Title: A Data Warehouse Roadmap for UC Berkeley
1A Data Warehouse Roadmap for UC Berkeley
- Suggested approach for developing and delivering
- Thom King, June, 2005
2Developing a Data Warehouse Roadmap
BusinessRequirements and Strategy
Impl. Project 1
Impl. Project 2
. . .
InitiateProject
On-going governance
Business Value Roadmap
Dataapplicationstechnologyorg/process
3Strategy Phase
IdentifyInterview team
Summarize interview results
traininterviewteam
Conduct business interviews
Opportunity prioritization meeting
Review with stakeholders
Conduct systems interviews
IdentifyInterviewees
Schedule interviews
Business Value Roadmap
4Resources for Strategy Phase
- Core Team
- Project leader
- Business analysis team
- Business analyst
- Interviewers
- Technical Team
- Systems analyst
- Data modeler
- (part-time project leader and 3 full-time
equivalent analysts can be staffed by as many as
5-6 people)
- Other Key Resources
- Executive interviewees(expect 5-8 interviews)
- Business area intervieweesanalysts subj. matter
experts(expect 5-10 interviews) - Systems experts
- (expect 6-8 interviews)
- Administrative systems
- Student systems
- Reporting systems
Expected Duration June-September, 2005
5Architecture Phase
Develop / Revise Query-pres Tech arch
Document Architecture Reqs Volumes, users,
Security, etc.
Summarize Required Changes
Develop Data Architecture
Document Warehouse Scope
Identify Skills / Training Needs
Develop BI/Query Apps Arch
Dev/revisesecurityarchitecture
Develop Fact/Dimension Data Matrix
Assess Existing Whse Capabilities Against Req.
Identify Interdependencies
Develop / Revise DB, ETL, metadatatechnology arc
hitecture
Reconcile wrequirements
Develop Implementation Strategy
SummarizeBI apps requirements
Document Gaps
Review w stakeholders
Scope, Describe, Sequence Projects
6Resources for Architecture Phase
- Core Team
- Dedicated (f/t or close)
- Data architect / modeler
- Systems analyst (1-1.5)
- Part-time
- Project Leader
- Tech/security architect
- Solutions / apps architect
- DBA
- Business Analyst
- Other Key Resources
- Existing DW teams
- DBA
- Reports
- Portal
- ETL
- IST leaders
- Project planners
- Skills planners
- management
Expected Duration August-December, 2005