GLD experimental hall and detector assembly - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

GLD experimental hall and detector assembly

Description:

Conventional facility (CF) construction schedule shown in Vancouver ... again and lowered to the underground experimental hall by 2500 ton gantry crane ... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 26
Provided by: sug56
Category:

less

Transcript and Presenter's Notes

Title: GLD experimental hall and detector assembly


1
GLD experimental hall and detector assembly
  • Y.Sugimoto
  • KEK
  • 3 Oct. 2006

2
Background
  • Experimental hall, detector assembly procedure,
    and iron yoke design are being re-considered
  • Motivations are
  • Conventional facility (CF) construction schedule
    shown in Vancouver
  • Distance between beam line and a wall increased
    from 12m to 12.5m due to change of crossing angle
    (2mrad20mrad ? 14mrad 14mrad)
  • Information about Air-pad

3
CF schedule
4
CF schedule
  • Underground experimental hall gets ready for
    detector construction at tt04y11m
  • ?It would be impossible to start experiment at
    tt07y
  • Surface assembly hall can be ready at tt03y
  • If detectors are assembled on surface, we could
    get ready for experiment earlier than underground
    assembly by 1.5y or more

5
Surface assembly options
  • Pure CMS-like assembly
  • Detector is segmented into several large pieces (
    lt2000 ton /segment) (5 barrel rings and 3x2
    endcap disks in case of CMS)
  • Detector assembly and test are done on surface,
    then disassembled again and lowered to the
    underground experimental hall by 2500 ton gantry
    crane
  • The large segments are moved by air-pads
    underground (no large crane in the experimental
    hall)
  • Modified CMS-like assembly
  • Detector is segmented into few tens of medium
    size pieces (lt300 ton/segment) Barrel yoke will
    be segmented into 24 (12(f)x2(r)) pieces
  • Detector segments are pre-assembled on surface
    and lowered to the u.g. exp. hall by 300 ton
    movable overhead crane
  • Final assembly and checkout of the detector are
    done underground

6
CMS
Barrel 5 rings Endcap 3 disks x2
7
  • Air pads for CMS

8
Possible drawback of two options
  • Pure CMS
  • Solenoid is supported by the central barrel ring
    ? Thicker cryostat wall ? Larger detector size
  • Gaps between rings ? More leakage field
  • Precision of rings ? ? Uniformity of B-field ?
  • More number of iron slabs and more muon detector
    modules ? Schedule and cost
  • Job duplication on surface and underground ?
    Schedule and cost
  • Larger access shaft (f20m) ? Schedule and cost
  • Modified CMS
  • More jobs underground ? Schedule?
  • Final construction of iron return yoke
  • Solenoid installation and test
  • Muon detector installation
  • 300 ton cranes both on surface and underground ?
    Cost
  • Assembly procedure of heavy (300 ton) pieces ?

9
Impact on detector/hall design
  • Less jobs in the experimental hall than totally
    underground assembly scheme ? Smaller hall size
  • For modified CMS-style assembly, less iron allows
    smaller crane
  • Barrel of the DOD design 8300 ton ? 400 ton
    crane is necessary if divided into 24
    (12(f)x2(r))
  • A new iron yoke design is made 6100 ton ? 300
    ton crane is OK
  • Larger leakage field of the new design is
    compensated by additional coils

10
New iron yoke design
  • Barrel
  • 4.5ltRlt7.2m, 8x25cm1x30cm iron 8x5cm gap
  • Zlt4.45m (35cm shorter than DOD design)
  • Endcap
  • 0.4ltRlt7.2m with pole tip of 0.4ltRlt2.5m
  • 4.5ltZlt7.5m with pole tip of 4.2ltZlt4.5m
  • 10x25cm 1x30cm iron 10x5cm gap
  • 5cm gap between barrel and endcap
  • Leakage field
  • 70 G (44 G for DOD design) at Z10m
  • Compensation coils at Z10m and 12.5m can make it
    lt 50 G for Zgt10m

11
New iron yoke design
  • Air-pad developed for LHC experiments allows
    free movement of heavy detectors
  • If the barrel part of GLD can move both in
    z-direction and x-direction,
  • Experimental hall width can be smaller (32m?25m)
  • Detector can be placed at the center of the hall
    (in z-direction)
  • Because of smaller detector size and slightly
    larger distance between the beam line and a wall,
    endcaps can be open normally (not like a door),
    and consequently, endcap calorimeters can be
    supported by endcaps

12
New iron yoke design
13
New iron yoke design
Self Shielding
14
New iron yoke design
  • Compensation coils for leakage field

L1 Z10m, R1.5m, 6kAT L2 Z12.5m,
R2.45m, 4.5kAT
15
New iron yoke design B-field
  • FEA calculation by COMSOL
  • Axial symmetric 2D calculation
  • Permeability of iron
  • Based on Yamaoka-sans data
  • Slightly modified by hand
  • Saturation magnetization 2.1T
  • Solenoid
  • Coil half length 4.08m
  • Correction coil length 0.65m
  • Field uniformity
  • New requirement dB/Blt4.5x10-4 for Zlt0.5m (D.
    Peterson)

M
H
16
Leakage B-field
  • B field along r0

Without compensation coil
With compensation coils
17
New experimental hall design
  • Assumptions
  • New GLD geometry (R7.2m, Z7.5m)
  • Modified CMS-like assembly scenario
  • Temporary floor of the beam line for the BDS
    pre-commissioning has a width of 3 m
  • Width of concrete shield used for the
    pre-commissioning is 3 m
  • Nothing should be placed at the bottom of the
    access shaft
  • Five large segments (Barrel and 4 halves of
    endcap) should have gt1.5 m clearance around them
    for crane and human access

18
(No Transcript)
19
(No Transcript)
20
(No Transcript)
21
(No Transcript)
22
Electronics huts
23
(No Transcript)
24
Discussion on the hall size
  • Hall width
  • 25m width would be necessary
  • 7.5m (detector) 2.5m (crane access for
    concrete shielding) 2.5m ( 3 cable chains (two
    for endcap halves and one for barrel)) x2 25m
  • Hall height
  • Less than 35m could be possible, depending on the
    shape of the vaulted ceiling
  • This will be studied by CF group of GDE (Concept
    groups will provide information on the height of
    crane hook and crane capacity)

25
  • Cable chains for CMS
Write a Comment
User Comments (0)
About PowerShow.com