TRANSMISSION INFRASTRUCTURE IMPROVEMENTS Current Projects - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

TRANSMISSION INFRASTRUCTURE IMPROVEMENTS Current Projects

Description:

'The Sun Valley Energy Roundtables 2006' November 30 December 1, 2006 ... EPACT provisions. FERC initiatives. 16. Coordination of Generation. and Transmission ... – PowerPoint PPT presentation

Number of Views:66
Avg rating:3.0/5.0
Slides: 18
Provided by: z5789
Category:

less

Transcript and Presenter's Notes

Title: TRANSMISSION INFRASTRUCTURE IMPROVEMENTS Current Projects


1
TRANSMISSIONINFRASTRUCTURE IMPROVEMENTS
Current Projects
Steve WheelerExecutive Vice PresidentArizona
Public Service Company
The Center for the New WestThe Sun Valley
Energy Roundtables 2006November 30 December
1, 2006
2
About APS
A subsidiary of Pinnacle West Capital Corporation
  • Largest electric utility in Arizona
  • Second fastest growing utility in country
  • Peak Control Area load over 7700 MW
  • Over 1 million customers
  • 1 billion Ten-Year In-state transmission
    expansion plan

3
Transmission East vs. West
4
Increasing Transmission Capability
  • OPTIONS
  • Upgrade existing system
  • New conductor technologies
  • New facilities
  • Advanced technologies for control
  • Integrated resource planning

5
Use of New Conductor Technology
  • Re-conductor West Phoenix-Lincoln Street 230kV
    line
  • 3M Aluminum Conductor Composite Reinforced (ACCR)

6
Palo Verde Hub TS5 Raceway Pinnacle Peak
500kV Project
  • New 500 kV system connecting SW Phoenix to NE
    Phoenix
  • Add 1500 MW import capability to Phoenix Area
  • Provide additional export capability for
    generation at Palo Verde Hub
  • Provide voltage support for NE Phoenix Area
  • 0.6B for 110 miles of line and substation
    equipment

7
Palo Verde Hub to Yuma 500kV
  • Provide 2nd 500kV source from Palo Verde Hub to
    Yuma
  • Provide transmission import capability to serve
    rapid load growth in theYuma Area
  • Provide additional export capability for
    generation at the Palo Verde Hub
  • In service date 2012
  • Permitting work underway
  • 300M cost estimate for 115 mile line and
    substation equipment

8
Conceptual TransWest Express ProjectDC Option
9
TransWest Express Project Summary
  • Driven from LSE need
  • Enables renewable wind and advanced clean coal
    technologies
  • Open stakeholder process
  • Transmission and permitting feasibility analysis
    essentially complete
  • Coordinating with Frontier activities

10
TransWest Express Project Timeline
  • 2006 Phase 1 feasibility study
  • 2007-2011 Phase 2 permitting
  • 2012-2015 Phase 3 construction
  • 2015 Phase 4 commercial operation

11
Feasibility Study Conclusions
  • Technically feasible
  • Economics indicate DC or AC/DChybrid
    alternatives
  • Multiple routes viable with minimal impact on
    sensitive environmental areas
  • Existing plans for AZ-CA expansion provide
    increase transfer capability in excess of 3000MW

12
TransWest ExpressCurrent Status
  • Phase 2 Agreement in negotiation
  • Participants
  • APS
  • SRP
  • SCE
  • TEP
  • National Grid
  • Wyoming Infrastructure Authority

13
Phase 2 Work Plan
  • Five year schedule 2007- 2011
  • Estimated cost of approximately 115M
  • Engineering and design
  • Routing
  • Permitting and approvals
  • Outreach and coordination
  • Options on right of way

14
Coordination with Frontier Line Activities
  • APS participant in Frontier Line feasibility
    study
  • TransWest Express one of transmission options in
    Frontier study
  • Frontier economic analysis will include TransWest
    Express
  • Possible participation in TransWest Express by
    Southern California load serving entities

15
Increasing Transmission CapabilityKey
Considerations
  • Resource needs
  • Renewable requirements
  • Resource diversity
  • Financial considerations
  • Business model
  • Siting feasibility
  • EPACT provisions
  • FERC initiatives

16
Coordination of Generationand Transmission
  • Cant invest in one without assuranceof the
    other
  • Timing issues
  • Permitting
  • Construction
  • FERC Standards of Conduct
  • IRPs
  • Regional transmission planning activities

17
Conclusion
  • Transmission expansion remains a daunting
    exercise in engineering, siting, technology,
    economics, and public policy
  • Coordinated planning and cooperation at all
    levels is essential
  • A stout heart is required
Write a Comment
User Comments (0)
About PowerShow.com