revolving letter of credit in favour of licensee
in lieu of security deposit as it becomes
extremely difficult for small and medium scale
industry to invest such huge sum for purchase of
power in cash. - Period of agreement The validity of power
agreement is presently 5 years, should be reduced
to 1 year in view of the changing market scenario
and fluctuating market demands.
26BROAD TARIFF RELATED ISSUES
27The following areas have not been adequately
addressed
- D.T. wise Energy Audit Consumer Indexing for
loss reduction - Spot Billing Collection for improvement of
Collection Efficiency - Repair Maintenance
- Arrear Collection Liquidation of power purchase
dues - Man power deployment ( Both Executive Non
Executive ) for reducing AT C Loss - Non Investment in system improvement for Quality
Supply
28(No Transcript)
29Revenue Requirement for 2007-08 ..Contd..
- Bifurcation of the amount towards cost of power
purchase and cost of transmission for FY 2007-08
has not been furnished. The same may be
submitted. - Actual expenditure against the above heads of
expenditure for first six months of FY 2006-07
has not been provided by the licensee. The same
may be submitted. - The reason for making higher provision in
employee cost of Rs.98.23 crore proposed for FY
2007-08 as against the approved amount of
Rs.68.18 crore for FY 2006-07 and Rs.61.22 crore
appeared in the tax audit report needs to be
justified. - The proposed rise in AG expenses for an amount
of Rs 20.72 crore for FY 2007-08 as against the
approved amount of Rs 10.88 crore for FY 2006-07
and Rs. 13.62 crore for the FY 2005-06 based on
Tax Audit reports needs to be explained. - Similarly, the quantum proposed for interest
amounting Rs.46.73 crore for FY 2007-08 is nearly
Rs.20 crore more than the approved amount of
Rs.26.77 crore for FY 2006-07 and nearly Rs. 25
crore more than the tax audited figure for the FY
2005-06. This needs to be explained. - It may be justified as to why the amortization of
regulatory asset and truing up of revenue gap
for the FY 2006-07 be allowed and if so how far
it is reasonable.
30RM Expenses of SOUTHCO (Rs. Cr.)
Note (i) Cause of declining expenditure in RM
?? (ii) Non utilisation of the approved amount
towards RM is affecting Quality of Supply
increasing interruption.
31Note Why the Gap Between the approved and actual
figures of various heads of expenditures have not
been adjusted in the Revenue Requirement filing ?
32Provision for Bad Doubtful Debt
33Miscellaneous Income SMD
- Miscellaneous Income
- At the time of determination of RST for 2006-07
for the purpose of computation of misc. income
the latest available audited data for FY 2003-04
was taken into consideration. Now, that audited
accounts for FY 2004-05 and accounts upto March
2006 as per tax audit are available and even
after deduction of DPS from the misc. income for
FY 2004-05 as per audited account is much higher
than what has been approved for 2006-07. - Determination of Simultaneous Maximum Demand
(SMD) - Whether increase/decrease in energy consumption
has got direct link with SMD. - Comments on the above subjects are invited for
determination of tariff.
34 Business Plan Vrs. ARR
- A comparison of figures in Business Plan and ARR
from FY 2004-05 to 2007-08 with regard to
Distribution Loss, Collection Efficiency and ATC
Loss, present two different sets of figures with
wide margins as follows
35SOUTHCO ARR FILING VRS BUSINESS PLAN
36Finance related issues
- Investment details have not been specified.
- Capital Works In Progress - capability of huge
investment proposal has not been justified. - Action plan for settlement and collection of
arrears outstanding with the consumers have not
been spelt out. - No Action Plan for establishment of Special
Police Station Special Court has been given
37Issue of Regulatory Assets
- National Tariff Policy on Regulatory Assets
stipulates - Pass through of past losses or profits should be
allowed to the extent caused by uncontrollable
factors. - The facility of a regulatory asset should be done
only as exception, and subject to the following
guidelines. - should only include natural causes or force
majeure conditions - Carrying cost of Regulatory Asset should be
allowed to the utilities - Recovery of Regulatory Asset should be time-bound
and within a period not exceeding three years at
the most and preferably within control period. - The use of the facility of Regulatory asset
should not be repetitive. - Does the claim of Licensee conform to the
National Tariff Policy? - Whether the past losses be treated as regulatory
asset and allowed in tariff along with carrying
charges? - Whether the interest cost an account of the
regulatory asset should be allowed to be
recovered as a pass through
38Average Revenue Billed (P/U) Vrs Actual as filed
by SOUTHCO in ARR filings
39(No Transcript)
40Thank You